Monthly Local Let Maintenance Report For Fort Worth District As Of Jun 08, 2018 Page 5 Of 6

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6315-69-001
Proj IDSUP - 631569001
Work TypeLITTER REMOVAL
 
0.010391997.62262312.4266.9
Work Order09-14-17
Work Began09-15-17
Work Completed
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170236
Totals391997.6232484.70262312.4266.9

CountyJOHNSON
HighwayUS0067
FromJOHNSON COUNTY
ToWITHIN CITY LIMITS
CSJ6315-82-001
Proj IDSUP - 631582001
Work TypeLANDSCAPING MAINTENANCE
 
0.01017700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-17
Work Began06-01-17
Work Completed
Time Computed12-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170231
Totals17700.000.000.000.0

CountyJOHNSON
HighwayFM2280
FromKEENE MAINTENANCE
ToOFFICE
CSJ6315-86-001
Proj IDSUP - 631586001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01025095.007860.0031.3
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged176
Percent Time Used48
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11170231
Totals25095.001910.007860.0031.3

CountyWISE
HighwayUS0081
FromUS DECATUR,OFFICE JACKSBORO OFFICE, OLD
ToAREA OFFICE, JACKSBORO MAINTENANCE YARD
CSJ6315-87-001
Proj IDSUP - 631587001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01062450.0029695.0047.5
Work Order11-03-17
Work Began11-03-17
Work Completed
Time Computed11-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged204
Percent Time Used55
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170231
Totals62450.006990.0029695.0047.5

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN JOHNSON
ToCOUNTY
CSJ6316-02-001
Proj IDRMC - 631602001
Work TypeCLEANING AND SEALING JOINTS & CRACKS
 
0.010205978.00183928.4089.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-30-17
Work Began11-14-17
Work Completed
Time Computed11-06-17
Contract Working Days43
Addl Days Granted0
Working Days Charged17
Percent Time Used39
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170201
Totals205978.000.00183928.4089.2

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToPARKER AND PALO PINTO
CSJ6316-03-001
Proj IDRMC - 631603001
Work TypeSWEEPING AND DEBRIS
 
0.010286745.33183683.4064.0
Work Order10-04-17
Work Began10-04-17
Work Completed
Time Computed10-04-17
Contract Working Days365
Addl Days Granted120
Working Days Charged236
Percent Time Used48
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6316-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170203
Totals286745.3339193.35183683.4064.0

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6316-15-001
Proj IDRMC - 631615001
Work TypeCALL OUT REFLEC PVMT MRKGS & MRKRS
 
0.010256350.0097595.2038.0
Work Order02-27-18
Work Began03-08-18
Work Completed
Time Computed03-05-18
Contract Working Days88
Addl Days Granted0
Working Days Charged7
Percent Time Used7
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170201
Totals256350.0030377.5097595.2038.0

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6316-30-001
Proj IDRMC - 631630001
Work TypeSWEEPING AND DEBRIS REMOVAL JOHNSON CO
 
0.010138385.4042484.5030.7
Work Order02-16-18
Work Began03-05-18
Work Completed
Time Computed02-22-18
Contract Working Days365
Addl Days Granted0
Working Days Charged93
Percent Time Used25
Contractor(s)
DEMENT ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-30-001
TEXAS TMA RENTAL (70.00)
Contract #12170201
Totals138385.409446.0042484.5030.7

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN WISE & JACK COUNTY
ToMAINTENANCE AREAS
CSJ6316-56-001
Proj IDRMC - 631656001
Work TypeTREE & BRUSH TRIMMING AND REMOVAL
 
0.100350500.00244828.5069.8
Work Order10-25-17
Work Began11-02-17
Work Completed
Time Computed11-02-17
Contract Working Days110
Addl Days Granted0
Working Days Charged110
Percent Time Used100
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170201
Totals350500.0079085.00244828.5069.8

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS WITHIN WISE
ToAND JACK CONTIES
CSJ6318-04-001
Proj IDSUP - 631804001
Work TypePICNIC AREA MAINTENANCE
 
0.01056810.0019545.0034.4
Work Order01-04-18
Work Began01-05-18
Work Completed
Time Computed01-05-18
Contract Working Days365
Addl Days Granted0
Working Days Charged141
Percent Time Used38
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6318-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170231
Totals56810.007135.0019545.0034.4

CountySOMERVELL
HighwayUS0067
FromVARIOUS LOCATIONS IN HOO, SOMERVELL
ToAND ERATH COUNTIES
CSJ6318-05-001
Proj IDSUP - 631805001
Work TypePICNIC AREA MAINTENANCE
 
0.010114036.3442287.8437.0
Work Order01-02-18
Work Began01-03-18
Work Completed
Time Computed01-03-18
Contract Working Days365
Addl Days Granted0
Working Days Charged145
Percent Time Used39
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170232
Totals114036.348880.4642287.8437.0

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATION WITHIN PARKER
To& PALO PINTO COUNTIES
CSJ6318-06-001
Proj IDSUP - 631806001
Work TypePICNIC AREA MAINTENANCE
 
0.01077143.2024340.4231.5
Work Order01-15-18
Work Began01-15-18
Work Completed
Time Computed01-15-18
Contract Working Days358
Addl Days Granted0
Working Days Charged131
Percent Time Used36
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180231
Totals77143.209586.7724340.4231.5

CountyPARKER
HighwayIH0020
FromVARIOUS ROADS IN
ToPARKER / PALO PINTO
CSJ6318-28-001
Proj IDRMC - 631828001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
116.000239500.0086550.0036.1
Work Order03-09-18
Work Began03-10-18
Work Completed
Time Computed03-10-18
Contract Working Days137
Addl Days Granted0
Working Days Charged48
Percent Time Used35
Contractor(s)
WESTGATE GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-28-001
DICKEY LANDSCAPE CONTRACTORS, INC. (46.34)
Contract #08170202
Totals239500.0047180.0086550.0036.1

CountyPARKER
HighwayIH0020
FromWEATHERFORD/MINERAL WELLS OFFICES &
ToTO GORDON LOCATION
CSJ6318-54-001
Proj IDSUP - 631854001
Work TypeJANITORIAL & GROUNDS WORK MAINTENANCE
 
0.01061457.9917683.0628.7
Work Order00-00-00
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged114
Percent Time Used31
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180232
Totals61457.994903.1817683.0628.7

CountyERATH
HighwaySH0006
FromFM 847
ToFM 914
CSJ6319-09-001
Proj IDRMC - 631909001
Work TypeEMERGENCY WORK ON SH 6 IN ERATH COUNTY
 
8.1941755117.003798424.58100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-16-17
Work Completed09-20-17
Time Computed06-16-17
Contract Working Days47
Addl Days Granted7
Working Days Charged54
Percent Time Used100
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6319-09-001
DUSTROL, INC. (1.18)
TRP CONSTRUCTION GROUP, LLC (4.41)
CROSS ROADS, L.P. (0.74)
Contract #06170240
Totals1755117.000.003798424.58100.0

CountyERATH
HighwayUS0067
FromEMC US 67 BRIDGE
ToIN ERATH COUNTY
CSJ6320-21-001
Proj IDEMC - 632021001
Work TypeEMC US67 BRIDGE
 
0.010561010.70438565.5878.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-09-17
Work Began10-09-17
Work Completed
Time Computed10-09-17
Contract Working Days32
Addl Days Granted30
Working Days Charged62
Percent Time Used100
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-21-001
STRIPING TECHNOLOGY, L.P. (3.91)
Contract #07170241
Totals561010.700.00438565.5878.1

CountyWISE
HighwayUS0380
FromWISE AND JACK COUNTIES
ToWISE AND JACK COUNTIES
CSJ6322-27-001
Proj IDRMC - 632227001
Work TypeCALL OUT REFL PAVE MARKINGS AND MARKERS
 
0.100278580.110.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180201
Totals278580.110.000.000.0

CountyWISE
HighwayUS0081
FromVARIOUS ROADWAYS WITHIN
ToJACK & WISE COUNTIES
CSJ6324-24-001
Proj IDRMC - 632424001
Work TypeDEBRIS REMOVAL
 
0.10091525.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days304
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6324-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180202
Totals91525.150.000.000.0

CountyTARRANT
HighwayIH0020
FromFORT WORTH DISTRICT
ToSW LOOP 820
CSJ6327-35-001
Proj IDSUP - 632735001
Work TypeJANITORIAL MAINTENANCE
 
0.0102755080.0076530.002.7
Work Order00-00-00
Work Began01-01-18
Work Completed
Time Computed01-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged120
Percent Time Used32
Contractor(s)
TIBH INDUSTRIES, INC.
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6327-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170233
Totals2755080.0019132.5076530.002.7

CountyTARRANT
HighwaySH0010
FromNORTH TARRANT ENGINEERS AND
ToMAINTENANCE OFFICE
CSJ6327-55-001
Proj IDSUP - 632755001
Work TypeJANITORIAL AND GROUNDS MAINTENENACE
 
0.01035320.1612507.3635.4
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed01-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged145
Percent Time Used39
Contractor(s)
TIBH INDUSTRIES, INC.
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6327-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170234
Totals35320.163635.3612507.3635.4