Monthly State Let Construction Report For Dallas District As Of Jun 08, 2018 Page 7 Of 8

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayFM 1387
From1.542 MI NE OF BU 287Q
To2.51 MI NE OF BU 287Q
CSJ1394-02-026
Proj IDSTP 2018(890)HES
Work TypeWIDEN EXISTING PAVEMENT
 
0.9681003410.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days133
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 1394-02-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183019
Totals1003410.950.000.000.0

CountyELLIS
HighwayFM 55
FromAT LITTLE ONION CREEK
To.
CSJ1451-01-020
Proj IDBR 2005(274)
Work TypeREPLACE BRIDGES AND APPROACHES
 
0.3122010620.161441956.6077.3
Work Order07-24-15
Work Began02-18-16
Work Completed
Time Computed11-21-15
Contract Working Days340
Addl Days Granted0
Working Days Charged484
Percent Time Used142
Contractor(s)
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-020
TEXOP CONSTRUCTION (1.10)
FORTSON CONTRACTING, INC. (2.27)
SAN-ANN-CO., INC. (0.96)
USA EROSION, INC. (4.31)
STRIPING TECHNOLOGY, L.P. (1.50)
W. W. FOUNDATION DRILLING, LTD. (2.35)
DFW REBAR, INC. (0.68)
VISTA RIDGE CONCRETE PUMPING, INC. (0.07)
ADVANCED PAVING COMPANY (6.67)
B.G. WILLIAMS ASPHALT, LTD (0.36)
HOUSTON SAWING & DRILLING (0.30)
KNIFE RIVER CORPORATION - SOUTH (0.35)
CTBX, INC. (1.96)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.89)
BUYERS BARRICADES, INC. (1.01)
SOUTHEAST GRINDING & GROOVING, LLC (0.20)
PANTHER CREEK TRANSPORTATION, INC. (0.45)
Contract #05153220
Totals2010620.16135020.001441956.6077.3

CountyELLIS
HighwayFM 55
FromAT BIG ONION CREEK
To.
CSJ1451-01-025
Proj IDBR 1502(533)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1351530409.40651771.8342.5
Work Order10-28-15
Work Began11-21-16
Work Completed
Time Computed11-30-15
Contract Working Days183
Addl Days Granted0
Working Days Charged151
Percent Time Used82
Contractor(s)
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-025
STRIPING TECHNOLOGY, L.P. (1.12)
FORTSON CONTRACTING, INC. (3.06)
ADVANCED PAVING COMPANY (2.70)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.31)
CTBX, INC. (2.13)
ACU CONSTRUCTION LLC (0.62)
W. W. FOUNDATION DRILLING, LTD. (2.81)
DFW REBAR, INC. (1.14)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (1.59)
BUYERS BARRICADES, INC. (0.83)
SOUTHEAST GRINDING & GROOVING, LLC (0.27)
PANTHER CREEK TRANSPORTATION, INC. (0.20)
Contract #08153020
Totals1530409.40144543.53651771.8342.5

CountyKAUFMAN
HighwayFM 3486
FromFM 986
ToSH 34
CSJ1494-03-001
Proj IDC 1494-3-1
Work TypeGR, STRS, BASE & SURF
 
2.4904849821.374292492.4189.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-26-16
Work Began07-19-16
Work Completed
Time Computed07-19-16
Contract Working Days168
Addl Days Granted1
Working Days Charged195
Percent Time Used115
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1494-03-001
PEACHTREE CONSTRUCTION, LTD. (15.94)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46)
SYNERGY SIGNS & SERVICES, LLC (0.64)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.05)
BRENDA PRICE TRUCKING (0.73)
FANNIN TREE FARM, LTD (0.79)
DFW MATERIALS LP (12.21)
Contract #04163222
Totals4849821.370.004292492.4189.0

CountyDENTON
HighwayFM 720
FromELDORADO PKWY (FM 720)
ToSOUTH OF MARTOP
CSJ1567-01-025
Proj IDC 1567-1-25
Work TypeGR, STRS & PVT
 
2.56515597320.2516903742.4599.9
Work Order04-11-14
Work Began10-26-15
Work Completed
Time Computed01-06-15
Contract Working Days420
Addl Days Granted102
Working Days Charged604
Percent Time Used115
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
S & S BRIDGE PAINTING, INC. (0.02)
C.T. AND S. METALWORKS, INC. (0.11)
ACU CONSTRUCTION LLC (0.69)
W.O.E. CONSTRUCTION (1.22)
BREDA COMPANY, INC. (0.99)
USA SWPPP INSPECTIONS, INC. (1.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.04)
FORTSON CONTRACTING, INC. (0.02)
DURABLE SPECIALTIES, INC. (1.69)
MARCOM"S MOWING SERVICE, LLC (0.10)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (15.66)
DALLAS LITE AND BARRICADE INC. (0.66)
THELIN RECYCLING COMPANY, L.P. (0.21)
A.E.A. TRANSPORTATION (0.21)
TEX OP CONSTRUCTION, LP (0.55)
URBAN INFRACONSTRUCTION, LLC. (0.18)
Contract #02143001
Totals15597320.2584153.6516903742.4599.9

CountyDENTON
HighwayFM 423
FromSH 121
ToSTEWARTS CREEK ROAD
CSJ1567-02-031
Proj IDSTP 2018(451)
Work TypePLANTS AND LANDSCAPING
 
3.761746680.66450856.0060.3
Work Order02-14-18
Work Began03-19-18
Work Completed
Time Computed03-19-18
Contract Working Days109
Addl Days Granted0
Working Days Charged51
Percent Time Used46
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183212
Totals746680.6639251.20450856.0060.3

CountyDENTON
HighwayFM 423
FromSTEWARTS CREEK ROAD
ToSH 121
CSJ1567-02-032
Proj IDC 1567-2-32
Work TypeWIDEN TO 6 LANE DIVIDED URBAN
 
3.76149691109.9254325021.4299.9
CountyDENTON
HighwayFM 423
FromSTEWARTS CREEK ROAD
ToSH 121
CSJ1567-02-033
Proj IDRW 1567-2-33
Work TypeADJUSTMENT OF UTILITIES
 
3.7618252384.389632434.5699.9
Work Order08-27-14
Work Began10-20-14
Work Completed
Time Computed09-12-14
Contract Working Days756
Addl Days Granted55
Working Days Charged810
Percent Time Used99
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
ATS DRILLING, INC. (1.12)
C.T. AND S. METALWORKS, INC. (0.32)
DUSTROL, INC. (0.52)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.08)
HOUSTON SAWING & DRILLING (0.00)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.31)
MEL"S ELECTRIC SERVICE, INC. (6.02)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.40)
DALLAS LITE AND BARRICADE INC. (0.14)
SCOTT DERR PAINTING CO, LLC (0.66)
STORM WATER MANAGEMENT, INC. (0.14)
STRIPING TECHNOLOGY, L.P. (0.73)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.13)
WEST TEXAS REBAR PLACERS INC. (0.35)
W.O.E. CONSTRUCTION (4.60)
MCL CONTRACTING, LLC (0.06)
BORE COMPANY (2.11)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS (0.19)
TEXAS STAR TRANSPORT, LP (0.69)
INDUS CONSTRUCTION, L.P. (4.75)
FORTSON CONTRACTING, INC. (0.09)
ACTION CONSTRUCTORS (0.54)
SYNERGY SIGNS & SERVICES, LLC (0.11)
RICE TUNNELING & BORING, INC. (0.15)
HIGH QUALITY ELECTRIC (0.04)
ALLIED DRILLING COMPANY (0.08)
TOMAS REYES TRUCKING, INC. (0.68)
ROAD MAKER CONTRACTORS (0.44)
PANIOLO CONSTRUCTION SERVICES, LLC (0.40)
DALE BROWN, INC. (0.15)
URBAN INFRACONSTRUCTION, LLC (0.14)
AQUA RECOVER GROUP, CORP. (0.73)
WEBBER BARRIER SERVICES, LLC. (0.12)
JSS BORI GROUP, LLC (1.09)
LINDAMOOD DEMOLITION, INC. (0.11)
TRANSAMERICAN UNDERGROUND, LTD (0.00)
TEXAS CONCRETE CUTTING & DEMOLITION (0.02)
J. E. GUZMAN CONSTRUCTION, INC. (0.00)
E-LOGIC, INC. (0.00)
URBAN INFRACONSTRUCTION, LLC. (0.73)
TEX OP CONSTRUCTION, LP (0.00)
C & S UTILITY CONTRACTORS, INC. (0.05)
Contract #05143001
Totals57943494.30504833.3163957455.9899.9

CountyDENTON
HighwayFM 1830
FromFM 407
ToUS 377
CSJ1785-01-032
Proj IDSTP 1602(424)
Work TypeSHLDR WDN,BS REP, CULVERT WDN
 
5.8773769368.723308067.2287.7
CountyDENTON
HighwayFM 1830
FromAT FINCHER BRANCH
To.
CSJ1785-01-034
Proj IDBR 1602(425)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3982131977.021754503.7982.2
Work Order01-25-17
Work Began04-17-17
Work Completed
Time Computed04-17-17
Contract Working Days400
Addl Days Granted0
Working Days Charged241
Percent Time Used60
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-032
IOWA BRIDGE & CULVERT, LC (1.11)
DUSTROL, INC. (3.32)
OSCAR ORDUNO, INC. (1.02)
COMEN ENTERPRISE LLC (1.67)
TOTAL HIGHWAY MAINTENANCE, LLC (1.06)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.11)
TEXAS SHAFTS, INC. (1.77)
THELIN RECYCLING COMPANY, L.P. (0.55)
Contract #10163011
Totals5901345.74108802.015062571.0185.7

CountyCOLLIN
HighwayFM 1461
FromSH 289
ToFM 2478
CSJ1973-01-014
Proj IDSSW 1973-1-14
Work TypeBASE REPAIR,LEVEL UP,OVERLAY
 
2.9902697083.132547591.8494.4
Work Order07-20-17
Work Began08-28-17
Work Completed
Time Computed08-28-17
Contract Working Days148
Addl Days Granted0
Working Days Charged148
Percent Time Used100
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1973-01-014
ALTUS TRAFFIC MANAGEMENT LLC (0.43)
FORTSON CONTRACTING, INC. (1.54)
MARCOM"S MOWING SERVICE, LLC (0.90)
TRP CONSTRUCTION GROUP, LLC (1.51)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.78)
W.S. CONSTRUCTION COMPANY (23.67)
W.O.E. CONSTRUCTION (0.06)
Contract #06173026
Totals2697083.13132164.562547591.8494.4

CountyDENTON
HighwayFM 2449
FromWEST OF DENTON CREEK
To.
CSJ2352-02-022
Proj IDC 2352-2-22
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.284709151.800.000.0
CountyDENTON
HighwayFM 2934
FromFM 423 (ELDORADO PKWY)
ToCOLLIN COUNTY LINE
CSJ2980-01-013
Proj IDSTP 2018(743)
Work TypeCONCRETE FULL DEPTH REPAIR
 
2.8101493859.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2352-02-022
BRENDA PRICE TRUCKING (0.00)
ALTUS TRAFFIC MANAGEMENT LLC (1.10)
TRP CONSTRUCTION GROUP, LLC (4.49)
Contract #04183010
Totals2203011.050.000.000.0

CountyDALLAS
HighwayIH 635
FromEAST OF ABRAMS RD
ToWEST OF PLANO RD
CSJ2374-01-180
Proj IDC 2374-1-180
Work TypeNOISE WALLS
 
2.5577705519.391513273.0719.6
CountyDALLAS
HighwayIH 635
FromEAST OF CENTERVILLE RD
ToIH 30
CSJ2374-02-144
Proj IDC 2374-2-144
Work TypeNOISE WALLS
 
2.3673665042.15233328.666.3
CountyDALLAS
HighwayIH 635
FromEAST OF CENTERVILLE RD
ToIH 30
CSJ2374-02-151
Proj IDNH 1702(428)
Work TypeUTILITIES ADJUSTMENTS
 
4.444380045.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began05-07-18
Work Completed
Time Computed00-00-00
Contract Working Days250
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-01-180
BOWMAN ENGINEERING & CONSULTING, INC (0.00)
MELS ELECTRIC, L.P. (0.20)
OSCAR ORDUNO, INC. (0.32)
PANIOLO CONSTRUCTION SERVICES, LLC (1.44)
RUSSO CORPORATION (12.24)
VENUS CONSTRUCTION (2.90)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.90)
WITHERS CONSTRUCTION, LLC (1.10)
BUYERS BARRICADES, INC. (0.67)
HERDEZ TRUCKING, INC. (0.00)
BOWMAN ENGINEERING & CONSULTING, INC (0.77)
Contract #11173201
Totals11750606.541475110.541746601.7314.8

CountyDALLAS
HighwayIH 635 ETC
From0.509 MI WEST OF FM 78
ToGREENVILLE AVE.
CSJ2374-01-187
Proj IDSTP 1702(455)HES
Work TypeINSTALL PROTECTION
 
56.4803522310.641606019.4545.5
Work Order10-03-17
Work Began11-27-17
Work Completed
Time Computed11-13-17
Contract Working Days185
Addl Days Granted0
Working Days Charged130
Percent Time Used70
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-01-187
LYNCO CONSTRUCTION (0.00)
Contract #07173227
Totals3522310.64332417.321606019.4545.5

CountyDALLAS
HighwayIH 635
FromAT QUAIL DRIVE
To.
CSJ2374-02-143
Proj IDCM 2018(891)
Work TypePEDESTRIAN IMPROVEMENTS
 
0.001350140.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEW WORLD CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-143
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183013
Totals350140.330.000.000.0

CountyDALLAS
HighwayIH 635
FromAT ELAM ROAD
ToAT LAKE JUNE ROAD
CSJ2374-02-149
Proj IDNH 1602(426)
Work TypeLANDSCAPE ENHANCEMENT
 
1.585821756.18970362.5299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-16
Work Began11-28-16
Work Completed
Time Computed11-21-16
Contract Working Days148
Addl Days Granted41
Working Days Charged178
Percent Time Used94
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-149
BUYERS BARRICADES, INC. (0.87)
MONSTER TREE SERVICE OF NORTH DFW (0.17)
DOWN UNDER CONSTRUCTION (0.24)
Contract #08163018
Totals821756.180.00970362.5299.9

CountyDALLAS
HighwayIH 20
FromWEST OF HAYMARKET RD
ToWEST OF US 175
CSJ2374-03-077
Proj IDSTP 1502(329)MM
Work TypeGRADING, PAVEMENT, SIGNS
 
0.9286825509.897628159.6999.9
CountyDALLAS
HighwayIH 20
FromWEST OF HAYMARKET RD
ToWEST OF US 175
CSJ2374-03-082
Proj IDROW 2374-3-82
Work TypeACQUISITION AND UTILITIES
 
0.928551776.00733396.2299.9
Work Order08-06-15
Work Began02-01-16
Work Completed
Time Computed01-03-16
Contract Working Days294
Addl Days Granted107
Working Days Charged394
Percent Time Used98
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-077
TOTAL HIGHWAY MAINTENANCE, LLC (1.18)
GJ SEEDING, LLC (0.69)
ACU CONSTRUCTION LLC (0.34)
DALLAS LITE AND BARRICADE INC. (0.70)
MICA CORPORATION (1.60)
PREMIER PAVING, LTD. (10.82)
S&S BRIDGE PAINTING (0.08)
PROJECT 2015, LLC (8.31)
ACME UTILITY INSPECTION SERVICES, INC. (0.09)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.25)
W.O.E. CONSTRUCTION (0.29)
A.E.A. TRANSPORTATION (1.88)
FORTSON CONTRACTING, INC. (0.35)
BREDA COMPANY, INC. (0.69)
T-BAR FENCE, INC. (0.10)
ANCORTEX, INC. (0.67)
MCL CONTRACTING, LLC (0.05)
WEBBER, LLC (0.35)
A-CORE, INC. (0.04)
KLEEN PIPE (0.15)
Contract #06153018
Totals7377285.891653.508361555.9199.9

CountyDALLAS
HighwayIH 20
FromWEST OF CARRIER PARKWAY
ToFM 1382 (BELT LINE ROAD)
CSJ2374-04-049
Proj IDNH 1602(427)
Work TypeCONSTRUCTION OF FRONTAGE ROAD
 
2.37254241512.3010801090.2019.9
Work Order07-20-17
Work Began01-18-18
Work Completed
Time Computed01-02-18
Contract Working Days791
Addl Days Granted0
Working Days Charged103
Percent Time Used13
Contractor(s)
FLUOR HEAVY CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-049
BUYERS BARRICADES, INC. (0.02)
WOLFE CONSTRUCTION GROUP, INC. (0.20)
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (5.17)
COMEN ENTERPRISE LLC (0.73)
A R DANIEL CONSTRUCTION SERVICES, INC. (1.14)
W.O.E. CONSTRUCTION (0.01)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.48)
A BROTHERS MILLING, LLC (0.25)
THELIN RECYCLING COMPANY, L.P. (0.03)
COWBOY TRUCKING (2.43)
KLP COMMERCIAL, LLC (1.86)
TEXAS SHAFTS, INC. (4.74)
ROYAL REBAR (0.79)
RENAISSANCE CONTRACTORS, INC. (0.86)
FARR FOUNDATION, INC. (1.12)
Contract #06173002
Totals54241512.301994292.5810801090.2019.9

CountyKAUFMAN
HighwayFM 2728
FromFM 429
ToUS 80
CSJ2512-02-010
Proj IDSTP 1702(086)
Work TypeGRADING, BASE, PVT, PVT MARKINGS
 
3.0003813436.393623769.7195.0
Work Order06-14-17
Work Began07-21-17
Work Completed
Time Computed07-21-17
Contract Working Days206
Addl Days Granted0
Working Days Charged198
Percent Time Used96
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2512-02-010
TOTAL HIGHWAY MAINTENANCE, LLC (0.36)
CATOCON, INC. (0.94)
OLDCASTLE MATERIALS TEXAS, INC. (18.16)
BAHENA CONSTRUCTION CO.,INC. (13.47)
FORTSON CONTRACTING, INC. (1.60)
A.E. MOORE CONSTRUCTION, INC. DBA (1.72)
MARCOM"S MOWING SERVICE, LLC (0.52)
TEXOP CONSTRUCTION (2.25)
AREA WIDE PROTECTIVE, INC. (0.43)
Contract #05173024
Totals3813436.3938466.703623769.7195.0

CountyKAUFMAN
HighwayFM 2578
FromUS 175
ToFM 987
CSJ2555-01-011
Proj IDC 2555-1-11
Work TypeGRADING,BASE,PVT,PVT MKS
 
5.6376878335.706026689.7188.6
Work Order12-05-16
Work Began02-07-17
Work Completed
Time Computed02-07-17
Contract Working Days247
Addl Days Granted0
Working Days Charged312
Percent Time Used126
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2555-01-011
ALTUS TRAFFIC MANAGEMENT LLC (0.26)
MARCOM"S MOWING SERVICE, LLC (0.48)
TOTAL HIGHWAY MAINTENANCE, LLC (0.64)
A. L. CONSTRUCTION, LLC (3.20)
NIXON ENGINEERING, L.L.C. (0.02)
HOUSTON TRUCKING & PAVING CO. (0.39)
Contract #10163018
Totals6878335.70404423.836026689.7188.6

CountyDENTON
HighwayFM 2499
FromFM 2181 N
ToIH 35E
CSJ2681-01-012
Proj IDC 2681-1-12
Work TypeGR, DR, STR, SURF & CONC PAV
 
2.91834857000.0039772645.4599.9
Work Order09-12-14
Work Began04-20-15
Work Completed
Time Computed03-11-15
Contract Working Days505
Addl Days Granted195
Working Days Charged689
Percent Time Used98
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2681-01-012
THELIN RECYCLING COMPANY, L.P. (0.28)
C.T. AND S. METALWORKS, INC. (1.03)
K & S UTILITY CONTRACTORS, INC. (12.74)
MELS ELECTRIC, L.P. (1.21)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.63)
STRIPE-A-ZONE, INC. (0.35)
TEXAS SHAFTS, INC. (6.63)
TEXOP CONSTRUCTION (0.13)
RAMBO CONTRACTING, INC. (3.23)
STORM WATER MANAGEMENT, INC. (0.15)
SLATON BROTHERS, INC. (1.91)
ALLIED DRILLING COMPANY (0.10)
MCL CONTRACTING, LLC (0.44)
DALLAS LITE AND BARRICADE INC. (0.14)
CINTEREX US, INC. (4.40)
HERDEZ TRUCKING, INC. (0.00)
JSS BORI GROUP, LLC (1.60)
COWBOY TRUCKING (0.36)
N. ROCK SOLUTIONS (0.09)
WEBBER BARRIER SERVICES, LLC. (0.41)
ACTION CONSTRUCTORS (3.63)
BREDA COMPANY, INC. (0.66)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
STRAIGHT LINE CONCRETE (0.02)
INDUS ROAD & BRIDGE, INC (0.64)
URBAN INFRACONSTRUCTION, LLC. (1.57)
SCOTT DERR PAINTING CO, LLC (0.41)
NORTH TEXAS BOMANITE, INC. (0.58)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.96)
ALLIED DRILLING COMPANY (0.02)
A CORE CONCRETE (0.25)
SOUTHEAST GRINDING & GROOVING, LLC (0.01)
SYNERGY SIGNS & SERVICES, LLC (0.06)
DURABLE SPECIALTIES, INC. (0.65)
Contract #07143002
Totals34857000.00258489.0539772645.4599.9

CountyCOLLIN
HighwayFM 2755
FromBUS 78G
ToFM 1138
CSJ2745-01-008
Proj IDSTP 2018(581)
Work TypeBS REP, OV
 
5.4931442157.61143985.869.9
Work Order04-09-18
Work Began05-18-18
Work Completed
Time Computed05-18-18
Contract Working Days69
Addl Days Granted0
Working Days Charged6
Percent Time Used8
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2745-01-008
WOLFE CONSTRUCTION GROUP, INC. (1.73)
MARCOM"S MOWING SERVICE, LLC (1.78)
AREA WIDE PROTECTIVE, INC. (0.56)
A BROTHERS MILLING, LLC (3.83)
Contract #03183023
Totals1442157.61143985.86143985.869.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8