Monthly State Let Maintenance Report For Dallas District As Of Aug 16, 2018 Page 1 Of 7

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN ROCKWALL AND
ToCOLLIN COUNTIES
CSJ6179-66-001
Proj IDRMC - 617966001
Work TypeVEGETATION MANAGEMENT
 
0.001138484.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ABH TREE SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6179-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11094014
Totals138484.000.000.000.0

CountyKAUFMAN
HighwayUS0175
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6263-98-001
Proj IDRMC - 626398001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001481998.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154005
Totals481998.500.000.000.0

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATIONS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6276-71-001
Proj IDRMC - 627671001
Work TypePOTHOLE REPAIR
 
0.0012875000.001382803.6048.0
Work Order05-11-15
Work Began05-18-15
Work Completed
Time Computed05-18-15
Contract Working Days730
Addl Days Granted502
Working Days Charged1,165
Percent Time Used94
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154012
Totals2875000.000.001382803.6048.0

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY
CSJ6280-68-001
Proj IDRMC - 628068001
Work TypeFLEXIBLE PVMT STRUCTURE REPAIR & OVERLAY
 
0.0014787375.005540239.3899.9
Work Order04-24-15
Work Began05-04-15
Work Completed
Time Computed05-04-15
Contract Working Days365
Addl Days Granted851
Working Days Charged1,184
Percent Time Used97
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6280-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154209
Totals4787375.00223632.195540239.3899.9

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6280-74-001
Proj IDRMC - 628074001
Work TypeCALL OUT REFLECTORIZED PAVMENT MARKINGS
 
0.001893845.00392122.3743.8
Work Order06-09-15
Work Began06-15-15
Work Completed
Time Computed06-16-15
Contract Working Days730
Addl Days Granted561
Working Days Charged1,125
Percent Time Used87
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154010
Totals893845.000.00392122.3743.8

CountyDALLAS
HighwayIH0030
FromNEAR ERVAY ST
ToNORTHWEST DRIVE
CSJ6285-62-001
Proj IDRMC - 628562001
Work TypePERFORM BASE O & M OF HOV LANE & BTM
 
11.10010595000.007698303.5072.6
Work Order09-23-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days1,460
Addl Days Granted0
Working Days Charged1,029
Percent Time Used70
Contractor(s)
LINDSAY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6285-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154010
Totals10595000.00220312.507698303.5072.6

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAITNENANCE SECTION
CSJ6290-32-001
Proj IDRMC - 629032001
Work TypeSWEEPING/DEBRIS REMOVAL
 
0.0011810867.001058842.0758.4
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged632
Percent Time Used86
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6290-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164005
Totals1810867.0059123.801058842.0758.4

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE
ToDALLAS DISTRICT
CSJ6292-93-001
Proj IDRMC - 629293001
Work TypeNON-SITE SPEC SIGN REPLACEMENT & REFURB
 
0.001628889.99484199.28100.0
Work Order07-27-16
Work Began08-03-16
Work Completed08-02-18
Time Computed08-03-16
Contract Working Days730
Addl Days Granted0
Working Days Charged722
Percent Time Used98
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164013
Totals628889.9941152.08484199.28100.0

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6295-33-001
Proj IDRMC - 629533001
Work TypeSPECIALTY MARKINGS
 
0.001423373.30244518.0157.7
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged595
Percent Time Used81
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164213
Totals423373.300.00244518.0157.7

CountyDALLAS
HighwayIH0030
FromVARIOUS HOV LANES IN DALLAS AND TARRANT
ToCOUNTIES
CSJ6296-73-001
Proj IDRMC - 629673001
Work TypePERF BASED O & M OF HOV-EXPRESS LANES
 
0.0012375000.002469761.6499.9
Work Order07-13-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted31
Working Days Charged724
Percent Time Used95
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164210
Totals2375000.0053440.002469761.6499.9

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6297-52-001
Proj IDRMC - 629752001
Work TypeGUARD FENCE & CABLE BARRIER REPAIR
 
0.001354169.00239005.00100.0
Work Order08-02-16
Work Began08-08-16
Work Completed08-07-18
Time Computed08-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164204
Totals354169.008804.00239005.00100.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6298-90-001
Proj IDRMC - 629890001
Work TypePOTHOLE REPAIR & EDGE REPAIR
 
0.001780000.00532391.0068.2
Work Order08-16-17
Work Began08-23-17
Work Completed
Time Computed08-24-17
Contract Working Days730
Addl Days Granted0
Working Days Charged338
Percent Time Used46
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164010
Totals780000.0010600.00532391.0068.2

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6299-00-001
Proj IDRMC - 629900001
Work TypeMETAL BEAM GUARD FENCE & DELINEATION
 
0.001897796.001522837.5099.9
Work Order10-13-16
Work Began10-20-16
Work Completed
Time Computed10-19-16
Contract Working Days730
Addl Days Granted0
Working Days Charged644
Percent Time Used88
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164011
Totals897796.0088309.001522837.5099.9

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6299-09-001
Proj IDRMC - 629909001
Work TypeFULL DEPTH CONRETE & SPALLING REPAIR
 
0.001587100.00574753.8397.8
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged595
Percent Time Used81
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164208
Totals587100.000.00574753.8397.8

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToMAINTENANCE SECTION
CSJ6299-33-001
Proj IDRMC - 629933001
Work TypeGUARDRAIL, CABLE & HEADLIGHT BARRIER REP
 
0.1001785538.001446708.0281.0
Work Order08-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged693
Percent Time Used94
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164009
Totals1785538.0074357.521446708.0281.0

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6299-34-001
Proj IDRMC - 629934001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.001752679.20530919.3370.5
Work Order08-24-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged693
Percent Time Used94
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164210
Totals752679.2032549.71530919.3370.5

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6299-75-001
Proj IDRMC - 629975001
Work TypeSPECIALTY MARKINGS
 
0.001369389.7590127.3524.3
Work Order08-24-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged695
Percent Time Used95
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164211
Totals369389.751180.0090127.3524.3

CountyDALLAS
HighwayUS0175
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-87-001
Proj IDRMC - 629987001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.0011869508.641412380.3375.5
Work Order11-10-16
Work Began11-14-16
Work Completed
Time Computed11-17-16
Contract Working Days730
Addl Days Granted0
Working Days Charged619
Percent Time Used84
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164211
Totals1869508.6449170.201412380.3375.5

CountyDALLAS
HighwayUS0067
FromVARIOUS HIGHWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-93-001
Proj IDRMC - 629993001
Work TypeGUARD FENCE & CABLE REPAIR
 
0.0011180195.002192585.4099.9
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged632
Percent Time Used86
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164013
Totals1180195.0070315.652192585.4099.9

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6300-19-001
Proj IDRMC - 630019001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
109.7001038782.10860192.0582.8
Work Order09-01-16
Work Began09-08-16
Work Completed
Time Computed09-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged686
Percent Time Used93
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164010
Totals1038782.1020800.00860192.0582.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7