Monthly State Let Maintenance Report For Dallas District As Of Mar 13, 2024 Page 1 Of 7

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN ROCKWALL AND
ToCOLLIN COUNTIES
CSJ6179-66-001
Proj IDRMC - 617966001
Work TypeVEGETATION MANAGEMENT
 
0.001138484.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ABH TREE SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6179-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11094014
Totals138484.000.000.000.0

CountyKAUFMAN
HighwayUS0175
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6263-98-001
Proj IDRMC - 626398001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001481998.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154005
Totals481998.500.000.000.0

CountyDALLAS
HighwayIH0030
FromNEAR ERVAY ST
ToNORTHWEST DRIVE
CSJ6285-62-001
Proj IDRMC - 628562001
Work TypePERFORM BASE O & M OF HOV LANE & BTM
 
11.10010595000.0021674125.6899.9
Work Order09-23-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days1,460
Addl Days Granted1,674
Working Days Charged3,070
Percent Time Used97
Contractor(s)
LINDSAY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6285-62-001
DUSTROL, INC. (1.37)
Contract #08154010
Totals10595000.00219821.4421674125.6899.9

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6317-51-001
Proj IDRMC - 631751001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.0011027494.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6317-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174008
Totals1027494.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6317-52-001
Proj IDRMC - 631752001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.0011099347.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6317-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174208
Totals1099347.000.000.000.0

CountyDENTON
HighwayUS0380
FromVARIOUS ROADWYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6322-81-001
Proj IDRMC - 632281001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.100562500.00447167.00100.0
Work Order03-09-18
Work Began03-12-18
Work Completed03-26-20
Time Computed03-16-18
Contract Working Days730
Addl Days Granted0
Working Days Charged685
Percent Time Used93
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6322-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184207
Totals562500.000.00447167.00100.0

CountyDALLAS
HighwayIH0030
FromVARIOUS MANAGED LANES IN DALLAS AND
ToTARRANT COUNTIES
CSJ6324-43-001
Proj IDRMC - 632443001
Work TypePERF BASED OPER & MAINT OF MANAGED LANES
 
16.5005662048.0017501924.9399.9
Work Order10-31-18
Work Began09-01-18
Work Completed
Time Computed09-01-18
Contract Working Days730
Addl Days Granted1,464
Working Days Charged2,006
Percent Time Used91
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184210
Totals5662048.00191474.1417501924.9399.9

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON COUNTY
ToMAINTENANCE SECTION
CSJ6327-47-001
Proj IDRMC - 632747001
Work TypeGUARDRAIL REPAIR
 
0.1005738770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184007
Totals5738770.000.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6329-79-001
Proj IDRMC - 632979001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.001431000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06194006
Totals431000.000.000.000.0

CountyDENTON
HighwayFM0455
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6336-29-001
Proj IDRMC - 633629001
Work TypeROADSIDE MOWING
 
0.001262790.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days46
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JMT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6336-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184016
Totals262790.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6338-26-001
Proj IDRMC - 633826001
Work TypeSTORM SEWER AND INLET CLEANING
 
0.0011042591.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184010
Totals1042591.150.000.000.0

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE EAST DALLAS
ToCOUNTY MAINTENANCE SECTIONS
CSJ6338-27-001
Proj IDRMC - 633827001
Work TypeSTORM SEWER AND INLET CLEANING
 
0.001871029.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184201
Totals871029.000.000.000.0

CountyNAVARRO
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6341-43-001
Proj IDRMC - 634143001
Work TypePOTHOLE REPAIR
 
0.001621400.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6341-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194011
Totals621400.000.000.000.0

CountyDALLAS
HighwayIH0035E
FromVARIOUS ROADWAYS IN
ToDALLAS AND DENTON COUNTY
CSJ6373-00-001
Proj IDRMC - 637300001
Work TypePERFORMANCE BASED CONTRACT
 
0.0103650661.755623340.6299.9
Work Order05-04-21
Work Began05-18-21
Work Completed
Time Computed05-18-21
Contract Working Days730
Addl Days Granted730
Working Days Charged1,014
Percent Time Used69
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6373-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214207
Totals3650661.75153554.365623340.6299.9

CountyDALLAS
HighwayUS0075
FromVARIOUS ROADWAYS IN
ToNORTHEAST DALLAS COUNTY MAINTENANCE
CSJ6379-14-001
Proj IDRMC - 637914001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010660078.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214015
Totals660078.500.000.000.0

CountyDALLAS
HighwayIH0045
FromVARIOUS ROADWAYS IN
ToSOUTHEAST DALLAS COUNTY MAINTENANCE
CSJ6379-15-001
Proj IDRMC - 637915001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010578294.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214014
Totals578294.920.000.000.0

CountyDALLAS
HighwayIH0035E
FromVARIOUS ROADWAYS IN
ToSOUTHWEST DALLAS COUNTY MAINTENANCE
CSJ6379-16-001
Proj IDRMC - 637916001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010505756.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214206
Totals505756.400.000.000.0

CountyDALLAS
HighwayIH0635
FromVARIOUS ROADWAYS IN
ToNORTHWEST DALLAS COUNTY MAINTENANCE
CSJ6379-17-001
Proj IDRMC - 637917001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010773289.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214205
Totals773289.350.000.000.0

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6385-96-001
Proj IDRMC - 638596001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101072475.001190270.6599.9
Work Order11-04-22
Work Began11-11-22
Work Completed
Time Computed11-11-22
Contract Working Days730
Addl Days Granted0
Working Days Charged472
Percent Time Used64
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6385-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224222
Totals1072475.0075006.901190270.6599.9

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToSOUTHEAST DALLAS COUNTY MAINTENANCE
CSJ6387-33-001
Proj IDRMC - 638733001
Work TypePOTHOLE REPAIR
 
0.010729425.00679750.7793.1
Work Order12-09-21
Work Began12-14-21
Work Completed
Time Computed12-16-21
Contract Working Days730
Addl Days Granted60
Working Days Charged790
Percent Time Used100
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6387-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214011
Totals729425.000.00679750.7793.1

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7