Monthly State Let Construction Report For Dallas District As Of Mar 19, 2019 Page 5 Of 8

Last Update: Tuesday, March 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKAUFMAN
HighwayFM 148
FromUS 175
ToSH 34
CSJ0751-02-024
Proj IDSTP 1802(748)HES
Work TypeSHOULDER TEXTURING
 
10.52072112.300.000.0
CountyKAUFMAN
HighwayFM 148
FromFM 1390
ToSH 34
CSJ0751-02-026
Proj IDSTP 1802(747)
Work TypeGR,STR,PVMT,SIGNS
 
3.0523869159.45307230.007.9
CountyKAUFMAN
HighwayFM 148
FromSH 34
ToFM 1388
CSJ0751-03-039
Proj IDC 751-3-39
Work TypeGR,STR,PVMT,SIGNS
 
2.8453877275.421085160.0927.9
Work Order08-15-18
Work Began11-05-18
Work Completed
Time Computed11-05-18
Contract Working Days461
Addl Days Granted0
Working Days Charged73
Percent Time Used15
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0751-02-024
AREA WIDE PROTECTIVE, INC. (0.66)
COMEN ENTERPRISE LLC (1.09)
KENSAR LLC DBA S & S TRUCKING (1.90)
NIXON ENGINEERING (0.31)
STRIPE-A-ZONE, INC. (1.02)
BAKER & REID COMPANY, LLC (7.45)
A. L. CONSTRUCTION, LLC (0.53)
Contract #07183236
Totals7818547.17679152.291392390.0917.8

CountyKAUFMAN
HighwayFM 148
FromAT BUFFALO CREEK
To.
CSJ0751-02-025
Proj IDBR 1802(375)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2302718727.83443854.0316.3
Work Order08-15-18
Work Began10-30-18
Work Completed
Time Computed10-29-18
Contract Working Days375
Addl Days Granted0
Working Days Charged63
Percent Time Used16
Contractor(s)
B & E CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 0751-02-025
BREDA COMPANY, INC. (0.35)
COMEN ENTERPRISE LLC (2.32)
HODGES AND SON CONSTRUCTION COMPANY, INC. (3.91)
HUNTER DEMOLITION & WRECKING CORPORATION (1.90)
STRIPING TECHNOLOGY, L.P. (1.31)
WOLFE CONSTRUCTION GROUP, INC. (1.50)
Contract #07183232
Totals2718727.833250.00443854.0316.3

CountyKAUFMAN
HighwayFM 148
FromFM 1388
ToFM 3094 NORTH
CSJ0751-03-038
Proj IDSTP 1702(356)
Work TypeGR,STR,PVMT,SIGNS
 
3.0744087837.403995973.4397.7
Work Order07-20-17
Work Began10-23-17
Work Completed
Time Computed10-23-17
Contract Working Days286
Addl Days Granted0
Working Days Charged286
Percent Time Used100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0751-03-038
ALTUS TRAFFIC MANAGEMENT LLC (0.40)
BROCK ENVIRONMENTAL, LLC (1.08)
COMEN ENTERPRISE LLC (1.00)
KLP COMMERCIAL, LLC (3.04)
STRIPE-A-ZONE, INC. (0.20)
STRIPING TECHNOLOGY, L.P. (0.62)
WOLFE CONSTRUCTION GROUP, INC. (0.67)
NIXON ENGINEERING (0.00)
Contract #06173014
Totals4087837.405554.673995973.4397.7

CountyDENTON
HighwayFM 424
FromAT FISHTRAP ROAD
To.
CSJ0815-03-013
Proj IDSTP 2018(741)
Work TypeLANDSCAPE ENHANCEMENT
 
0.030113821.7951645.3045.3
CountyDENTON
HighwayFM 1171
FromEAST OF OLD CROSS TIMBERS RD
ToSHILOH ROAD
CSJ1311-01-056
Proj IDNH 2018(742)
Work TypeLANDSCAPE ENHANCEMENT
 
3.251570955.79211001.9736.9
CountyDENTON
HighwayFM 720
FromCOTTONWOOD TRAIL
ToELDORADO PARKWAY
CSJ1567-01-041
Proj IDSTP 2018(741)
Work TypeLANDSCAPE ENHANCEMENT
 
1.186170715.30175290.7599.9
CountyDENTON
HighwayFM 407
FromLANTANA TRAIL
To450' EAST OF EAST CARUTH LANE
CSJ1950-01-039
Proj IDSTP 2018(741)
Work TypeLANDSCAPE ENHANCEMENT
 
0.264670.00602.0089.8
Work Order05-17-18
Work Began07-05-18
Work Completed
Time Computed06-14-18
Contract Working Days255
Addl Days Granted0
Working Days Charged121
Percent Time Used47
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0815-03-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183218
Totals856162.883201.85438540.0251.2

CountyELLIS
HighwayFM 875
From0.6 MI W OF NORRELL
To0.3 MI N OF JORDAN
CSJ0815-08-031
Proj IDSTP 2016(990)HES
Work TypeWIDEN PAVEMENT
 
1.5001558868.081647708.0499.9
CountyELLIS
HighwayFM 875
FromFM 157
ToFM 663
CSJ0815-08-032
Proj IDSTP 2016(991)
Work TypeWIDEN PAVEMENT
 
5.2067240712.897067221.3597.6
Work Order06-23-16
Work Began07-27-16
Work Completed
Time Computed07-27-16
Contract Working Days287
Addl Days Granted0
Working Days Charged310
Percent Time Used108
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0815-08-031
SAN-ANN-CO., INC. (0.62)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.95)
BEAR CREEK CONSTRUCTION, LLC (9.31)
A BROTHERS MILLING, LLC (0.90)
COWBELL TRAFFIC SERVICES, INC. (0.10)
ODUM SERVICES, L.P. (1.55)
STRIPING TECHNOLOGY, L.P. (0.55)
STRIPING SYSTEMS, INC. (0.01)
ALTUS TRAFFIC MANAGEMENT LLC (0.11)
STRIPE-A-ZONE, INC. (0.10)
Contract #04163033
Totals8799580.9735622.308714929.3999.3

CountyDENTON
HighwayFM 455
FromAT FM 2164 AND UNION HILL ROAD
To.
CSJ0816-02-079
Proj IDCC 816-2-79
Work TypeGR, STR, PVMT, SIGNS
 
0.4201190539.581016589.4485.3
CountyDENTON
HighwayFM 455
FromAT FM 2164 AND UNION HILL ROAD
To.
CSJ0816-02-080
Proj IDROW 816-2-80
Work TypeROW ACQUISITION & UTILITY ADJUSTMEN
 
0.42089637.00108316.0099.9
Work Order04-13-18
Work Began07-11-18
Work Completed
Time Computed07-11-18
Contract Working Days159
Addl Days Granted7
Working Days Charged157
Percent Time Used94
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0816-02-079
WOLFE CONSTRUCTION GROUP, INC. (2.04)
ALTUS TRAFFIC MANAGEMENT LLC (1.07)
VENUS CONSTRUCTION (14.26)
DUSTROL, INC. (2.46)
MARCOM"S MOWING SERVICE, LLC (2.39)
DAKOTA UTILITY CONTRACTORS, INC. (0.66)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.85)
NOLAND"S CONSTRUCTION, LLC (2.39)
Contract #03183217
Totals1280176.58189987.641124905.4487.8

CountyCOLLIN
HighwayFM 455
FromAT COLE'S BRANCH (W OF SH 289)
To.
CSJ0816-04-050
Proj IDBR 2019(009)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1521254483.46444113.9135.4
CountyCOLLIN
HighwayFM 455
FromAT BILDERBACK CREEK (E OF SH 289)
To.
CSJ0816-04-051
Proj IDBR 2013(600)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1331096778.87100567.509.1
CountyCOLLIN
HighwayFM 455
FromAT HONEY CREEK (E OF SH 289)
To.
CSJ0816-04-052
Proj IDBR 2013(601)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2871767737.6769069.003.9
Work Order10-16-18
Work Began12-03-18
Work Completed
Time Computed12-03-18
Contract Working Days417
Addl Days Granted0
Working Days Charged51
Percent Time Used12
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-050
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.30)
WOLFE CONSTRUCTION GROUP, INC. (1.51)
STRIPING TECHNOLOGY, L.P. (1.85)
MORRIS COUNTY CONTRACTORS, LLC (3.99)
TEXAS SHAFTS, INC. (3.40)
DUSTROL, INC. (1.11)
PEACHTREE CONSTRUCTION, LTD. (9.72)
SOUTHERN CROSS CONTRACTORS, LLC (0.34)
Contract #09183011
Totals4119000.00282097.54613750.4114.9

CountyCOLLIN
HighwayFM 455
FromSH 289
ToCR 98
CSJ0816-04-096
Proj IDC 816-4-96
Work TypePROVIDE ADDTL PAVED SURFACE WIDTH
 
2.1752436804.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-20-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days168
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01193031
Totals2436804.350.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS IN DISTRICT
ToAT DIAMOND INTERCHANGES
CSJ0918-00-263
Proj IDNH 2017(084)
Work TypePAVEMENT MARKINGS,SIGNS,SIGNALS
 
0.0011785330.87666732.2137.3
Work Order10-25-16
Work Began02-22-17
Work Completed
Time Computed12-24-16
Contract Working Days548
Addl Days Granted0
Working Days Charged309
Percent Time Used56
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-263
TOTAL HIGHWAY MAINTENANCE, LLC (8.18)
WG ENGINEERING & CONSTRUCTION, LLC (19.16)
Contract #09163210
Totals1785330.870.00666732.2137.3

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS DISTRICT
CSJ0918-00-267
Proj IDSTP 1702(453)
Work TypeTRAFFIC SIGNAL REHABILITATION
 
0.1001367285.031333803.0297.5
CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS COUNTY
CSJ0918-47-175
Proj IDSTP 1702(453)
Work TypeDMS INSTALLATION
 
0.100332183.00359792.1499.9
Work Order08-22-17
Work Began01-15-18
Work Completed
Time Computed11-26-17
Contract Working Days240
Addl Days Granted5
Working Days Charged240
Percent Time Used97
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-267
TCB FOUNDATION DRILLERS, INC. (3.40)
ALTUS TRAFFIC MANAGEMENT LLC (0.87)
WG ENGINEERING & CONSTRUCTION, LLC (7.21)
ODUM SERVICES, L.P. (2.10)
MEX DRILLING (0.23)
Contract #07173236
Totals1699468.0329269.461693595.1699.6

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-275
Proj IDSTP 2018(303)
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0012600000.001062252.1340.8
Work Order12-21-17
Work Began03-20-18
Work Completed
Time Computed03-20-18
Contract Working Days913
Addl Days Granted0
Working Days Charged343
Percent Time Used37
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-275
ROAD MASTER STRIPING LLC (8.90)
JR WEST TEXAS CONCRETE LLC (0.29)
Contract #11173214
Totals2600000.0041249.401062252.1340.8

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-283
Proj IDSTP 2018(504)
Work TypeNON-SITE SPECIFIC SIGNALS
 
0.0011468000.001217571.8682.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-18
Work Began05-27-18
Work Completed
Time Computed00-00-00
Contract Working Days548
Addl Days Granted0
Working Days Charged275
Percent Time Used50
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-283
ROAD MASTER STRIPING LLC (3.82)
JR WEST TEXAS CONCRETE LLC (1.57)
Contract #01183012
Totals1468000.0045558.301217571.8682.9

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-286
Proj IDSTP 2019(178)
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0012294098.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days913
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-286
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10183221
Totals2294098.020.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-287
Proj IDSTP 2019(631)
Work TypeWRONG WAY DRIVING IMPLEMENTATION
 
0.001671750.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days540
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SELECT STRIPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-287
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193237
Totals671750.100.000.000.0

CountyKAUFMAN
HighwayCR
FromCR 301
ToAT BACHELOR CREEK
CSJ0918-11-089
Proj IDBR 2017(103)
Work TypeREPL BR & APPRS
 
0.081277209.520.000.0
CountyKAUFMAN
HighwayCR
FromCR 279; 0.01 MI E OF CR 301
ToAT KINGS CREEK
CSJ0918-11-093
Proj IDBR 2017(106)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.089364307.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days231
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-11-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01193228
Totals641516.520.000.000.0

CountyKAUFMAN
HighwayCR
FromCR 4083
ToAT COAL IRON CREEK
CSJ0918-11-090
Proj IDBR 2017(104)
Work TypeREPL BR & APPRS
 
0.069459476.750.000.0
CountyKAUFMAN
HighwayCR
FromON CR 151 AT PRAIRIE BRANCH
To.
CSJ0918-11-092
Proj IDBR 2017(105)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.076599916.250.000.0
CountyKAUFMAN
HighwayCR
FromCR4031B AT TRIBUTARY KINGS CREEK
To.
CSJ0918-11-095
Proj IDBR 2017(435)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.067327766.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-25-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-11-090
BOWMAN ENGINEERING & CONSULTING, INC. (0.37)
COMEN ENTERPRISE LLC (6.15)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.63)
J. H. ODEN CONTRACTING COMPANY (1.75)
Contract #01193023
Totals1387159.000.000.000.0

CountyNAVARRO
HighwayVA
FromAT VARIOUS LOCATIONS
To.
CSJ0918-18-135
Proj IDC 918-18-135
Work TypeREPLACE TURNDOWNS AND GUARDRAILS
 
12.9863230499.222007900.3462.1
Work Order08-13-18
Work Began08-22-18
Work Completed
Time Computed08-22-18
Contract Working Days240
Addl Days Granted0
Working Days Charged125
Percent Time Used52
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-135
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183236
Totals3230499.22249681.872007900.3462.1

CountyELLIS
HighwayVA
FromAT VARIOUS LOCATIONS
To.
CSJ0918-22-157
Proj IDC 918-22-157
Work TypeREPLACE TURNDOWNS AND GUARDRAILS
 
8.3794527134.12992257.2821.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-18
Work Began01-02-19
Work Completed
Time Computed00-00-00
Contract Working Days246
Addl Days Granted0
Working Days Charged40
Percent Time Used16
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-22-157
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183222
Totals4527134.12500387.84992257.2821.9

CountyDALLAS
HighwayCS
From2ND AVE SB AT TRIB OF WHITE ROCK CR
To.
CSJ0918-45-757
Proj IDBR 2007(303)
Work TypeREPL BR & APPRS
 
0.0851161950.951206081.8299.9
CountyDALLAS
HighwayCS
FromPARKDALE DR AT WHITE ROCK CRK TRIB
To.
CSJ0918-45-759
Proj IDBR 2007(304)
Work TypeREPL BR & APPRS
 
0.066694170.00349552.2650.3
CountyDALLAS
HighwayCS
From2ND AVE NB AT WHITE ROCK CREEK
To.
CSJ0918-47-147
Proj IDBR 2017(293)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.072902462.75906170.1499.9
CountyDALLAS
HighwayCS
FromPARKDALE DR AT WHITE ROCK CRK TRIB
To.
CSJ0918-47-195
Proj IDROW 918-47-195
Work TypeUTILITY ADJUSTMENTS
 
0.066125215.3087275.0069.6
Work Order09-20-17
Work Began12-11-17
Work Completed
Time Computed12-04-17
Contract Working Days381
Addl Days Granted0
Working Days Charged276
Percent Time Used72
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-757
LINDAMOOD CONSTRUCTION COMPANY, INC. (2.50)
STRIPING TECHNOLOGY, L.P. (2.57)
PREMIER PAVING, LTD. (4.01)
ATS DRILLING, INC. (5.55)
BUYERS BARRICADES, INC. (0.71)
OSCAR ORDUNO, INC. (1.45)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.77)
ACU CONSTRUCTION LLC (0.48)
BREDA COMPANY, INC. (0.42)
BOWMAN ENGINEERING & CONSULTING, INC (0.25)
JE CASEY, LLC (1.40)
PENHALL COMPANY (0.27)
W.O.E. CONSTRUCTION (0.05)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (2.66)
Contract #08173015
Totals2883799.006300.002549079.2288.3

CountyDENTON
HighwayCS
FromS. BLUE MOUND RD
ToAT ELIZABETH CREEK IN FT WORTH
CSJ0918-46-274
Proj IDBR 1502(368)
Work TypeREPL BR & APPRS
 
0.120877705.46839501.1399.9
CountyDENTON
HighwayCR
FromHILLTOP RD 0.4 MI NORTH OF FM 407
ToAT LOVING BRANCH TRIB
CSJ0918-46-277
Proj IDBR 1602(008)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.061345671.42342724.9899.1
CountyDENTON
HighwayCS
FromMOBBERLY RD @ LITTLE ELM CREEK TRIB
To.
CSJ0918-46-287
Proj IDBR 1602(142)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.059425036.72417395.6498.2
Work Order07-12-17
Work Began09-06-17
Work Completed
Time Computed09-06-17
Contract Working Days286
Addl Days Granted0
Working Days Charged367
Percent Time Used128
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-274
TEXAS SHAFTS, INC. (3.95)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.83)
PEACHTREE CONSTRUCTION, LTD. (3.48)
COMEN ENTERPRISE LLC (3.13)
ALTUS TRAFFIC MANAGEMENT LLC (0.68)
STRIPING TECHNOLOGY, L.P. (0.59)
TEX OP CONSTRUCTION, LP (1.16)
MCL CONTRACTING, LLC (0.21)
Contract #06173246
Totals1648413.60137555.691599621.7599.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8