Monthly Local Let Maintenance Report For Fort Worth District As Of Jul 13, 2018 Page 2 Of 6

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER AND PALO PINTO COUNTIES
CSJ6280-89-001
Proj IDRMC - 628089001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.010291850.00583700.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-23-15
Work Began11-30-15
Work Completed08-25-16
Time Computed11-30-15
Contract Working Days150
Addl Days Granted31
Working Days Charged174
Percent Time Used96
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12140206
Totals291850.000.00583700.00100.0

CountyPALO PINTO
HighwayUS0180
FromVARIOUS ROADWAYS WITHIN PARKER
ToAND PALO PINTO COUNTIES
CSJ6280-90-001
Proj IDRMC - 628090001
Work TypeTREE REMOVAL
 
0.010263200.00544180.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-29-15
Work Began07-14-14
Work Completed08-17-16
Time Computed07-06-15
Contract Working Days150
Addl Days Granted89
Working Days Charged199
Percent Time Used83
Contractor(s)
KASPARIAN UNDERGROUND, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6280-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12140205
Totals263200.000.00544180.00100.0

CountyTARRANT
HighwaySH0360
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6281-46-001
Proj IDRMC - 628146001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.100181715.00129677.0071.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-15
Work Began02-17-15
Work Completed
Time Computed02-23-15
Contract Working Days100
Addl Days Granted0
Working Days Charged41
Percent Time Used41
Contractor(s)
SMITH LAWN AND TREE
SUBCONTRACTOR(S) FOR CCSJ: 6281-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12140202
Totals181715.000.00129677.0071.3

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADS WITHIN_SOUTH TARRANT
ToCOUNTY MAINTENENACE SECTION
CSJ6284-39-001
Proj IDRMC - 628439001
Work TypeCALL-OUT REFL PAV MRKS & MRKRS
 
0.010260825.00321595.3599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-15
Work Began08-05-15
Work Completed
Time Computed08-27-15
Contract Working Days102
Addl Days Granted11
Working Days Charged69
Percent Time Used61
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06150205
Totals260825.000.00321595.3599.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6285-32-001
Proj IDRMC - 628532001
Work TypeMAILBOX ASSEMBLIES
 
0.01038500.0041220.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-15
Work Began01-29-16
Work Completed
Time Computed12-21-15
Contract Working Days12
Addl Days Granted0
Working Days Charged5
Percent Time Used41
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6285-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09150201
Totals38500.000.0041220.0099.9

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6286-28-001
Proj IDRMC - 628628001
Work TypeCLEANING & SEALIN JOINTS & CRACKS
 
0.010201132.006222.813.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-16
Work Began01-13-16
Work Completed
Time Computed01-13-16
Contract Working Days38
Addl Days Granted0
Working Days Charged5
Percent Time Used13
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150203
Totals201132.000.006222.813.0

CountyTARRANT
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6286-95-001
Proj IDRMC - 628695001
Work TypeFULL-DEPTH CONCRETE PAVAMENT REPAIR
 
0.010287066.60284543.6099.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-16
Work Began03-14-16
Work Completed
Time Computed03-21-16
Contract Working Days22
Addl Days Granted21
Working Days Charged43
Percent Time Used100
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6286-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150201
Totals287066.600.00284543.6099.1

CountyJOHNSON
HighwayFM0157
FromFM 157 IN
ToJOHNSON COUNTY
CSJ6287-59-001
Proj IDRMC - 628759001
Work TypeCULVERT REPLACEMENT
 
0.010285707.06586342.33100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-13-15
Work Began07-20-15
Work Completed01-17-17
Time Computed07-20-15
Contract Working Days43
Addl Days Granted114
Working Days Charged206
Percent Time Used131
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-59-001
DALLAS LITE AND BARRICADE INC. (9.67)
J & G CONCRETE PRODUCTS (5.50)
STRIPING TECHNOLOGY, L.P. (2.00)
THE TURNER CO. (2.10)
OLDCASTLE PRECAST INC. (BROOKS PRODUCTS) (1.93)
RATLIFF READY MIX (0.00)
APAC-TEXAS, INC. (0.00)
GSI HIGHWAY PRODUCTS (0.00)
GSI HIGHWAY PRODUCTS (2.55)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (11.15)
REED HYDROMULCHING, INC. (1.13)
Contract #05150201
Totals285707.060.00586342.33100.0

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6289-88-001
Proj IDRMC - 628988001
Work TypeROADSIDE MOWING & HERBICIDE
 
0.010262978.88171306.4365.1
Work Order06-05-17
Work Began05-05-16
Work Completed
Time Computed04-14-16
Contract Working Days68
Addl Days Granted58
Working Days Charged106
Percent Time Used84
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6289-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150202
Totals262978.88748.88171306.4365.1

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6291-17-001
Proj IDSUP - 629117001
Work TypeGROUNDS MAINTENANCE
 
0.01063628.1640583.3263.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged299
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6291-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150237
Totals63628.160.0040583.3263.7

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS IN WISE
ToAND JACK COUNTIES
CSJ6291-80-001
Proj IDRMC - 629180001
Work TypeCALL-OUT THERMO
 
0.010234520.00267411.95100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-16
Work Began08-24-16
Work Completed03-16-18
Time Computed09-01-16
Contract Working Days83
Addl Days Granted0
Working Days Charged45
Percent Time Used54
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160203
Totals234520.000.00267411.95100.0

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6291-83-001
Proj IDSUP - 629183001
Work TypeLITTER REMOVAL
 
0.010476530.57430406.0890.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150232
Totals476530.570.00430406.0890.3

CountyHOOD
HighwayUS0377
FromLITTER REMOVAL IN VARIOUS ROADWAYS
ToWITHIN HOOD,SOMERVELL & ERATH COUNTIES
CSJ6291-84-001
Proj IDSUP - 629184001
Work TypeLITTER REMOVAL WITHIN HSE
 
0.010106883.87104604.16100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed08-31-16
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged345
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150231
Totals106883.870.00104604.16100.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITIN PARKER
ToAND PALO PINTO COUNTY
CSJ6291-85-001
Proj IDSUP - 629185001
Work TypeLITTER REMOVAL WITHIN PARKER/PALO PINTO
 
0.010301614.62296084.21100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-15
Work Completed08-31-16
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150235
Totals301614.620.00296084.21100.0

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6291-98-001
Proj IDRMC - 629198001
Work TypeCLEANING/SHAPING DITCHES
 
0.010228500.00661000.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-03-16
Work Began01-20-16
Work Completed
Time Computed02-10-16
Contract Working Days365
Addl Days Granted0
Working Days Charged65
Percent Time Used17
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150204
Totals228500.000.00661000.0099.9

CountyERATH
HighwayUS0377
FromVARIOUS ROADWAYS IN ERATH, HOOD, &
ToSOMERVELL COUNTIES
CSJ6293-93-001
Proj IDRMC - 629393001
Work TypeGUARDRAIL
 
0.010203375.00306717.0099.9
Work Order05-02-17
Work Began04-13-17
Work Completed
Time Computed04-20-17
Contract Working Days365
Addl Days Granted157
Working Days Charged394
Percent Time Used75
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170201
Totals203375.0024750.00306717.0099.9

CountyERATH
HighwayUS0377
FromVARIOUS ROADWAYS IN ERATH, HOOD,
To& SOMERVELL COUNTIES
CSJ6294-01-001
Proj IDRMC - 629401001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.010299500.0044310.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-21-17
Work Began07-07-16
Work Completed12-15-17
Time Computed02-28-17
Contract Working Days100
Addl Days Granted0
Working Days Charged11
Percent Time Used11
Contractor(s)
DIAMOND JK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160207
Totals299500.000.0044310.00100.0

CountyERATH
HighwayUS0377
FromVARIOUS ROADWAYS IN
ToERATH COUNTY
CSJ6294-98-001
Proj IDRMC - 629498001
Work TypeROADSIDE MOWING
 
0.010290282.52290080.52100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began05-23-16
Work Completed01-01-18
Time Computed05-30-16
Contract Working Days74
Addl Days Granted0
Working Days Charged69
Percent Time Used93
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150206
Totals290282.520.00290080.52100.0

CountyHOOD
HighwayUS0377
FromVARIOUS ROADWAYS IN HOOD AND
ToSOMERVELL COUNTIES
CSJ6294-99-001
Proj IDRMC - 629499001
Work TypeROADSIDE MOWING
 
0.010242961.36221040.10100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-16-16
Work Completed01-10-18
Time Computed05-23-16
Contract Working Days64
Addl Days Granted44
Working Days Charged102
Percent Time Used94
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150204
Totals242961.360.00221040.10100.0

CountyWISE
HighwayUS0081
FromWISE & JACK COUNTY
ToMAINTENANCE OFFICES AND YARDS
CSJ6295-54-001
Proj IDSUP - 629554001
Work TypeGROUNDS MAINTENANCE
 
0.01022860.0033210.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-16
Work Began03-20-16
Work Completed
Time Computed03-22-16
Contract Working Days365
Addl Days Granted0
Working Days Charged222
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6295-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150233
Totals22860.000.0033210.0099.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6