Monthly State Let Maintenance Report For El Paso District As Of Apr 10, 2018 Page 1 Of 2

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6215-03-001
Proj IDRMC - 621503001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
600.000315260.00267748.0584.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-10
Work Began11-01-10
Work Completed
Time Computed11-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6215-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09104013
Totals315260.000.00267748.0584.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6263-82-001
Proj IDRMC - 626382001
Work TypePOTHOLE REPAIR
 
100.0004188410.008463765.56100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-14
Work Began03-06-14
Work Completed12-31-15
Time Computed03-06-14
Contract Working Days365
Addl Days Granted275
Working Days Charged640
Percent Time Used100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6263-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12134024
Totals4188410.000.008463765.56100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6276-48-001
Proj IDRMC - 627648001
Work TypeBARRICADES, SIGNS, & TRAFFIC CONTROL
 
1.0001818870.002394701.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-15
Work Began03-01-15
Work Completed03-31-17
Time Computed03-01-15
Contract Working Days730
Addl Days Granted62
Working Days Charged762
Percent Time Used96
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144212
Totals1818870.000.002394701.75100.0

CountyEL PASO
HighwayUS0054
FromNEW MEXICO STATE LINE
ToEL PASO DISTRICT LINE
CSJ6276-69-001
Proj IDRMC - 627669001
Work TypeTRAFFIC MANAGEMENT SYSTEM
 
200.000606095.00714957.2699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted365
Working Days Charged881
Percent Time Used80
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6276-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154218
Totals606095.001080.00714957.2699.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6285-04-001
Proj IDRMC - 628504001
Work TypePOTHOLE REPAIR
 
100.000867150.001009490.9099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-15
Work Began07-13-15
Work Completed
Time Computed07-13-15
Contract Working Days365
Addl Days Granted45
Working Days Charged410
Percent Time Used100
Contractor(s)
DOUBLE H CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05154010
Totals867150.000.001009490.9099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6285-46-001
Proj IDRMC - 628546001
Work TypeDISTRICT WIDE CRACK SEAL
 
100.000849527.50549829.2564.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-15
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged67
Percent Time Used83
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154211
Totals849527.500.00549829.2564.7

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6288-05-001
Proj IDRMC - 628805001
Work TypeSPALL REPAIR
 
500.0001423671.002619153.5899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-13-16
Work Began00-00-00
Work Completed
Time Computed01-24-16
Contract Working Days365
Addl Days Granted251
Working Days Charged565
Percent Time Used91
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09154009
Totals1423671.000.002619153.5899.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6293-25-001
Proj IDBPM - 629325001
Work TypeBPM__BRIDGE PREVENTATIVE MAINTENANCE
 
4.500931184.101548805.68100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-05-16
Work Began07-05-16
Work Completed04-26-17
Time Computed07-05-16
Contract Working Days120
Addl Days Granted80
Working Days Charged200
Percent Time Used100
Contractor(s)
HAWK CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6293-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164011
Totals931184.100.001548805.68100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-32-001
Proj IDRMC - 629532001
Work TypeBUNDLE BID
 
1.0001692521.002323646.3099.9
Work Order03-02-16
Work Began04-04-16
Work Completed
Time Computed04-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6295-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154012
Totals1692521.00144705.202323646.3099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6298-38-001
Proj IDRMC - 629838001
Work TypeMETAL BEAM GUARD FENCE
 
100.000544153.00761901.18100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-16
Work Completed02-28-18
Time Computed00-00-00
Contract Working Days365
Addl Days Granted150
Working Days Charged485
Percent Time Used94
Contractor(s)
BOWEN INDUSTRIAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164021
Totals544153.0054565.07761901.18100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-10-001
Proj IDRMC - 630010001
Work TypeMETAL BEAM GUARDRAIL FENCE REPAIR
 
200.000613882.71866532.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-05-16
Work Completed12-31-17
Time Computed00-00-00
Contract Working Days365
Addl Days Granted180
Working Days Charged545
Percent Time Used100
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164006
Totals613882.710.00866532.75100.0

CountyCULBERSON
HighwayRM0652
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6304-83-001
Proj IDRMC - 630483001
Work TypePOTHOLE REPAIR
 
100.000683925.001882693.1199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-17-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted135
Working Days Charged408
Percent Time Used81
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6304-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164014
Totals683925.000.001882693.1199.9

CountyJEFF DAVIS
HighwaySH0017
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6306-40-001
Proj IDBPM - 630640001
Work TypeBPM
 
4.000739781.00325056.0043.9
Work Order06-28-17
Work Began07-10-17
Work Completed
Time Computed07-01-17
Contract Working Days140
Addl Days Granted0
Working Days Charged124
Percent Time Used88
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174216
Totals739781.006960.00325056.0043.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6307-29-001
Proj IDRMC - 630729001
Work TypeDISTRICT WIDE CRACK SEAL
 
2.790820550.00395072.2948.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged67
Percent Time Used67
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164218
Totals820550.000.00395072.2948.1

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6308-13-001
Proj IDRMC - 630813001
Work TypePOTHOLE REPAIR
 
100.0001054700.00501623.3947.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-20-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged405
Percent Time Used55
Contractor(s)
DOUBLE H CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164017
Totals1054700.000.00501623.3947.5

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6308-53-001
Proj IDRMC - 630853001
Work TypePOTHOLE REPAIR
 
100.0001084400.00303405.7527.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-06-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged424
Percent Time Used58
Contractor(s)
DOUBLE H CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164218
Totals1084400.000.00303405.7527.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6308-54-001
Proj IDRMC - 630854001
Work TypeILLUMINATION MAINTENANCE REPAIR
 
100.000530175.00640227.7999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged364
Percent Time Used49
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6308-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174235
Totals530175.001970.00640227.7999.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-13-001
Proj IDRMC - 630913001
Work TypeBARRICADES, SIGNS, AND TRAFFIC CONTROL
 
200.000659645.00536249.0081.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174236
Totals659645.0049257.33536249.0081.2

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-17-001
Proj IDRMC - 630917001
Work TypeMISC. CONCRETE REPAIR
 
186.0001311766.43804783.2661.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174010
Totals1311766.43178188.44804783.2661.3

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-55-001
Proj IDRMC - 630955001
Work TypeTRAFFIC CONTROL
 
100.000659645.00805311.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174237
Totals659645.0071073.00805311.0099.9

page 1 | page 2