Monthly Local Let Maintenance Report For Dallas District As Of Aug 16, 2018 Page 1 Of 4

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.000.0

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATION IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6291-42-001
Proj IDRMC - 629142001
Work TypeRAISED PAVEMENT MARKERS
 
0.001133279.7054110.0040.5
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged595
Percent Time Used81
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6291-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161801
Totals133279.700.0054110.0040.5

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyELLIS
HighwayFM0813
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6296-95-001
Proj IDRMC - 629695001
Work TypeREMOVAL AND DISPOSAL OF DRIFTWOOD
 
0.001274500.00157770.0057.4
Work Order02-22-16
Work Began01-26-16
Work Completed
Time Computed02-29-16
Contract Working Days730
Addl Days Granted189
Working Days Charged853
Percent Time Used92
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161801
Totals274500.000.00157770.0057.4

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6297-44-001
Proj IDRMC - 629744001
Work TypeSPECIALTY MARKINGS
 
0.001273952.00139889.0751.0
Work Order06-27-16
Work Began07-06-16
Work Completed
Time Computed07-05-16
Contract Working Days730
Addl Days Granted179
Working Days Charged755
Percent Time Used83
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161805
Totals273952.000.00139889.0751.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-24-001
Proj IDRMC - 630124001
Work TypeCALL OUT REFLECTORIZED PAVEMENT MARKINGS
 
0.001171011.4493103.1854.4
Work Order09-13-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days730
Addl Days Granted0
Working Days Charged674
Percent Time Used92
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161803
Totals171011.440.0093103.1854.4

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-00-001
Proj IDRMC - 630200001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001253810.00233834.2092.1
Work Order02-03-17
Work Began02-10-17
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 6302-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161806
Totals253810.000.00233834.2092.1

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-03-001
Proj IDRMC - 630203001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.0010.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161802
Totals0.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-04-001
Proj IDRMC - 630204001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00155500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161803
Totals55500.000.000.000.0

CountyNAVARRO
HighwayIH0045
FromVARIOUS ROADWAYS IN THE NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6302-47-001
Proj IDSUP - 630247001
Work TypeLITTER REMOVAL
 
0.00148732.2447294.7897.0
Work Order06-18-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged694
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6302-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161830
Totals48732.24102.6247294.7897.0

CountyDALLAS
HighwayIH0020
FromVARIOUS ROADWAYS IN THE NORTHWEST DALLAS
ToCOUNTY MAINTENANCE SECFTION
CSJ6302-48-001
Proj IDSUP - 630248001
Work TypeLITTER REMOVAL
 
0.00194310.46111000.8299.9
Work Order07-21-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged693
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161831
Totals94310.464308.92111000.8299.9

CountyDALLAS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE SOUTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-49-001
Proj IDSUP - 630249001
Work TypeLITTER REMOVAL
 
0.001212694.94196578.7692.4
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged693
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161832
Totals212694.948438.20196578.7692.4

CountyKAUFMAN
HighwayUS0080
FromVARIOUS ROADWAYS IN KAUFMAN
ToMAINTENANCE SECTION
CSJ6302-50-001
Proj IDSUP - 630250001
Work TypeLITTER REMOVAL
 
0.001222173.02187777.8384.5
Work Order08-02-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged693
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161833
Totals222173.025859.47187777.8384.5

CountyCOLLIN
HighwayUS0380
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6302-51-001
Proj IDSUP - 630251001
Work TypeLITTER REMOVAL
 
0.001196309.70190018.72100.0
Work Order05-27-16
Work Began09-01-16
Work Completed08-03-18
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged695
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6302-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161834
Totals196309.70689.91190018.72100.0

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE NORTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-52-001
Proj IDSUP - 630252001
Work TypeLITTER REMOVAL
 
0.00195207.7160284.2263.3
Work Order07-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged693
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161835
Totals95207.714401.3060284.2263.3

page 1 | page 2 | page 3 | page 4