Monthly State Let Construction Report For Fort Worth District As Of Jun 08, 2018 Page 4 Of 5

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyERATH
HighwayVA
FromTARLETON ST
ToNEAR FM 8
CSJ0902-49-068
Proj IDSTP 2014(119)TE
Work TypeGR, BS, DR, STRUCTURE AND PAVEMENT
 
0.9272150084.201326865.5661.7
Work Order06-14-17
Work Began08-14-17
Work Completed
Time Computed07-15-17
Contract Working Days180
Addl Days Granted0
Working Days Charged159
Percent Time Used88
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0902-49-068
STORM WATER MANAGEMENT, INC. (0.76)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (19.06)
STRIPE-A-ZONE, INC. (0.51)
TEXAS ALTERNATIVE GRASSER, INC. (0.22)
LUZ LERMA CONSTRUCTION, INC. (9.53)
Contract #08163051
Totals2150084.20344940.001326865.5661.7

CountyTARRANT
HighwayVA
FromFM 156 AND HURLEY STREET
ToFM 156 AND SCHOOLHOUSE
CSJ0902-90-045
Proj IDSTP 1702(004)TAPS
Work TypeGR, BS, DR, STR, PAV
 
1.4201141382.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days171
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183051
Totals1141382.100.000.000.0

CountyTARRANT
HighwayCS
FromFOREST HILL DR. AT TRIB. OF VILLAGE
ToCREEK IN FOREST HILL
CSJ0902-90-067
Proj IDBR 2006(543)
Work TypeREPLACE BRIDGES AND APPROACHES
 
0.1002474990.242390138.9697.2
Work Order01-10-17
Work Began02-27-17
Work Completed
Time Computed02-10-17
Contract Working Days192
Addl Days Granted60
Working Days Charged273
Percent Time Used108
Contractor(s)
MCMAHON CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-067
ACTION COMMERCIAL SERVICES, L.L.C. (0.66)
FORTSON CONTRACTING, INC. (0.24)
INLET STRUCTURE SPECIALTIES LTD. (2.67)
JESUS MORALES TRUCKING (0.00)
KLP COMMERCIAL, LLC (3.09)
LUZ TRUCKING, INC. (0.00)
STOIC CIVIL CONSTRUCTION, INC. (6.78)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.08)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.87)
FOUNDATION DRILLERS, INC. (1.78)
AAA DRILLING FOUNDATION CO., INC. (0.26)
EL CALA CONSTRUCTION LLC (0.64)
Contract #11163010
Totals2474990.24283850.712390138.9697.2

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToON DFW CONNECTOR
CSJ0902-90-071
Proj IDC 902-90-71
Work TypeILLUMINATION REFURBISHMENT
 
0.1002906756.940.000.0
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed10-22-17
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173209
Totals2906756.940.000.000.0

CountyTARRANT
HighwayIH 30
FromWB IH30 COL DIST FROM UNIVERISTY DR
ToOVER WB IH30 EXIT RAMP TO MONTGOMER
CSJ1068-01-216
Proj IDBR 1702(737)
Work TypeGR, BS, DR, PAV
 
0.130997337.74701470.7770.3
Work Order09-14-17
Work Began02-05-18
Work Completed
Time Computed10-15-17
Contract Working Days128
Addl Days Granted0
Working Days Charged80
Percent Time Used62
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 1068-01-216
T & R EXCAVATION, INC. (5.47)
CROSS ROADS, L.P. (1.38)
PENHALL COMPANY (0.30)
S & S BRIDGE PAINTING, INC. (20.10)
TOTAL HIGHWAY MAINTENANCE, LLC (1.19)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.81)
DFW SERVICES, LLC (3.06)
FORTSON CONTRACTING, INC. (2.88)
TEXOP CONSTRUCTION (0.56)
PEACHTREE CONSTRUCTION, LTD. (2.38)
GIBSON & ASSOCIATES, INC. (0.80)
Contract #08173018
Totals997337.74111212.50701470.7770.3

CountyTARRANT
HighwayIH 30
From1.0 MI W OF SH 360
ToGREAT SOUTHWEST PKWY
CSJ1068-02-076
Proj IDNH 2016(183)
Work TypeGR STRS & SURF
 
2.933228440784.53116389010.6650.9
CountyTARRANT
HighwayIH 30
From1.0 MI W OF SH 360
ToGREAT SOUTHWEST PKWY
CSJ1068-02-123
Proj IDNH 2007(893)
Work TypeROW ACQ, RELOC & UTILITIES
 
0.0014741104.003733803.6078.7
Work Order12-09-15
Work Began01-19-16
Work Completed
Time Computed01-19-16
Contract Working Days1,150
Addl Days Granted249
Working Days Charged723
Percent Time Used51
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-076
USA SWPPP INSPECTIONS, INC. (0.99)
THELIN RECYCLING COMPANY, L.P. (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06)
SCOTT DERR PAINTING CO, LLC (0.21)
BROOKLYN SWEEPS (0.35)
F A BROWN"S CONSTRUCTION, LLC (0.67)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (5.72)
W.O.E. CONSTRUCTION (3.34)
BUYERS BARRICADES, INC. (0.00)
ROYAL REBAR (5.43)
ARK CONTRACTING SERVICES, LLC (2.29)
INTEGRATED ROADWAY SERVICES, INC. (4.41)
TOTAL HIGHWAY MAINTENANCE, LLC (0.59)
NORTH TEXAS CONTRACTING, INC. (7.30)
MIKE ALBERT, INC. (0.13)
1 PRIORITY ENVIRONMENTAL SERVICES, INC. (0.40)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.07)
BORE COMPANY, LLC (0.29)
EXCEL 4 CONSTRUCTION, LLC (0.09)
JAGOE-PUBLIC COMPANY (0.13)
UNDER CONSTRUCTION INC. (0.07)
FOUNDATION DRILLERS, INC. (0.03)
MORNING STAR TREE SERVICE (0.00)
Contract #11153231
Totals233181888.532536125.43120122814.2651.5

CountyTARRANT
HighwayIH 30
FromIH 35W
ToIH 820
CSJ1068-02-146
Proj IDCM 2018(455)
Work TypeITS FIBER, EQUIP, SATELLITE BLDG
 
7.1952498951.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-03-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-146
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183215
Totals2498951.080.000.000.0

CountyTARRANT
HighwaySS 341
FromWHITE SETTLEMENT ROAD
ToDOWNE DRIVE
CSJ1068-03-022
Proj IDNH 1602(327)
Work TypeLANDSCAPING
 
1.001282864.35254095.4089.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-16
Work Began12-12-16
Work Completed
Time Computed10-17-16
Contract Working Days64
Addl Days Granted0
Working Days Charged64
Percent Time Used100
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-03-022
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.22)
Contract #08163248
Totals282864.350.00254095.4089.8

CountyWISE
HighwayFM 920
FromSOUTH OF TRINITY RIVER
ToSOUTH OF BOONSVILLE
CSJ1179-01-043
Proj IDSTP 1802(189)
Work TypeBASE RPR, OVERLAY, PAVMT MARK
 
10.9662881535.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1179-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183247
Totals2881535.480.000.000.0

CountyPARKER
HighwayFM 2552
FromUS 180
ToIH 20
CSJ1179-03-010
Proj IDSTP 2018(748)
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
2.5271285250.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1179-03-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183227
Totals1285250.030.000.000.0

CountyWISE
HighwayFM 2264
FromUS 287/81
ToCR 4431
CSJ1310-03-026
Proj IDC 1310-3-26
Work TypeGRADING,BASE,DRAINAGE,STRUCTURE,PAV
 
7.2447015561.582147481.0930.6
Work Order10-09-17
Work Began11-06-17
Work Completed
Time Computed11-06-17
Contract Working Days406
Addl Days Granted0
Working Days Charged135
Percent Time Used33
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1310-03-026
DUSTROL, INC. (0.53)
SOUTHERN CROSS CONTRACTORS, LLC (1.71)
MARCOM"S MOWING SERVICE, LLC (0.50)
TOTAL HIGHWAY MAINTENANCE, LLC (1.63)
WOLFE CONSTRUCTION GROUP, INC. (1.90)
BUYERS BARRICADES, INC. (0.47)
Contract #07173044
Totals7015561.58378194.202147481.0930.6

CountyTARRANT
HighwayFM 1187
FromEAST OF FM 1902
ToBF 1187C
CSJ1330-01-062
Proj IDNH 2017(892)
Work TypeHMAC OVERLAY
 
2.5565144732.723140160.3261.1
Work Order04-24-17
Work Began09-05-17
Work Completed
Time Computed05-25-17
Contract Working Days299
Addl Days Granted163
Working Days Charged143
Percent Time Used105
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-01-062
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.35)
TEXOP CONSTRUCTION (6.92)
TOTAL HIGHWAY MAINTENANCE, LLC (0.70)
SOUTHERN CROSS CONTRACTORS, LLC (0.38)
STRIPING TECHNOLOGY, L.P. (1.39)
O. TREVINO CONSTRUCTION, LLC (3.61)
W.O.E. CONSTRUCTION (0.05)
BRENDA PRICE TRUCKING (0.32)
DUSTROL, INC. (0.09)
Contract #03173212
Totals5144732.7296700.623140160.3261.1

CountyTARRANT
HighwayFM 1187
FromUS-377
ToFM-1902
CSJ1330-01-063
Proj IDNH 2018(572)
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
7.2722137400.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1330-01-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183214
Totals2137400.150.000.000.0

CountyTARRANT
HighwayFM 1187
FromMCCART AVE
ToMAIN ST
CSJ1330-03-003
Proj IDSTP 2017(737)
Work TypeLANDSCAPING
 
3.000540000.00484170.5189.6
Work Order03-16-17
Work Began05-24-17
Work Completed
Time Computed04-16-17
Contract Working Days104
Addl Days Granted0
Working Days Charged55
Percent Time Used52
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-03-003
DALLAS LITE AND BARRICADE INC. (1.88)
Contract #02173036
Totals540000.002262.50484170.5189.6

CountyPARKER
HighwayFM 1189
FromYOUNG BEND ROAD
ToHOOD COUNTY LINE
CSJ1468-01-024
Proj IDSTP 1402(036)
Work TypeGR,STR,FLX BS, SC, MBGF,SIGN,PVT MK
 
9.0586481549.556871499.0799.9
Work Order10-07-14
Work Began01-25-16
Work Completed
Time Computed10-23-14
Contract Working Days253
Addl Days Granted163
Working Days Charged342
Percent Time Used82
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1468-01-024
RAMBO CONTRACTING, INC. (4.87)
TEXAS ALTERNATIVE GRASSER, INC. (0.76)
PEACHTREE CONSTRUCTION, LTD. (19.95)
CHEROKEE SERVICES (0.03)
FOUNDATION DRILLERS, INC. (0.65)
WEST TEXAS RUMBLE STRIP (0.05)
MARCOM"S MOWING SERVICE, LLC (0.87)
D. I. J. CONSTRUCTION, INC. (1.69)
FORTSON CONTRACTING, INC. (0.49)
Contract #08143043
Totals6481549.5528572.006871499.0799.9

CountyHOOD
HighwayFM 167
FromFM 4
To3.712 MILES SOUTH OF FM 4
CSJ1513-01-019
Proj IDSTP 2017(738)HES
Work TypeSFTY TRT FIXED OBJECTS & PVD SHLDRS
 
3.7122616562.961811834.5469.2
Work Order06-14-17
Work Began08-21-17
Work Completed
Time Computed07-15-17
Contract Working Days187
Addl Days Granted0
Working Days Charged147
Percent Time Used78
Contractor(s)
BRETT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1513-01-019
NORTH EASTERN PAVERS (21.65)
LUZ LERMA CONSTRUCTION, INC. (16.06)
DUSTROL, INC. (0.68)
Contract #05173220
Totals2616562.96331682.601811834.5469.2

CountyJOHNSON
HighwayFM 916
FromSH 171
ToFM 4
CSJ1599-02-014
Proj IDSTP 1402(037)HES
Work TypeGRADING, BASE AND PAVEMENT
 
12.8426925133.468181786.4999.9
Work Order09-30-14
Work Began09-02-15
Work Completed
Time Computed10-16-14
Contract Working Days201
Addl Days Granted86
Working Days Charged421
Percent Time Used146
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1599-02-014
STRIPING TECHNOLOGY, L.P. (0.77)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
RAMBO CONTRACTING, INC. (7.05)
FARR FOUNDATION, INC. (2.15)
PEACHTREE CONSTRUCTION, LTD. (21.42)
FORTSON CONTRACTING, INC. (1.19)
TEXAS ALTERNATIVE GRASSER, INC. (0.23)
Contract #08143036
Totals6925133.460.008181786.4999.9

CountyPARKER
HighwayFM 1884
FromAT W BB FIELDER DR
To.
CSJ1601-02-032
Proj IDCC 1601-2-32
Work TypeINSTALL OF TRAFFIC ACTUATED SIGNAL
 
0.001105020.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SIGNAL SERVICES GROUP INC.
SUBCONTRACTOR(S) FOR CCSJ: 1601-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183038
Totals105020.850.000.000.0

CountyTARRANT
HighwayFM 1709
FromSTONE BRIDGE LN
ToUS 377
CSJ1603-03-040
Proj IDC 1603-3-40
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
3.8612474193.460.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1603-03-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183050
Totals2474193.460.000.000.0

CountyTARRANT
HighwayFM 1938
From0.2 MILE SOUTH OF FM 1709
ToRANDOL MILL RD/WESTLAKE C/L
CSJ1978-01-050
Proj IDSTP 1402(039)MM
Work TypeGR, BS, DR, STRUCTURES & PAVEMENT
 
1.74320575236.8719914639.4096.7
Work Order01-16-15
Work Began03-23-15
Work Completed
Time Computed02-01-15
Contract Working Days554
Addl Days Granted373
Working Days Charged781
Percent Time Used84
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-050
DALLAS LITE AND BARRICADE INC. (0.38)
GJ SEEDING, LLC (0.59)
THELIN RECYCLING COMPANY, L.P. (0.25)
AUSTCO, INC. (0.05)
NORTH TEXAS CONTRACTING, INC. (35.34)
LIRA ELECTRIC (2.63)
FARR FOUNDATION, INC. (0.60)
BREDA COMPANY, INC. (0.50)
W.O.E. CONSTRUCTION (9.26)
TEXAS SHAFTS, INC. (0.76)
CROSSROADS DECORATIVE PAVEMENT (0.09)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.75)
SCOTT DERR PAINTING CO, LLC (0.06)
TRP CONSTRUCTION GROUP, LLC (0.67)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.69)
A & A CONSTRUCTION (0.06)
MARCOM"S MOWING SERVICE, LLC (0.32)
BRENDA PRICE TRUCKING (0.68)
INLET STRUCTURE SPECIALTIES LTD. (3.12)
JM MATERIALS, INC. (0.50)
KLP COMMERCIAL, LLC (8.05)
TEX OP CONSTRUCTION, LP (0.41)
VENEGAS MASONRY (0.43)
BIG DOG DRILLING, LLC (0.18)
MURRAY-WARD CONTRACTING (0.03)
S & W FOUNDATION CONTRACTORS, INC. (0.16)
Contract #08143005
Totals20575236.87178815.1019914639.4096.7

page 1 | page 2 | page 3 | page 4 | page 5