Monthly State Let Construction Report For Dallas District As Of Nov 12, 2021 Page 4 Of 6

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKAUFMAN
HighwayFM 148
FromFM 3094 SOUTH
ToFM 2613
CSJ0751-03-041
Proj IDF 2021(906)
Work TypeRESTORATION
 
2.0702707441.130.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-21
Work Began11-02-21
Work Completed
Time Computed00-00-00
Contract Working Days111
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0751-03-041
CATOCON, INC. (1.10)
DUSTROL, INC. (2.09)
FORTSON CONTRACTING, INC. (1.19)
INLET STRUCTURES SPECIALTIES (4.34)
STRIPE-A-ZONE, LLC (0.93)
SYNERGY SIGNS & SERVICES LLC (0.66)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.52)
TEXAS SWPPP SERVICES (1.00)
PEACHTREE CONSTRUCTION, LTD. (19.76)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.37)
BRENDA PRICE TRUCKING (0.85)
Contract #07213229
Totals2707441.130.000.000.0

CountyCOLLIN
HighwayFM 455
FromAT COLE'S BRANCH (W OF SH 289)
To.
CSJ0816-04-050
Proj IDBR 2019(009)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1521254483.461094430.9491.9
CountyCOLLIN
HighwayFM 455
FromAT BILDERBACK CREEK (E OF SH 289)
To.
CSJ0816-04-051
Proj IDBR 2013(600)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1331096778.871010993.4992.1
CountyCOLLIN
HighwayFM 455
FromAT HONEY CREEK (E OF SH 289)
To.
CSJ0816-04-052
Proj IDBR 2013(601)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2871767737.671631228.0792.2
Work Order10-16-18
Work Began12-03-18
Work Completed
Time Computed12-03-18
Contract Working Days417
Addl Days Granted167
Working Days Charged645
Percent Time Used110
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-050
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.30)
WOLFE CONSTRUCTION GROUP, INC. (1.51)
STRIPING TECHNOLOGY, L.P. (1.85)
MORRIS COUNTY CONTRACTORS, LLC (3.99)
TEXAS SHAFTS, INC. (3.40)
DUSTROL, INC. (1.11)
PEACHTREE CONSTRUCTION, LTD. (9.72)
SOUTHERN CROSS CONTRACTORS, LLC (0.34)
MCL CONTRACTING, LLC (0.17)
PRIMATE CONSTRUCTION, LP (0.18)
Contract #09183011
Totals4119000.0025075.333736652.5092.1

CountyDENTON
HighwayFM 428
FromUS 377
ToFM 1385
CSJ0817-01-024
Proj IDC 817-1-24
Work TypeREHABILITATION OF EXISTING ROAD
 
5.3798828849.782893453.9932.7
Work Order10-21-20
Work Began01-04-21
Work Completed
Time Computed01-04-21
Contract Working Days440
Addl Days Granted0
Working Days Charged179
Percent Time Used40
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0817-01-024
BARRICADES UNLIMITED (2.30)
DUSTIN ALLEN, INC. (3.23)
DUSTROL, INC. (0.85)
JOE"S TREE SERVICE (1.13)
PEACHTREE CONSTRUCTION, LTD. (4.03)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.54)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36)
MARCOM"S MOWING SERVICE, LLC (0.53)
Contract #09203207
Totals8828849.78235776.672893453.9932.7

CountyDENTON
HighwayFM 428
FromSHERMAN DR
ToPLUM ST
CSJ0817-01-027
Proj IDF 2022(180)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.150248457.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0817-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213221
Totals248457.800.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-286
Proj IDSTP 2019(178)
Work TypeNON-SITE SPECIFIC TRAFFIC SIGNALS
 
0.0012294098.022281446.2999.4
Work Order11-16-18
Work Began04-18-19
Work Completed
Time Computed04-15-19
Contract Working Days913
Addl Days Granted0
Working Days Charged853
Percent Time Used93
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-286
JSG ENTERPRISES LLC (1.63)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.17)
ROAD MASTER STRIPING, LLC (3.73)
WG ENGINEERING & CONSTRUCTION, LLC (4.64)
MEDELLIN HDD LLC (1.13)
JR WEST TEXAS CONCRETE LLC (1.17)
Contract #10183221
Totals2294098.021561.202281446.2999.4

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-326
Proj IDC 918-00-326
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
202386.60997701.1299.9
CountyDALLAS
HighwayVA
FromVARIOUS INTERSECTIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-361
Proj IDC 918-00-361
Work TypeTRAFFIC CONTROL DEVICES
 
1447179.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-326
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213211
Totals1649565.66326945.12997701.1260.4

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-328
Proj IDSTP 2B20(253)
Work TypeTRAFFIC CONTROL DEVICES
 
2315000.00676911.0329.2
Work Order10-14-20
Work Began03-22-21
Work Completed
Time Computed02-11-21
Contract Working Days913
Addl Days Granted0
Working Days Charged218
Percent Time Used23
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-328
ROAD MASTER STRIPING, LLC (0.00)
Contract #09203013
Totals2315000.0014960.00676911.0329.2

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-330
Proj IDC 918-00-330
Work TypeTRAFFIC CONTROL DEVICES
 
2444000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-14-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days913
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-330
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213010
Totals2444000.000.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToON US 75, US 380 AND SL 12
CSJ0918-00-340
Proj IDNH 2B20(033)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
424176.00238492.9056.2
CountyCOLLIN
HighwayFM 1778
FromBS 78 F
ToFM 547
CSJ1735-01-016
Proj IDC 1735-1-16
Work TypeREHABILITATION OF EXISTING ROAD
 
4.6664417316.844225803.1595.6
CountyCOLLIN
HighwayFM 1778
FromBS 78F
ToCR 597
CSJ1735-01-017
Proj IDSTP 2B20(036)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.9611033623.751096942.3299.9
Work Order08-14-20
Work Began09-17-20
Work Completed
Time Computed09-13-20
Contract Working Days260
Addl Days Granted0
Working Days Charged259
Percent Time Used99
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-340
BAHENA CONSTRUCTION CO.,INC. (15.45)
FORTSON CONTRACTING, INC. (0.28)
A. E. MOORE CONSTRUCTION, INC. (2.14)
J. H. ODEN CONTRACTING COMPANY (2.31)
PREMIER PAVING, LTD. (17.00)
SYNERGY SIGNS & SERVICES LLC (0.78)
TEXOP CONSTRUCTION (0.73)
TOTAL HIGHWAY MAINTENANCE, LLC (6.39)
AREA WIDE PROTECTIVE, INC. (0.92)
HDZ CONSTRUCTION (0.13)
Contract #07203211
Totals5875116.5934812.005561238.3794.6

CountyDALLAS
HighwayVA
FromDIGITAL VIDEO PROJECT
To.
CSJ0918-00-353
Proj IDCM 2021(085)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
1052807.67519021.0349.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-19-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-353
VISTACOM CONTROL ROOM SOLUTIONS INC. (0.00)
Contract #10203014
Totals1052807.670.00519021.0349.2

CountyDALLAS
HighwayVA
FromON STATE FACILITIES
ToIN THE DALLAS DISTRICT
CSJ0918-00-356
Proj IDCM 2B20(281)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
3364193.431651412.7749.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-08-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days214
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-356
FC TRAFFIC CONTROL, INC. (0.00)
Contract #08203069
Totals3364193.430.001651412.7749.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-360
Proj IDC 918-00-360
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1646740.691288088.6878.2
Work Order10-28-20
Work Began11-09-20
Work Completed
Time Computed11-09-20
Contract Working Days218
Addl Days Granted0
Working Days Charged207
Percent Time Used94
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-360
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09203216
Totals1646740.690.001288088.6878.2

CountyDALLAS
HighwayVA
FromON IH 35E FROM DALLAS/DENTON COUNTY
ToN OF OAK ST.
CSJ0918-00-377
Proj IDF 2022(179)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
22.43274657.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-377
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213220
Totals74657.200.000.000.0

CountyKAUFMAN
HighwayCR
FromAT SOUTH DRAW
To.
CSJ0918-11-096
Proj IDBR 1902(106)
Work TypeBRIDGE REPLACEMENT
 
0.066425983.03337248.3779.1
CountyKAUFMAN
HighwayCR
FromAT NORTH DRAW
To.
CSJ0918-11-098
Proj IDBR 1902(117)
Work TypeBRIDGE REPLACEMENT
 
0.057413537.35235050.0856.8
Work Order02-03-21
Work Began02-23-21
Work Completed
Time Computed02-23-21
Contract Working Days248
Addl Days Granted0
Working Days Charged168
Percent Time Used67
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-11-096
LINEAR TRAFFIC MARKINGS LLC (0.58)
PANOLA SIGN & BARRICADE, INC. (2.02)
PREMIER PAVING, LTD. (5.01)
WOLFE CONSTRUCTION GROUP, INCORPORATED (2.17)
HODGES AND SON CONSTRUCTION COMPANY, INC. (10.80)
TORO BRAVO CONSTRUCTION, LLC (0.43)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.02)
Contract #11203230
Totals839520.3857496.17572298.4568.1

CountyDENTON
HighwayVA
FromVARIOUS LOCATIONS ON STATE HIGHWAYS
ToIN DENTON COUNTY
CSJ0918-46-279
Proj IDSTP 1902(221)
Work TypePED
 
0.0012979676.752587167.8888.6
Work Order08-16-19
Work Began10-17-19
Work Completed
Time Computed10-17-19
Contract Working Days190
Addl Days Granted100
Working Days Charged358
Percent Time Used123
Contractor(s)
J.R. POPE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-279
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (5.51)
KITECO PROPERTY SOLUTIONS INC. (4.15)
LS HIGHWAY PRODUCTS, INC. (0.29)
AMERICAN LIGHTING AND SIGNALIZATION, LLC (3.29)
Contract #07193020
Totals2979676.752446.612587167.8888.6

CountyDALLAS
HighwayFD
FromON WEST SPINE ROAD
ToWITHIN THE CEDAR HILL STATE PARK
CSJ0918-47-096
Proj IDC 918-47-96
Work TypeTEXAS PARK AND WILDLIFE
 
4.2704547348.280.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-18-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days112
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213027
Totals4547348.280.000.000.0

CountyDALLAS
HighwayCS
FromMALLOY BRIDGE RD AT PARSONS SLOUGH
To.
CSJ0918-47-148
Proj IDBR 2018(785)
Work TypeBRIDGE REPLACEMENT
 
0.0861766278.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-148
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213211
Totals1766278.500.000.000.0

CountyDALLAS
HighwayCS
FromDNT-INWOOD AT HARVEST HILL RD
ToIN THE CITY OF DALLAS
CSJ0918-47-179
Proj IDSTP 2020(580)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.2001480000.001383667.3293.4
Work Order07-20-20
Work Began11-16-20
Work Completed
Time Computed11-16-20
Contract Working Days222
Addl Days Granted0
Working Days Charged175
Percent Time Used78
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-179
ROAD MASTER STRIPING, LLC (3.51)
Contract #02203221
Totals1480000.00143634.951383667.3293.4

CountyDALLAS
HighwayCS
FromON ILLINOIS AVE AT KIEST BLVD
ToIN THE CITY OF DALLAS
CSJ0918-47-180
Proj IDSTP 2020(180)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.2001694000.001655282.1997.7
Work Order03-31-20
Work Began07-30-20
Work Completed
Time Computed07-30-20
Contract Working Days180
Addl Days Granted0
Working Days Charged176
Percent Time Used97
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-180
ROAD MASTER STRIPING, LLC (4.16)
JR WEST TEXAS CONCRETE LLC (18.61)
Contract #11193026
Totals1694000.0014778.001655282.1997.7

CountyDALLAS
HighwayCS
FromZANGS BLVD AT CLARENDEN DR
ToIN THE CITY OF DALLAS
CSJ0918-47-212
Proj IDSTP 2021(496)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012040000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-212
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213215
Totals2040000.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6