Monthly State Let Construction Report For Dallas District As Of Nov 13, 2018 Page 5 Of 7

Last Update: Tuesday, November 13, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDENTON
HighwayFM 455
FromAT FM 2164 AND UNION HILL ROAD
To.
CSJ0816-02-079
Proj IDCC 816-2-79
Work TypeGR, STR, PVMT, SIGNS
 
0.4201190539.58356375.5929.9
CountyDENTON
HighwayFM 455
FromAT FM 2164 AND UNION HILL ROAD
To.
CSJ0816-02-080
Proj IDROW 816-2-80
Work TypeROW ACQUISITION & UTILITY ADJUSTMEN
 
0.42089637.0065703.0073.2
Work Order04-13-18
Work Began07-11-18
Work Completed
Time Computed07-11-18
Contract Working Days159
Addl Days Granted0
Working Days Charged79
Percent Time Used49
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0816-02-079
WOLFE CONSTRUCTION GROUP, INC. (2.04)
ALTUS TRAFFIC MANAGEMENT LLC (1.07)
VENUS CONSTRUCTION (14.26)
DUSTROL, INC. (2.46)
MARCOM"S MOWING SERVICE, LLC (2.39)
DAKOTA UTILITY CONTRACTORS, INC. (0.66)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.85)
Contract #03183217
Totals1280176.5830011.71422078.5932.9

CountyCOLLIN
HighwayFM 455
FromAT COLE'S BRANCH (W OF SH 289)
To.
CSJ0816-04-050
Proj IDBR 2019(009)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1521254483.460.000.0
CountyCOLLIN
HighwayFM 455
FromAT BILDERBACK CREEK (E OF SH 289)
To.
CSJ0816-04-051
Proj IDBR 2013(600)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1331096778.870.000.0
CountyCOLLIN
HighwayFM 455
FromAT HONEY CREEK (E OF SH 289)
To.
CSJ0816-04-052
Proj IDBR 2013(601)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2871767737.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days417
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09183011
Totals4119000.000.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS IN DISTRICT
ToAT DIAMOND INTERCHANGES
CSJ0918-00-263
Proj IDNH 2017(084)
Work TypePAVEMENT MARKINGS,SIGNS,SIGNALS
 
0.0011785330.87653774.1436.6
Work Order10-25-16
Work Began02-22-17
Work Completed
Time Computed12-24-16
Contract Working Days548
Addl Days Granted0
Working Days Charged309
Percent Time Used56
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-263
TOTAL HIGHWAY MAINTENANCE, LLC (8.18)
WG ENGINEERING & CONSTRUCTION, LLC (19.16)
Contract #09163210
Totals1785330.8777998.38653774.1436.6

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS DISTRICT
CSJ0918-00-267
Proj IDSTP 1702(453)
Work TypeTRAFFIC SIGNAL REHABILITATION
 
0.1001367285.031055613.7977.2
CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS COUNTY
CSJ0918-47-175
Proj IDSTP 1702(453)
Work TypeDMS INSTALLATION
 
0.100332183.00313888.9094.4
Work Order08-22-17
Work Began01-15-18
Work Completed
Time Computed11-26-17
Contract Working Days240
Addl Days Granted5
Working Days Charged178
Percent Time Used72
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-267
TCB FOUNDATION DRILLERS, INC. (3.40)
ALTUS TRAFFIC MANAGEMENT LLC (0.87)
WG ENGINEERING & CONSTRUCTION, LLC (7.21)
ODUM SERVICES, L.P. (2.10)
MEX DRILLING (0.23)
Contract #07173236
Totals1699468.0396638.661369502.6980.5

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-275
Proj IDSTP 2018(303)
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0012600000.00733526.0128.2
Work Order12-21-17
Work Began03-20-18
Work Completed
Time Computed03-20-18
Contract Working Days913
Addl Days Granted0
Working Days Charged220
Percent Time Used24
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-275
ROAD MASTER STRIPING LLC (8.90)
JR WEST TEXAS CONCRETE LLC (0.29)
Contract #11173214
Totals2600000.00102213.00733526.0128.2

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-283
Proj IDSTP 2018(504)
Work TypeNON-SITE SPECIFIC SIGNALS
 
0.0011468000.00654698.4444.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-18
Work Began05-27-18
Work Completed
Time Computed00-00-00
Contract Working Days548
Addl Days Granted0
Working Days Charged152
Percent Time Used27
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-283
ROAD MASTER STRIPING LLC (3.82)
Contract #01183012
Totals1468000.00175402.00654698.4444.5

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-286
Proj IDSTP 2019(178)
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0012294098.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days913
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-286
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10183221
Totals2294098.020.000.000.0

CountyNAVARRO
HighwayVA
FromAT VARIOUS LOCATIONS
To.
CSJ0918-18-135
Proj IDC 918-18-135
Work TypeREPLACE TURNDOWNS AND GUARDRAILS
 
12.9863230499.221112314.6934.4
Work Order08-13-18
Work Began08-22-18
Work Completed
Time Computed08-22-18
Contract Working Days240
Addl Days Granted0
Working Days Charged47
Percent Time Used19
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-135
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183236
Totals3230499.22252538.501112314.6934.4

CountyELLIS
HighwayVA
FromAT VARIOUS LOCATIONS
To.
CSJ0918-22-157
Proj IDC 918-22-157
Work TypeREPLACE TURNDOWNS AND GUARDRAILS
 
8.3794527134.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days246
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-22-157
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183222
Totals4527134.120.000.000.0

CountyDALLAS
HighwayCS
From2ND AVE SB AT TRIB OF WHITE ROCK CR
To.
CSJ0918-45-757
Proj IDBR 2007(303)
Work TypeREPL BR & APPRS
 
0.0851161950.951129074.1097.1
CountyDALLAS
HighwayCS
FromPARKDALE DR AT WHITE ROCK CRK TRIB
To.
CSJ0918-45-759
Proj IDBR 2007(304)
Work TypeREPL BR & APPRS
 
0.066694170.0046138.406.6
CountyDALLAS
HighwayCS
From2ND AVE NB AT WHITE ROCK CREEK
To.
CSJ0918-47-147
Proj IDBR 2017(293)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.072902462.75887216.6998.3
CountyDALLAS
HighwayCS
FromPARKDALE DR AT WHITE ROCK CRK TRIB
To.
CSJ0918-47-195
Proj IDROW 918-47-195
Work TypeUTILITY ADJUSTMENTS
 
0.066125215.300.000.0
Work Order09-20-17
Work Began12-11-17
Work Completed
Time Computed12-04-17
Contract Working Days381
Addl Days Granted0
Working Days Charged227
Percent Time Used59
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-757
LINDAMOOD CONSTRUCTION COMPANY, INC. (2.50)
STRIPING TECHNOLOGY, L.P. (2.57)
PREMIER PAVING, LTD. (4.01)
ATS DRILLING, INC. (5.55)
BUYERS BARRICADES, INC. (0.71)
OSCAR ORDUNO, INC. (1.45)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.77)
ACU CONSTRUCTION LLC (0.48)
BREDA COMPANY, INC. (0.42)
BOWMAN ENGINEERING & CONSULTING, INC (0.25)
JE CASEY, LLC (1.40)
PENHALL COMPANY (0.27)
W.O.E. CONSTRUCTION (0.05)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (2.66)
Contract #08173015
Totals2883799.0011251.102062429.1971.5

CountyDENTON
HighwayCS
FromS. BLUE MOUND RD
ToAT ELIZABETH CREEK IN FT WORTH
CSJ0918-46-274
Proj IDBR 1502(368)
Work TypeREPL BR & APPRS
 
0.120877705.46585582.2367.2
CountyDENTON
HighwayCR
FromHILLTOP RD 0.4 MI NORTH OF FM 407
ToAT LOVING BRANCH TRIB
CSJ0918-46-277
Proj IDBR 1602(008)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.061345671.42336618.6097.3
CountyDENTON
HighwayCS
FromMOBBERLY RD @ LITTLE ELM CREEK TRIB
To.
CSJ0918-46-287
Proj IDBR 1602(142)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.059425036.72405338.1495.3
Work Order07-12-17
Work Began09-06-17
Work Completed
Time Computed09-06-17
Contract Working Days286
Addl Days Granted0
Working Days Charged292
Percent Time Used102
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-274
TEXAS SHAFTS, INC. (3.95)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.83)
PEACHTREE CONSTRUCTION, LTD. (3.48)
COMEN ENTERPRISE LLC (3.13)
ALTUS TRAFFIC MANAGEMENT LLC (0.68)
STRIPING TECHNOLOGY, L.P. (0.59)
TEX OP CONSTRUCTION, LP (1.16)
MCL CONTRACTING, LLC (0.21)
Contract #06173246
Totals1648413.6061082.001327538.9780.8

CountyDENTON ETC
HighwayCS
FromMARSH LANE AT ROSEMEADE PKWY
To.
CSJ0918-46-280
Proj IDSTP 1702(357)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.0001284000.00684249.3653.2
Work Order07-12-17
Work Began11-02-17
Work Completed
Time Computed11-02-17
Contract Working Days190
Addl Days Granted14
Working Days Charged112
Percent Time Used54
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-280
AXIS CONTRACTING, INC. (19.61)
ROAD MASTER STRIPING LLC (4.86)
Contract #06173017
Totals1284000.0021520.00684249.3653.2

CountyDENTON ETC
HighwayCS
FromFRANKFORD RD AT MARSH LN
To.
CSJ0918-46-291
Proj IDSTP 2018(120)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.4001478000.00620913.9942.0
Work Order12-04-17
Work Began03-19-18
Work Completed
Time Computed03-19-18
Contract Working Days246
Addl Days Granted0
Working Days Charged135
Percent Time Used54
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-291
JR WEST TEXAS CONCRETE LLC (12.20)
ROAD MASTER STRIPING LLC (5.12)
Contract #10173008
Totals1478000.0083315.20620913.9942.0

CountyDALLAS
HighwayCS
FromCEDAR HILL STATE PARK
ToNEW CLARK RD IN CITY OF CEDAR HILL
CSJ0918-47-097
Proj IDSTP 2014(156)TE
Work TypeHIKE AND BIKE TRAIL
 
1.3682766088.001442276.3452.1
CountyDALLAS
HighwayFM 1382
FromAT CEDAR HILL STATE PARK SPINE RD
To.
CSJ1047-03-066
Proj IDC 1047-3-66
Work TypeGR, BS, ASPH PVMT, PVMT MKGS
 
0.2671257559.701442121.8799.9
CountyDALLAS
HighwayFM 1382
FromSOUTHEAST OF WEST SPINE ROAD
ToWEST OF NEW CLARK ROAD
CSJ1047-03-068
Proj IDCM 1602(423)
Work TypeINTERSECTION IMPROVEMENTS
 
0.6001197552.401259591.1199.9
CountyDALLAS
HighwayFM 1382
FromAT CEDAR HILL STATE PARK SPINE RD
To.
CSJ1047-03-070
Proj IDNH 1602(422)
Work TypeTRAF SIG
 
0.196827701.00943689.3599.9
Work Order11-16-16
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days365
Addl Days Granted7
Working Days Charged288
Percent Time Used77
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-097
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.94)
STRIPING TECHNOLOGY, L.P. (0.87)
STRIPING SYSTEMS, INC. (0.01)
COWBOY TRUCKING (0.11)
GJ SEEDING, LLC (3.14)
UNDER CONSTRUCTION INC. (0.09)
XTREEME SAWING & SEALING, INC. (0.09)
MABAK DIRECTIONAL DRILLING (0.09)
NEWSTAR DRILLING, INC (1.01)
Q. ROBERTS TRUCKING INCORPORATED (0.57)
TEXOP CONSTRUCTION (0.09)
ASHLAR CONTRACTING COMPANY (2.29)
Contract #07163040
Totals6048901.100.005087678.6784.1

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS ON STATE HIGHWAYS
ToIN DALLAS COUNTY
CSJ0918-47-114
Proj IDNH 1702(722)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012650440.801924527.1072.6
Work Order09-18-17
Work Began10-26-17
Work Completed
Time Computed10-23-17
Contract Working Days375
Addl Days Granted0
Working Days Charged252
Percent Time Used67
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-114
STRIPING TECHNOLOGY, L.P. (3.89)
TOTAL HIGHWAY MAINTENANCE, LLC (2.15)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (12.90)
Contract #08173214
Totals2650440.80136253.341924527.1072.6

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS ON STATE HIGHWAYS
ToIN DALLAS COUNTY
CSJ0918-47-115
Proj IDSTP 2019(039)
Work TypeCONSTRUCT CURB RAMPS AND SIDEWALKS
 
0.0012237635.190.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-115
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09183223
Totals2237635.190.000.000.0

CountyDALLAS
HighwayCS
FromROYAL LN AT ABRAMS RD
To.
CSJ0918-47-128
Proj IDSTP 2018(739)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.0001340240.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183018
Totals1340240.000.000.000.0

CountyDALLAS
HighwayCS
FromON BELTLINE RD, FROM DRY BRANCH
ToBEAR CREEK
CSJ0918-47-176
Proj IDSTP 2018(887)
Work TypeCHANNEL WORK,GRD
 
0.4732950293.01415511.6314.0
Work Order06-14-18
Work Began07-23-18
Work Completed
Time Computed07-23-18
Contract Working Days275
Addl Days Granted0
Working Days Charged68
Percent Time Used24
Contractor(s)
T KWEST GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-176
STOIC CIVIL CONSTRUCTION, INC. (45.69)
DEVOLL EROSION, L.L.C. (0.60)
XROADS, L.P. (1.38)
Contract #05183220
Totals2950293.0116938.20415511.6314.0

CountyNAVARRO
HighwayFM 667
FromSH 31
ToFM 744
CSJ0997-03-007
Proj IDSTP 2018(888)
Work TypeACP OVERLAY; GR; STR; PMVT MKGS
 
14.63212773111.871915727.6414.9
Work Order06-11-18
Work Began07-16-18
Work Completed
Time Computed07-16-18
Contract Working Days614
Addl Days Granted0
Working Days Charged76
Percent Time Used12
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0997-03-007
BAHENA CONSTRUCTION CO.,INC. (15.96)
COMEN ENTERPRISE LLC (0.86)
MURRAY CONSTRUCTION (0.78)
TRP CONSTRUCTION GROUP, LLC (1.28)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.49)
NIXON ENGINEERING (0.00)
Contract #05183204
Totals12773111.871009640.471915727.6414.9

CountyCOLLIN
HighwayFM 981
FromAT BEAR CREEK
To.
CSJ1012-03-018
Proj IDBR 2018(683)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.178986705.49945250.1095.7
CountyCOLLIN
HighwayFM 981
FromAT BEAR CREEK RELIEF
To.
CSJ1012-03-021
Proj IDBR 2018(684)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.169898831.61848166.5694.3
Work Order03-12-18
Work Began04-23-18
Work Completed
Time Computed04-23-18
Contract Working Days126
Addl Days Granted0
Working Days Charged109
Percent Time Used86
Contractor(s)
L & N BRIDGE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1012-03-018
MORRIS COUNTY CONTRACTORS, LLC (1.91)
PEACHTREE CONSTRUCTION, LTD. (6.32)
SOUTHEAST GRINDING & GROOVING, LLC (0.25)
STRIPING TECHNOLOGY, L.P. (1.04)
TEX OP CONSTRUCTION, LP (0.53)
TOTAL HIGHWAY MAINTENANCE, LLC (0.58)
WOLFE CONSTRUCTION GROUP, INC. (2.11)
WYLIE DRILLING & DRAINAGE, INC. (5.52)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (0.30)
Contract #02183004
Totals1885537.106119.141793416.6695.1

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7