Monthly Local Let Maintenance Report For Fort Worth District As Of Aug 16, 2018 Page 1 Of 5

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayFM0156
FromJANITORIAL MAINTENANCE AT
ToSAGINAW MAINTENANCE OFFICE
CSJ6257-39-001
Proj IDSUP - 625739001
Work TypeJANITIORIAL MAINTENANCE
 
0.01010868.0410868.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-02-13
Work Completed
Time Computed07-08-13
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6257-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06130231
Totals10868.040.0010868.0499.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToFORT WORTH DISTRICT
CSJ6259-56-001
Proj IDRMC - 625956001
Work TypeLOOP DETECTOR REPAIR AND/OR REPLACE
 
0.010256748.0010391.60100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-13
Work Began12-20-13
Work Completed04-30-14
Time Computed12-19-13
Contract Working Days365
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07130203
Totals256748.000.0010391.60100.0

CountyTARRANT
HighwaySH0360
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT & JOHNSON COUNTIES
CSJ6261-69-001
Proj IDRMC - 626169001
Work TypeFULL-DEPTH REPAIR OF EXIST. CONC. PAV.
 
0.010289381.09133873.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-14-14
Work Began04-14-14
Work Completed08-05-14
Time Computed04-21-14
Contract Working Days37
Addl Days Granted0
Working Days Charged33
Percent Time Used89
Contractor(s)
OMEGA CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6261-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09130201
Totals289381.090.00133873.00100.0

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS WITHIN
ToWISE & JACK COUNTY
CSJ6263-14-001
Proj IDRMC - 626314001
Work TypeGUARDRAIL INSTALLATION/REPAIR
 
0.01076570.00229914.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-13
Work Began11-11-13
Work Completed12-10-14
Time Computed11-14-13
Contract Working Days365
Addl Days Granted0
Working Days Charged352
Percent Time Used96
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10130201
Totals76570.000.00229914.50100.0

CountyTARRANT
HighwayUS0287
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6263-50-001
Proj IDRMC - 626350001
Work TypeROADSIDE MOWING
 
0.010214872.00114919.20100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-19-14
Work Began05-21-14
Work Completed06-30-15
Time Computed05-26-14
Contract Working Days56
Addl Days Granted0
Working Days Charged38
Percent Time Used67
Contractor(s)
SIGNATURE CONTRACTING SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6263-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12130201
Totals214872.000.00114919.20100.0

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT
CSJ6265-95-001
Proj IDSUP - 626595001
Work TypeROADSIDE MOWING
 
0.010101970.42101970.42100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-05-14
Work Began05-12-14
Work Completed04-30-15
Time Computed05-12-14
Contract Working Days90
Addl Days Granted0
Working Days Charged46
Percent Time Used51
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6265-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140233
Totals101970.420.00101970.42100.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToPARKER, PALO PINTO AND ERATH COUNTY
CSJ6267-65-001
Proj IDRMC - 626765001
Work TypeDEBRIS REMOVAL
 
0.010143325.00211712.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-14
Work Began00-00-00
Work Completed03-30-16
Time Computed06-09-14
Contract Working Days164
Addl Days Granted0
Working Days Charged161
Percent Time Used98
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6267-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140204
Totals143325.000.00211712.50100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS WITHIN
ToNORTH TARRANT COUNTY
CSJ6269-80-001
Proj IDRMC - 626980001
Work TypeFULL-DEPTH REPAIR OF EXIST. CONC. PAV.
 
0.010275530.80411803.13100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-29-14
Work Began06-29-14
Work Completed09-10-14
Time Computed07-06-14
Contract Working Days37
Addl Days Granted16
Working Days Charged34
Percent Time Used64
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140202
Totals275530.800.00411803.13100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS WITHIN
ToNORTH TARRANT COUNTY
CSJ6270-72-001
Proj IDRMC - 627072001
Work TypeCALL-OUT REFLEC. PAV. MRKINGS & MRKS
 
0.010196175.00272457.27100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-14
Work Began10-20-14
Work Completed07-11-16
Time Computed10-23-14
Contract Working Days70
Addl Days Granted0
Working Days Charged44
Percent Time Used62
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05140201
Totals196175.000.00272457.27100.0

CountyERATH
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToERATH, HOOD & SOMERVELL COUNTY
CSJ6272-00-001
Proj IDRMC - 627200001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.010231973.72282544.78100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-21-15
Work Began04-29-15
Work Completed06-08-15
Time Computed04-28-15
Contract Working Days20
Addl Days Granted0
Working Days Charged17
Percent Time Used85
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06140202
Totals231973.720.00282544.78100.0

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE OFFICE
ToAT WAGGONMON STREET
CSJ6272-01-001
Proj IDSUP - 627201001
Work TypeJANITORIAL MAINTENANCE
 
0.0107822.927822.92100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-14
Work Began05-01-14
Work Completed04-30-15
Time Computed05-08-14
Contract Working Days365
Addl Days Granted0
Working Days Charged300
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6272-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140231
Totals7822.920.007822.92100.0

CountyTARRANT
HighwayIH0820
FromJANITORIAL MAINTENANCE @
ToDISTRICT COMPLEX
CSJ6272-37-001
Proj IDSUP - 627237001
Work TypeJANITORIAL MAINTENANCE
 
0.010156163.46216306.21100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-02-14
Work Completed09-30-15
Time Computed00-00-00
Contract Working Days365
Addl Days Granted184
Working Days Charged489
Percent Time Used89
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6272-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140232
Totals156163.460.00216306.21100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS WITHIN
ToNORTH TARRANT COUNTY
CSJ6272-40-001
Proj IDRMC - 627240001
Work TypeREFLECTORIZED PAV.MARKINGS & MARKERS
 
0.010351001.50350490.17100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-13-15
Work Completed02-14-16
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged17
Percent Time Used100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06150211
Totals351001.500.00350490.17100.0

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN SOUTH TARRANT,
ToPARKER, & JOHNSON COUNTIES
CSJ6273-53-001
Proj IDRMC - 627353001
Work TypeCLEANING & SEALING JOINTS & CRACKS
 
0.010195507.70240868.5199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began00-00-00
Work Completed
Time Computed01-12-15
Contract Working Days37
Addl Days Granted0
Working Days Charged25
Percent Time Used67
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11140206
Totals195507.700.00240868.5199.9

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6277-91-001
Proj IDSUP - 627791001
Work TypeGROUNDS MAINTENANCE
 
0.01050990.3439344.94100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed07-31-15
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09140231
Totals50990.340.0039344.94100.0

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE OFFICE
ToWAGGOMAN STREET
CSJ6277-97-001
Proj IDSUP - 627797001
Work TypeJANITORIAL MAINTENANCE
 
0.0108253.488253.48100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-15
Work Completed04-30-16
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged337
Percent Time Used92
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04150232
Totals8253.480.008253.48100.0

CountyTARRANT
HighwaySH0360
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6281-46-001
Proj IDRMC - 628146001
Work TypeTREE & BRUSH TRIMMING/REMOVAL
 
0.100181715.00129677.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-15
Work Began02-17-15
Work Completed03-15-16
Time Computed02-23-15
Contract Working Days100
Addl Days Granted0
Working Days Charged41
Percent Time Used41
Contractor(s)
SMITH LAWN AND TREE
SUBCONTRACTOR(S) FOR CCSJ: 6281-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12140202
Totals181715.000.00129677.00100.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADS WITHIN_SOUTH TARRANT
ToCOUNTY MAINTENENACE SECTION
CSJ6284-39-001
Proj IDRMC - 628439001
Work TypeCALL-OUT REFL PAV MRKS & MRKRS
 
0.010260825.00321595.3599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-15
Work Began08-05-15
Work Completed
Time Computed08-27-15
Contract Working Days102
Addl Days Granted11
Working Days Charged69
Percent Time Used61
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6284-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06150205
Totals260825.000.00321595.3599.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6285-32-001
Proj IDRMC - 628532001
Work TypeMAILBOX ASSEMBLIES
 
0.01038500.0041220.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-15
Work Began01-29-16
Work Completed12-30-15
Time Computed12-21-15
Contract Working Days12
Addl Days Granted0
Working Days Charged5
Percent Time Used41
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6285-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09150201
Totals38500.000.0041220.00100.0

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6286-28-001
Proj IDRMC - 628628001
Work TypeCLEANING & SEALIN JOINTS & CRACKS
 
0.010201132.006222.813.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-16
Work Began01-13-16
Work Completed
Time Computed01-13-16
Contract Working Days38
Addl Days Granted0
Working Days Charged5
Percent Time Used13
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150203
Totals201132.000.006222.813.0

page 1 | page 2 | page 3 | page 4 | page 5