Monthly State Let Construction Report For Dallas District As Of Nov 12, 2021 Page 5 Of 6

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayCS
FromOATES DR AT LA PRADA DR
ToIN THE CITY OF DALLAS
CSJ0918-47-215
Proj IDSTP 2021(337)HES
Work TypeTRAFFIC CONTROL DEVICES
 
1.0001886400.00495496.0026.2
Work Order04-01-21
Work Began08-03-21
Work Completed
Time Computed07-30-21
Contract Working Days367
Addl Days Granted0
Working Days Charged41
Percent Time Used11
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-215
ROAD MASTER STRIPING, LLC (4.92)
Contract #02213219
Totals1886400.00201675.00495496.0026.2

CountyDALLAS
HighwayCS
FromWEBB CHAPEL EXT AT LARGA DR
ToIN THE CITY OF DALLAS
CSJ0918-47-227
Proj IDSTP 2020(722)HES
Work TypeTRAFFIC CONTROL DEVICES
 
1.2001568006.49539527.3134.4
Work Order10-07-20
Work Began03-03-21
Work Completed
Time Computed02-03-21
Contract Working Days360
Addl Days Granted0
Working Days Charged146
Percent Time Used40
Contractor(s)
SELECT MAINTENANCE, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-227
ACT SAW CUTTING & REMOVAL (0.11)
E.P. DRILLING, INC. (0.00)
LINEAR TRAFFIC MARKINGS LLC (0.00)
AAA DRILLING FOUNDATION COMPANY, INC. (0.19)
COWBOY TRUCKING (0.47)
Contract #04203008
Totals1568006.493785.00539527.3134.4

CountyDALLAS
HighwayCS
FromHARRY HINES BLVD AT MARKET CENTER
ToIN THE CITY OF DALLAS
CSJ0918-47-247
Proj IDSTP 2021(611)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1374730.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROADWAY SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-247
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213227
Totals1374730.000.000.000.0

CountyDALLAS
HighwayCS
FromCORINTH ST AT MORREL AVE
ToIN THE CITY OF DALLAS
CSJ0918-47-250
Proj IDSTP 2022(087)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.2041403403.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-250
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213216
Totals1403403.900.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS INTERSECTIONS
ToIN THE DALLAS COUNTY
CSJ0918-47-279
Proj IDSTP 2021(279)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.2002125611.75744904.7035.0
Work Order03-01-21
Work Began05-10-21
Work Completed
Time Computed05-10-21
Contract Working Days200
Addl Days Granted0
Working Days Charged100
Percent Time Used50
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-279
BROCK CONSTRUCTION, LLC (0.43)
LINEAR TRAFFIC MARKINGS LLC (0.47)
PBJ CONSTRUCTION (6.69)
ROAD SOLUTIONS L.L.C. (4.92)
ROBIN STEEL LLC (2.42)
SLATON BROTHERS, INC. (2.77)
Contract #01213008
Totals2125611.75130090.74744904.7035.0

CountyDALLAS
HighwayVA
FromAT VARIOUS LOCATIONS
ToON IH 20 AND IH 30
CSJ0918-47-299
Proj IDNH 2B20(034)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1482132.002673091.0099.9
CountyDALLAS
HighwayVA
FromAT VARIOUS LOCATIONS
ToON SL 12 AND IH 35E
CSJ0918-47-300
Proj IDNH 2B20(035)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1271020.00119600.009.4
Work Order09-16-20
Work Began11-03-20
Work Completed
Time Computed11-03-20
Contract Working Days239
Addl Days Granted0
Working Days Charged65
Percent Time Used27
Contractor(s)
SELECT MAINTENANCE, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-299
DALLAS LITE AND BARRICADE, INC. (13.46)
Contract #07203029
Totals2753152.00894072.602792691.0099.9

CountyNAVARRO
HighwayFM 637
FromAT CEDAR CREEK (S OF FM 2859)
To.
CSJ0995-01-026
Proj IDBR 2021(538)
Work TypeBRIDGE REPLACEMENT
 
0.1311529560.35446964.6529.2
CountyELLIS
HighwayFM 308
FromAT DRAW (0.3 MI NW OF IH 35E)
To.
CSJ1393-01-015
Proj IDBR 2021(538)
Work TypeBRIDGE REPLACEMENT
 
0.1091182841.25105350.008.9
Work Order06-10-21
Work Began07-29-21
Work Completed
Time Computed07-09-21
Contract Working Days331
Addl Days Granted0
Working Days Charged61
Percent Time Used18
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0995-01-026
MORRIS COUNTY CONTRACTORS, L.L.C. (3.89)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.95)
HERMANOS STEEL, LLC (0.78)
TEXAS TRAFFIC AND BARRICADE, LLC (2.48)
TRP CONSTRUCTION GROUP, LLC (2.01)
PEACHTREE CONSTRUCTION, LTD. (8.24)
DUSTROL, INC. (0.61)
Contract #05213022
Totals2712401.608755.90552314.6520.3

CountyCOLLIN
HighwayFM 545
From0.073 MILE WEST OF OLD VALDASTA RD
To0.040 MILE EAST OF FM 1377
CSJ1012-02-036
Proj IDSSW 1012-2-36
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.6891057380.310.000.0
CountyCOLLIN
HighwayFM 545
From0.012 MILE WEST OF FM 2933
To0.103 MILE EAST OF CR 1095
CSJ1012-02-037
Proj IDSSW 1012-2-37
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.6801261948.70102120.508.0
CountyCOLLIN
HighwayFM 545
From0.026 MILE EAST OF L'HOTE LANE
ToBS 78(D)
CSJ1012-02-038
Proj IDSSW 1012-2-38
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.736274017.2013530.204.9
CountyCOLLIN
HighwayFM 545
FromFM 2933
ToBS 78D
CSJ1012-02-042
Proj IDF 2021(790)
Work TypeREHABILITATION OF EXISTING ROAD
 
9.1965657091.65457959.908.0
Work Order08-25-21
Work Began09-24-21
Work Completed
Time Computed09-24-21
Contract Working Days450
Addl Days Granted0
Working Days Charged23
Percent Time Used5
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1012-02-036
TEXAS TRAFFIC AND BARRICADE, LLC (0.45)
ROAD SOLUTIONS L.L.C. (0.39)
A. E. MOORE CONSTRUCTION, INC. (1.47)
DUSTROL, INC. (0.96)
BAHENA CONSTRUCTION CO.,INC. (13.81)
FORTSON CONTRACTING, INC. (0.82)
SOUTHERN CROSS CONTRACTORS, LLC (1.34)
STRIPE-A-ZONE, INC. (1.31)
CHEROKEE SERVICES (0.07)
PEACHTREE CONSTRUCTION, LTD. (19.57)
FARR FOUNDATION, INC. (3.24)
Contract #07213214
Totals8250437.86573610.60573610.606.9

CountyCOLLIN
HighwayFM 546
From0.304 MI S OF PRINCE LANE
To0.014 MI W OF THE CROSSING DRIVE
CSJ1013-01-034
Proj IDSTP 2020(487)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.7581994656.111957391.1098.1
CountyCOLLIN
HighwayFM 546
FromWEST OF ALMETA LANE
ToTHE CROSSING DRIVE
CSJ1013-01-035
Proj IDSTP 2020(488)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.0902247334.452129903.5894.7
Work Order07-20-20
Work Began08-17-20
Work Completed
Time Computed08-19-20
Contract Working Days262
Addl Days Granted0
Working Days Charged238
Percent Time Used90
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-034
AREA WIDE PROTECTIVE, INC. (0.51)
BAHENA CONSTRUCTION CO.,INC. (20.54)
FORTSON CONTRACTING, INC. (4.02)
MARCOM"S MOWING SERVICE, LLC (1.38)
A. E. MOORE CONSTRUCTION, INC. (1.33)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (21.46)
TEXOP CONSTRUCTION (2.09)
TOTAL HIGHWAY MAINTENANCE, LLC (0.13)
TRP CONSTRUCTION GROUP, LLC (0.94)
CATACON, INC. (1.18)
WITHERS CONSTRUCTION, LLC (0.23)
HIGHWAY 19 CONSTRUCTION LLC (0.65)
Contract #06203210
Totals4241990.560.004087294.6896.3

CountyELLIS
HighwayFM 780
FromFM 660
ToEND OF MAINTENANCE
CSJ1048-03-011
Proj IDC 1048-3-11
Work TypeREHABILITATION OF EXISTING ROAD
 
4.9966868176.574150647.9460.4
Work Order11-19-20
Work Began02-05-21
Work Completed
Time Computed02-05-21
Contract Working Days263
Addl Days Granted0
Working Days Charged174
Percent Time Used66
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1048-03-011
PEACHTREE CONSTRUCTION, LTD. (1.41)
SYNERGY SIGNS & SERVICES LLC (0.56)
BRENDA PRICE TRUCKING (0.01)
DUSTROL, INC. (1.57)
FORTSON CONTRACTING, INC. (1.02)
TEXAS SWPPP SERVICES (2.47)
TOTAL HIGHWAY MAINTENANCE, LLC (0.72)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.84)
STATEWIDE TRUCKING CORP. (0.00)
Contract #10203209
Totals6868176.57479592.314150647.9460.4

CountyDALLAS
HighwayIH 30
FromSH 161
ToNW 7TH STREET IN GRAND PRAIRIE
CSJ1068-04-119
Proj IDNH 1802(544)
Work TypeGR, STRS & PAV
 
1.95637840877.8444239952.5199.9
Work Order07-19-18
Work Began10-08-18
Work Completed
Time Computed09-17-18
Contract Working Days543
Addl Days Granted186
Working Days Charged728
Percent Time Used99
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-119
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.31)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.50)
STRIPING TECHNOLOGY, L.P. (0.66)
PENHALL COMPANY (AUSTIN) (0.01)
TEX OP CONSTRUCTION, LP (0.12)
STORM WATER MANAGEMENT, INC. (0.43)
AREA WIDE PROTECTIVE, INC. (0.18)
LAYFIELD CONSTRUCTION, INC (0.14)
PANIOLO CONSTRUCTION SERVICES, LLC (3.01)
OSCAR ORDUNO, INC. (7.12)
MICA CORPORATION (5.06)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (0.16)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.09)
W.O.E. CONSTRUCTION (1.60)
BOWMAN ENGINEERING & CONSULTING, INC. (1.20)
J.H. PAINTING COMPANY (0.30)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.06)
ANCORTEX, INC. (4.44)
PROTEX EROSION CONTROL, LLC (0.43)
BRENDA PRICE TRUCKING (0.21)
LINDAMOOD DEMOLITION, INC. (0.03)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
DURABLE SPECIALTIES, INC. (1.37)
COMEN ENTERPRISE LLC (0.12)
Contract #06183243
Totals37840877.8484081.2044239952.5199.9

CountyDENTON
HighwayFM 1171
FromLONG PRAIRIE ROAD
ToNORTH GARDEN RIDGE BLVD
CSJ1311-01-058
Proj IDF 2022(063)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
2.170313460.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days87
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213222
Totals313460.500.000.000.0

CountyNAVARRO
HighwayFM 744
FromFM 1578
ToFM 55
CSJ1663-03-017
Proj IDSTP 2020(182)
Work TypeREHABILITATION OF EXISTING ROAD
 
11.09112342946.367501136.4160.7
Work Order12-16-19
Work Began03-23-20
Work Completed
Time Computed03-23-20
Contract Working Days531
Addl Days Granted0
Working Days Charged395
Percent Time Used74
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1663-03-017
D. I. J. CONSTRUCTION, INC. (0.76)
FORTSON CONTRACTING, INC. (1.17)
J & M CONTRACTING, COMPANY (13.77)
MURRAY CONSTRUCTION (0.98)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48)
MASSEY CONTRACTORS, LLC (1.97)
Contract #11193204
Totals12342946.36312063.187501136.4160.7

CountyNAVARRO
HighwayFM 744
FromFM 55
ToFM 1126 WEST
CSJ1663-03-020
Proj IDC 1663-3-20
Work TypeRESTORATION
 
6.0685714506.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days370
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1663-03-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213004
Totals5714506.650.000.000.0

CountyDENTON
HighwayFM 2181
FromLILLIAN MILLER IN DENTON
ToWEST OF FM 2499 (BARREL STRAP RD)
CSJ2054-02-015
Proj IDSTP 1702(730)
Work TypeGRADING, BASE, ACP AND STRUCTURES
 
3.51130199398.4019332493.8264.0
CountyDENTON
HighwayFM 2181
FromLILLIAN MILLER IN DENTON
ToWEST OF FM 2499 (BARREL STRAP RD)
CSJ2054-02-017
Proj IDROW 2054-2-17
Work TypeROW ACQ., RELO ASSIST. & UTIL. ADJ.
 
2.5964841751.744751060.2498.1
Work Order08-28-17
Work Began11-21-17
Work Completed
Time Computed09-27-17
Contract Working Days678
Addl Days Granted524
Working Days Charged1,133
Percent Time Used94
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 2054-02-015
WILDSTONE CONSTRUCTION, LLC (24.68)
DUSTROL, INC. (0.65)
FORTSON CONTRACTING, INC. (0.03)
ROADWAY SOLUTIONS, INC. (4.68)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.01)
TOTAL HIGHWAY MAINTENANCE, LLC (0.76)
W.O.E. CONSTRUCTION (6.35)
RPM XCONSTRUCTION, LLC (7.02)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (11.13)
DUKE"S TREE SERVICE (0.08)
J.H. PAINTING COMPANY (0.17)
C&M PRECAST (1.42)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.52)
GMNW,LLC DBA TRINITY UTILITIES & BORING (3.94)
KEY"S TAPPING & CONSTRUCTION SERVICES, INC. (0.02)
UTILITY AND ENVIRONMENTAL SERVICES, INCORPORATED (0.00)
BURTON TRUCKING (0.06)
BREDA COMPANY, INC. (0.72)
RANGELINE PIPELINE SERVICES, LLC (0.28)
SMITH LAWN AND TREE (0.08)
UNIVERSAL FENCE COMPANY, INC. (0.02)
CIRCLE H CONTRACTORS, L.P. (1.63)
ZACHRY CONSTRUCTION CORPORATION (114.20)
DUSTROL, INC. (0.63)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (10.65)
RPM XCONSTRUCTION, LLC (3.68)
WYLIE DRILLING & DRAINAGE, INC. (0.71)
TEXAS SWPPP SERVICES (0.12)
RENAISSANCE CONTRACTORS, INC. (26.90)
BREDA COMPANY, INC. (0.81)
SKAGGS ROAD BORING, INC. (0.81)
AMERICAN LIGHTING AND SIGNALIZATION, LLC (4.79)
J.H. PAINTING COMPANY (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.95)
UNIVERSAL FENCE COMPANY, INC. (0.01)
COMEN ENTERPRISE LLC (0.22)
CIRCLE H CONTRACTORS, L.P. (0.65)
W.O.E. CONSTRUCTION, INC. (0.52)
FARR FOUNDATION, INC. (0.21)
ATCO, LLC (0.82)
HILL BROTHERS CONSTRUCTION COMPANY, INC. (0.01)
CGC LOGISTICS (0.00)
Contract #07173013
Totals35041150.141027122.3824083554.0668.7

CountyCOLLIN
HighwayFM 2478
FromUS 380
ToFM 1461
CSJ2351-01-017
Proj IDSTP 2B20(255)
Work TypeWIDEN NON-FREEWAY
 
24834021.3810218802.8441.1
CountyCOLLIN
HighwayFM 2478
FromFM 1461
ToNORTH OF FM 1461
CSJ2351-02-014
Proj IDC 2351-2-14
Work TypeWIDEN NON-FREEWAY
 
3219051.47234286.537.2
Work Order10-28-20
Work Began01-25-21
Work Completed
Time Computed01-25-21
Contract Working Days584
Addl Days Granted0
Working Days Charged221
Percent Time Used37
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2351-01-017
AREA WIDE PROTECTIVE, INC. (0.26)
SOUTHWEST EROSION CONTROL, INC. (0.74)
PRIMATE CONSTRUCTION, LP (0.24)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.14)
FARR FOUNDATION, INC. (0.31)
W.O.E. CONSTRUCTION, INC. (0.32)
BARRICADES UNLIMITED (1.01)
SCOTT DERR PAINTING CO, LLC (0.02)
WYLIE DRILLING & DRAINAGE, INC. (0.34)
SOUTHERN CROSS CONTRACTORS, LLC (0.38)
STOIC CIVIL CONSTRUCTION, INC. (0.83)
DFW REBAR, INC. (0.83)
MELS ELECTRIC, L.P. (3.76)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
PANTHER CREEK TRANSPORTATION, INC. (1.61)
OSCAR ORDUNO, INC. (0.31)
HERMANOS STEEL, LLC (0.00)
3PAZ TRUCKING LLC (0.01)
LOLLAR CONSTRUCTION GROUP LLC (4.51)
Contract #09203205
Totals28053072.852338854.4010453089.3737.2

CountyDENTON
HighwayFM 2449
From0.2M EAST OF FM 156
To0.7M WEST OF IH 35W
CSJ2352-02-023
Proj IDSTP 2021(153)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.3582660850.061594628.0159.9
CountyDENTON
HighwayFM 2449
From0.2 M EAST OF FM 156
To0.7M WEST OF IH 35W
CSJ2352-02-025
Proj IDSTP 2021(154)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.3583242124.43780318.3424.0
Work Order04-16-21
Work Began06-03-21
Work Completed
Time Computed06-03-21
Contract Working Days301
Addl Days Granted5
Working Days Charged102
Percent Time Used33
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 2352-02-023
BARRICADES UNLIMITED (1.91)
DUSTROL, INC. (3.03)
SOUTHERN CROSS CONTRACTORS, LLC (0.39)
FORTSON CONTRACTING, INC. (0.65)
JR WEST TEXAS CONCRETE LLC (13.53)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.54)
PEACHTREE CONSTRUCTION, LTD. (4.61)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.24)
Contract #03213220
Totals5902974.49254916.492374946.3540.2

CountyDALLAS
HighwayIH 635
FromIH 20
ToIH 30
CSJ2374-02-156
Proj IDF 2021(732)
Work TypeOVERLAY
 
8.18111519821.62515216.254.4
Work Order08-31-21
Work Began10-04-21
Work Completed
Time Computed10-04-21
Contract Working Days222
Addl Days Granted0
Working Days Charged13
Percent Time Used5
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-156
FORTSON CONTRACTING, INC. (5.51)
IBCTX, LLC (10.21)
O. TREVINO CONSTRUCTION, LLC (6.10)
SIOUX EROSION CONTROL, INC. (0.41)
STRIPING TECHNOLOGY, L.P. (1.71)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.20)
TEXAS TRAFFIC AND BARRICADE, LLC (0.19)
TEXOP CONSTRUCTION (3.74)
W.O.E. CONSTRUCTION, INC. (0.34)
BRENDA PRICE TRUCKING (0.29)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
Contract #07213206
Totals11519821.62515216.25515216.254.4

CountyDALLAS
HighwayIH 20
FromAT BONNIE VIEW RD
ToIN CITY OF DALLAS
CSJ2374-03-074
Proj IDSTP 2021(539)MM
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.0223246150.50390450.0012.0
Work Order06-10-21
Work Began09-21-21
Work Completed
Time Computed09-21-21
Contract Working Days267
Addl Days Granted0
Working Days Charged25
Percent Time Used9
Contractor(s)
IBCTX, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-074
AXIS CONTRACTING, INC. (8.90)
CHOCTAW ERECTORS, INC. (6.95)
DALLAS LITE AND BARRICADE, INC. (2.58)
G J SEEDING, LLC (2.67)
ROAD MASTER STRIPING, LLC (0.57)
ROAD SOLUTIONS L.L.C. (11.74)
TEXAS SHAFTS, INC. (3.01)
Contract #05213213
Totals3246150.50174700.00390450.0012.0

CountyDALLAS
HighwayIH 20
FromWEST OF CARRIER PARKWAY
ToFM 1382 (BELT LINE ROAD)
CSJ2374-04-049
Proj IDNH 1602(427)
Work TypeCONSTRUCTION OF FRONTAGE ROAD
 
2.37254241512.3053168000.3198.0
Work Order07-20-17
Work Began01-18-18
Work Completed
Time Computed01-02-18
Contract Working Days791
Addl Days Granted150
Working Days Charged941
Percent Time Used100
Contractor(s)
FLUOR HEAVY CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-049
BUYERS BARRICADES, INC. (0.02)
WOLFE CONSTRUCTION GROUP, INC. (0.20)
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (5.17)
COMEN ENTERPRISE LLC (0.73)
A R DANIEL CONSTRUCTION SERVICES, INC. (1.14)
W.O.E. CONSTRUCTION (0.01)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.48)
A BROTHERS MILLING, LLC (0.25)
THELIN RECYCLING COMPANY, L.P. (0.03)
COWBOY TRUCKING (2.43)
KLP COMMERCIAL, LLC (1.86)
TEXAS SHAFTS, INC. (4.74)
ROYAL REBAR (0.79)
RENAISSANCE CONTRACTORS, INC. (0.00)
FARR FOUNDATION, INC. (1.12)
PANIOLO CONSTRUCTION SERVICES, LLC (4.97)
STRAIGHT LINE SAWING & SEALING, INC. (0.12)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.26)
PANTHER CREEK TRANSPORTATION, INC. (0.11)
W.O.E. CONSTRUCTION (1.11)
ALLIANCE GEOTECHNICAL GROUP, INC. (0.32)
SISK BORING AND TUNNELING INC (0.06)
SCOTT DERR PAINTING CO, LLC (0.45)
THE F.A. BARTLETT TREE EXPERT COMPANY (0.05)
SOUTHEAST GRINDING & GROOVING, LLC (0.04)
KHONSU ENTERPRISE LLC (0.09)
Q. ROBERTS TRUCKING INCORPORATED (0.06)
Contract #06173002
Totals54241512.30858219.7853168000.3198.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6