Monthly State Let Construction Report For Fort Worth District As Of May 10, 2018 Page 1 Of 5

Last Update: Thursday, May 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPARKER
HighwayIH 20
From450 FT WEST OF FM 5
To550 FT EAST OF FM 5
CSJ0008-03-089
Proj IDNH 1702(087)
Work TypeGRADING, PAVEMENT, STRIPING, & SIGN
 
0.1893921685.6177223.241.9
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed10-22-17
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173237
Totals3921685.610.0077223.241.9

CountyPARKER
HighwayIH 20
FromFM 1187
ToIH 30
CSJ0008-03-107
Proj IDNH 2018(537)
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
3.4352047763.190.000.0
Work Order03-12-18
Work Began00-00-00
Work Completed
Time Computed04-12-18
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-107
TOTAL HIGHWAY MAINTENANCE, LLC (0.85)
VANN/ELLI, INC. (2.25)
O. TREVINO CONSTRUCTION, LLC (6.20)
W.O.E. CONSTRUCTION (0.35)
TRP CONSTRUCTION GROUP, LLC (1.64)
Contract #02183217
Totals2047763.190.000.000.0

CountyPARKER
HighwayUS 180
FromJACK BORDEN WAY
ToLAKESHORE DRIVE
CSJ0008-03-116
Proj IDSTP 2018(744)
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
6.2024502728.590.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183028
Totals4502728.590.000.000.0

CountyTARRANT
HighwaySH 180
FromWEST OF RIVERSIDE DRIVE
ToTIERNEY ROAD
CSJ0008-05-027
Proj IDC 8-5-27
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
3.5354223908.260.000.0
CountyTARRANT
HighwaySH 180
FromTIERNEY RD
ToLOUISE ST
CSJ0008-06-051
Proj IDC 8-6-51
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
1.3681609857.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-05-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183247
Totals5833765.360.000.000.0

CountyPARKER
HighwayFM 5
FromAUTUMNWOOD DR
ToVILLAGE PARKWAY
CSJ0008-09-035
Proj IDSTP 2016(350)TP
Work TypeGR, BS, DR, PAV
 
0.400417195.94370414.2988.7
CountyPARKER
HighwayVA
FromVARIOUS LOCATIONS ALONG WEST SIDE
ToOF FM 5 AND FM 1187 IN ALEDO
CSJ0902-38-124
Proj IDSTP 2017(448)TAPS
Work TypeGR, BS, DR, STR, PAV
 
0.600568660.55370947.6172.8
Work Order06-14-17
Work Began08-14-17
Work Completed
Time Computed07-15-17
Contract Working Days86
Addl Days Granted0
Working Days Charged157
Percent Time Used182
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-09-035
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.41)
WOLFE CONSTRUCTION GROUP, INC. (1.58)
COWBOY TRUCKING (2.03)
DURABLE SPECIALTIES, INC. (1.81)
Contract #05173217
Totals985856.4916783.75741361.9079.5

CountyPARKER
HighwayFM 5
From6 MILES WEST OF FM 1187
ToNORTH OF FM 1187
CSJ0008-09-036
Proj IDC 8-9-36
Work TypeBASE RPR, OVERLAY, PAVMENT MARK
 
6.1652939418.330.000.0
CountyPARKER
HighwayFM 5
FromIH 20
To4.8 MILES SOUTH OF IH 20
CSJ1469-01-019
Proj IDC 1469-1-19
Work TypeBASE RPR, OVERLAY, PAVMT MARK
 
4.8592072892.830.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-09-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183242
Totals5012311.160.000.000.0

CountyTARRANT
HighwayIH 20
FromWESTLAKE DR.
ToWEST OF SOUTH DR.
CSJ0008-12-090
Proj IDNH 1602(168)
Work TypeLANDSCAPE
 
0.17688581.6587243.9298.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-03-16
Work Began09-12-16
Work Completed
Time Computed08-29-16
Contract Working Days27
Addl Days Granted0
Working Days Charged11
Percent Time Used40
Contractor(s)
LANDSTAR GROUP
SUBCONTRACTOR(S) FOR CCSJ: 0008-12-090
GREEN HILLS LANDSCAPING AND CONSTRUCTION CO. (57.03)
Contract #06163227
Totals88581.650.0087243.9298.4

CountyTARRANT
HighwayIH 820 ETC
FromSH 121/SH 183 INTERCHANGE
ToRANDOL MILL ROAD
CSJ0008-13-221
Proj IDNH 2018(321)
Work TypeGR,DR,BS,STR,PAV,ITS,SGNL,ILLUM&SGN
 
8.944173724094.740.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,126
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-221
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173001
Totals173724094.740.000.000.0

CountyTARRANT
HighwayIH 20
From.62 MI W OF BU 287P
To.01 M N OF IH 820
CSJ0008-13-231
Proj IDSTP 2016(994)HES
Work TypeCONVERT MEDIAN BARRIER
 
0.7951187693.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed03-10-17
Contract Working Days159
Addl Days Granted0
Working Days Charged67
Percent Time Used42
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-231
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163044
Totals1187693.000.000.000.0

CountyTARRANT
HighwayIH 820
FromWESTPOINT BOULEVARD
ToLAKE WORTH BRIDGE
CSJ0008-15-046
Proj IDNH 2018(452)
Work TypeDIAMOND GRIND,MILL,OVERLAY,SC,PAV
 
5.7583231503.760.000.0
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-19-18
Contract Working Days128
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIAMOND CORING COMPANY, INC
SUBCONTRACTOR(S) FOR CCSJ: 0008-15-046
PEACHTREE CONSTRUCTION, LTD. (13.34)
ALAMO BRIDGE AND ROAD, LLC (1.64)
O. TREVINO CONSTRUCTION, LLC (10.18)
DALLAS LITE AND BARRICADE INC. (1.52)
DIAMOND SURFACE, INC. (0.32)
DUSTROL, INC. (0.14)
W.O.E. CONSTRUCTION (1.16)
BRENDA PRICE TRUCKING (0.06)
DFW MATERIALS LP (0.00)
MOBILE ENTERPRISES, INC. (0.48)
GJ SEEDING, LLC (0.16)
Contract #01183229
Totals3231503.760.000.000.0

CountyTARRANT
HighwayIH 820
From.3 MILES N OF TEAM RANCH ROAD
To1.3 MILES S OF TEAM RANCH ROAD
CSJ0008-15-050
Proj IDC 8-15-50
Work TypeREPLACE WIRE/CONDUIT
 
2.900485156.990.000.0
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed10-22-17
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-15-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173219
Totals485156.990.000.000.0

CountyTARRANT
HighwayIH 20
FromAT IH 20
ToON BRYANT IRVIN ROAD
CSJ0008-16-036
Proj IDSTP 1502(095)MM
Work TypeGR, LIM TRT, HMA, PCCP, BRG, PAV MK
 
0.2203864789.852210796.2257.2
Work Order07-24-15
Work Began11-18-16
Work Completed
Time Computed08-24-15
Contract Working Days363
Addl Days Granted0
Working Days Charged350
Percent Time Used96
Contractor(s)
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0008-16-036
FORTSON CONTRACTING, INC. (0.38)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC. (0.20)
FOUNDATION DRILLERS, INC. (3.47)
DALLAS LIGHT & BARRICADES (1.52)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (9.95)
ACU CONSTRUCTION LLC (0.16)
STRIPING TECHNOLOGY, L.P. (1.15)
BOWMAN ENGINEERING & CONSULTING, INC (0.11)
DFW REBAR, INC. (0.89)
JOHNSON BROS. CORPORATION (104.03)
DALLAS LITE AND BARRICADE INC. (1.75)
BEAN ELECTRICAL, INC. (11.86)
W. W. FOUNDATION DRILLING, LTD. (2.16)
C & S UTILITY CONTRACTORS, INC. (0.29)
AAA UTILITY CONTRACTORS, INC. (0.18)
Contract #05153244
Totals3864789.85308335.052210796.2257.2

CountyTARRANT
HighwayIH 35W
FromON MCPHERSON
ToAT IH 35W
CSJ0014-02-049
Proj IDSTP 1602(429)MM
Work TypeGR, DR, STRUC, AND PAVEMENT
 
0.1006093665.755595876.3992.5
Work Order11-22-16
Work Began01-19-17
Work Completed
Time Computed12-23-16
Contract Working Days278
Addl Days Granted0
Working Days Charged319
Percent Time Used114
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-049
BUYERS BARRICADES, INC. (0.63)
COWBOY TRUCKING (1.20)
FORTSON CONTRACTING, INC. (0.82)
GJ SEEDING, LLC (0.54)
NORTH TEXAS CONTRACTING, INC. (22.97)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.36)
STAR OPERATIONS, INC. (7.81)
STRIPE-A-ZONE, INC. (0.46)
WOLFE CONSTRUCTION GROUP, INC. (0.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.18)
W.O.E. CONSTRUCTION (0.08)
CIP CONCRETE, LLC (0.22)
MCL CONTRACTING, LLC (0.27)
V.C. HUFF, L.L.C. (4.01)
Contract #08163039
Totals6093665.75208872.075595876.3992.5

CountyTARRANT
HighwayIH 35W
FromIH 20
ToSH 174
CSJ0014-02-051
Proj IDCM 2018(453)
Work TypeITS FIBER AND EQUIPMENT
 
7.8311657422.770.000.0
CountyJOHNSON
HighwaySH 174
FromIH 35W
ToWICKER HILL DRIVE
CSJ0019-01-145
Proj IDNH 2018(498)
Work TypeINSTALL ITS FIBER & EQUIPMENT
 
4.211377160.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days171
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183009
Totals2034583.750.000.000.0

CountyJOHNSON
HighwayIH 35W
FromCR 604
ToTARRANT C/L
CSJ0014-03-095
Proj IDNH 2018(892)
Work TypeCONC PAV RPR, MILL, OVERLAY, PAVMT
 
9.35110321476.860.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days235
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-03-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183232
Totals10321476.860.000.000.0

CountyJOHNSON
HighwayIH 35W
From0.391 MI S OF FM 917
To1.672 MI N OF FM 917
CSJ0014-03-096
Proj IDSTP 2018(893)HES
Work TypeSAFETY LIGHTING
 
2.063459534.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-03-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183025
Totals459534.390.000.000.0

CountyTARRANT
HighwayIH 35W
FromIH 820
ToUS 81/287 SPLIT
CSJ0014-16-255
Proj IDIM 0355(151)
Work TypeGR, BSE, DR, SURF & SIGN
 
3.580120205602.75119098968.1999.9
CountyTARRANT
HighwayIH 35W
FromIH 820
ToUS 81/287_SPLIT
CSJ0014-16-267
Proj IDNH 2012(657)
Work TypeROW ACQ, RELOC ASSIT, UTILITY ADJ
 
2.7353080289.852623831.2585.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-12
Work Began04-29-13
Work Completed
Time Computed04-29-13
Contract Working Days847
Addl Days Granted0
Working Days Charged1,427
Percent Time Used168
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0014-16-255
JACKSON CONSTRUCTION, LTD. (2.32)
STRIPING TECHNOLOGY, L.P. (0.53)
USA SWPPP INSPECTIONS, INC. (0.39)
C.B. SERVICES, INC. (0.94)
MAVERICK PUMP SERVICES, LLC (0.04)
W.O.E. CONSTRUCTION (0.04)
MICA CORPORATION (5.31)
COWBELL TRAFFIC SERVICES, INC. (0.01)
CROSSROADS, L.P. (0.09)
FORTSON CONTRACTING, INC. (0.38)
HOUSTON SAWING & DRILLING (0.02)
FOUNDATION DRILLERS, INC. (1.60)
GREAT WESTERN ERECTORS (0.04)
LINDAMOOD DEMOLITION, INC. (0.23)
FARR FOUNDATION, INC. (1.86)
DURABLE SPECIALTIES, INC. (0.36)
NORTH TEXAS BOMANITE, INC. (0.17)
ANTIGO CONSTRUCTION, INC. (0.15)
CEN CONCRETE CONSTRUCTION COMPANY, INC. (0.54)
THELIN RECYCLING COMPANY, L.P. (0.02)
TEX OP CONSTRUCTION, LP (0.33)
BREDA COMPANY, INC. (0.39)
BRENDA PRICE TRUCKING (0.00)
CHOCTAW ERECTORS, INC. (4.52)
CLEANSERVE, INC. (0.07)
DANRIDGE CONSTRUCTION, LLC. (0.01)
SCOTT DERR PAINTING CO, LLC (0.28)
MASTERPIECE GRINDING & GROOVING, LLC (0.00)
INDUS CONSTRUCTION, L.P. (0.02)
MENDEZ EXCAVATION (0.03)
WEBBER BARRIER SERVICES, LLC. (4.34)
DCCS, LLC (2.62)
RAMBO CONTRACTING, INC. (0.06)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.06)
ACTION CONSTRUCTORS (0.39)
CENTRAL NORTH CONSTRUCTION, LLC (0.07)
O. TREVINO CONSTRUCTION, LLC (0.12)
JSS BORI GROUP, LLC (0.05)
SOUTHWEST CONSTRUCTION SERVICES (0.01)
COMEN ENTERPRISE LLC (0.01)
SUPERIOR MATERIALS (0.00)
HYDRO-CON, LLC (0.00)
BCAC UNDERGROUND, LLC (0.00)
Contract #09123201
Totals123285892.600.00121722799.4499.9

CountyJOHNSON
HighwaySH 174
FromSOUTH OF FM 731
ToPHILLIPS DRIVE SOUTH OF JOSHUA
CSJ0019-01-144
Proj IDNH 2016(741)
Work TypeMILL AND OVERLAY
 
6.1003929910.033950568.0999.9
Work Order05-10-16
Work Began11-04-16
Work Completed
Time Computed07-09-16
Contract Working Days213
Addl Days Granted1
Working Days Charged211
Percent Time Used98
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-144
TEXOP CONSTRUCTION (16.47)
TRP CONSTRUCTION GROUP, LLC (1.92)
RICE ENVIRONMENTAL SERVICES (1.60)
MICA CORPORATION (5.27)
CROSSROADS, L.P. (1.00)
WESTHILL CONSTRUCTION, INC. (1.92)
TORRES TRUCKINGS (3.00)
DURABLE SPECIALTIES, INC. (4.78)
Contract #02163219
Totals3929910.031640.003950568.0999.9

CountyERATH
HighwayUS 67
FromUS-281
ToFM-988
CSJ0079-05-054
Proj IDNH 2017(889)
Work TypeMILL AND OVERLAY AND SIGNAL WORK
 
3.8203129743.251831290.6559.4
CountyERATH
HighwayUS 67
FromUS 377
ToFM 913
CSJ0259-01-033
Proj IDNH 2017(889)
Work TypeOVERLAY ROADWAY
 
7.4041525980.44658.000.0
Work Order04-12-17
Work Began08-28-17
Work Completed
Time Computed07-12-17
Contract Working Days76
Addl Days Granted0
Working Days Charged107
Percent Time Used140
Contractor(s)
IOC COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0079-05-054
DURABLE SPECIALTIES, INC. (14.35)
TEX OP CONSTRUCTION, LP (0.00)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00)
Contract #03173018
Totals4655723.690.001831948.6539.9

CountyERATH ETC
HighwayUS 67 ETC
FromFM 988
ToFM 219
CSJ0079-05-057
Proj IDNH 2018(326)
Work TypeSEAL COAT
 
238.9038357383.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-29-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0079-05-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173220
Totals8357383.920.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5