Monthly State Let Construction Report For Dallas District As Of Oct 11, 2018 Page 1 Of 8

Last Update: Thursday, October 11, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwaySH 66
FromWESTERN CITY LIMIT OF ROWLET
ToDALROCK RD
CSJ0009-03-045
Proj IDNH 1702(443)
Work TypeLANDSCAPE ENHANCEMENT
 
4.4841398334.691353334.3096.7
CountyROCKWALL
HighwaySH 66
FromDALROCK ROAD
ToHERITAGE PARKWAY
CSJ0009-04-068
Proj IDNH 1702(443)
Work TypeLANDSCAPE ENHANCEMENT
 
0.890351665.31347481.9798.8
Work Order07-14-17
Work Began08-07-17
Work Completed
Time Computed08-07-17
Contract Working Days253
Addl Days Granted0
Working Days Charged231
Percent Time Used91
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-03-045
BUYERS BARRICADES, INC. (0.79)
DOWN UNDER CONSTRUCTION (2.76)
WRECKHOUSE DEMOLITION, LLC (10.00)
KICKER UNDERGROUND CONSTRUCTION, LLC (3.25)
Contract #06173245
Totals1750000.0018335.581700816.2797.1

CountyDALLAS
HighwaySH 66
FromDEXHAM RD TO DALROCK RD
ToIN THE CITY OF ROWLETT
CSJ0009-03-047
Proj IDSTP 1802(305)HES
Work TypeTRAFFIC SIGNAL IMPROVEMENT
 
4.600399625.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-03-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183011
Totals399625.730.000.000.0

CountyROCKWALL
HighwaySH 66
From0.1 MILE WEST OF FM 1141
ToCOLLIN COUNTY LINE
CSJ0009-04-061
Proj IDSTP 2016(819)HES
Work TypeGR, BASE, PVMT, PVMT MKGS, SIGNS
 
8.92510521700.237377234.9770.1
CountyROCKWALL
HighwaySH 66
FromFM 1141
ToE COUNTY LINE ROAD (COUNTY LINE)
CSJ0009-04-065
Proj IDCC 9-4-65
Work TypeADD TURN LANES
 
8.7722605686.771638575.7462.8
CountyCOLLIN
HighwaySH 66
FromROCKWALL COUNTY LINE
ToHUNT COUNTY LINE
CSJ0009-05-011
Proj IDSTP 2016(820)
Work TypeGR,BASE, PVMT, PVMT MKGS, SIGNS
 
2.1562744978.341974931.7371.9
Work Order12-07-16
Work Began03-22-17
Work Completed
Time Computed03-20-17
Contract Working Days505
Addl Days Granted0
Working Days Charged372
Percent Time Used73
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-04-061
MICA CORPORATION (0.62)
SYNERGY SIGNS & SERVICES, LLC (0.91)
FORTSON CONTRACTING, INC. (1.21)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.05)
TEX OP CONSTRUCTION, LP (4.72)
DUSTROL, INC. (1.01)
DALLAS LITE AND BARRICADE INC. (0.48)
C & J TREE SERVICE (0.26)
TOTAL HIGHWAY MAINTENANCE, LLC (1.28)
J & M CONTRACTING COMPANY (16.02)
DURABLE SPECIALTIES, INC. (0.56)
ALTUS TRAFFIC MANAGEMENT LLC (0.06)
W.O.E. CONSTRUCTION (0.00)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.37)
DALLAS LITE AND BARRICADE, INC. (0.48)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.37)
Contract #03163001
Totals15872365.34160579.4310990742.4469.2

CountyROCKWALL
HighwaySH 66
FromAT LAKE RAY HUBBARD BRIDGE EB
ToNORTH SLOPE NEAR EAST END
CSJ0009-04-066
Proj IDNH 2018(575)
Work TypeSLOPE FAILURE REPAIR
 
1.2522226102.00983066.8344.1
Work Order04-13-18
Work Began06-05-18
Work Completed
Time Computed06-05-18
Contract Working Days146
Addl Days Granted14
Working Days Charged76
Percent Time Used47
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0009-04-066
XROADS, L.P. (0.68)
STRIPING TECHNOLOGY, L.P. (1.78)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.12)
COMEN ENTERPRISE LLC (10.57)
PETERSON CONTRACTORS, INC. (14.86)
T & R EXCAVATION, INC. (16.52)
PENHALL COMPANY (0.36)
Contract #03183229
Totals2226102.00262380.00983066.8344.1

CountyDALLAS
HighwayIH 30
FromIH 635
ToCHAHA RD.
CSJ0009-11-227
Proj IDCM 1402(021)
Work TypeITS INSTALLATION
 
8.4002749311.962723418.4599.0
Work Order05-08-15
Work Began08-10-15
Work Completed
Time Computed08-06-15
Contract Working Days200
Addl Days Granted0
Working Days Charged188
Percent Time Used94
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-227
LAYFIELD CONSTRUCTION, INC (0.49)
BUYERS BARRICADES, INC. (1.25)
DYNAMIC VISION CO., INC. (3.88)
KLP COMMERCIAL, LLC (3.65)
WOLFE CONSTRUCTION GROUP, INC. (0.17)
PANIOLO CONSTRUCTION SERVICES, LLC (0.63)
Contract #08143015
Totals2749311.96509584.712723418.4599.0

CountyDALLAS
HighwayIH 30
FromAT ST FRANCIS
To.
CSJ0009-11-233
Proj IDSTP 1602(322)HES
Work TypeCONSTRUCT PEDESTRIAN OVER/UNDERPASS
 
0.1742254488.451812637.6681.9
Work Order09-15-16
Work Began05-12-17
Work Completed
Time Computed09-15-16
Contract Working Days247
Addl Days Granted0
Working Days Charged292
Percent Time Used118
Contractor(s)
RAMA ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-233
TOTAL HIGHWAY MAINTENANCE, LLC (1.03)
WYLIE DRILLING & DRAINAGE, INC. (2.08)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (0.10)
ODUM SERVICES, L.P. (1.67)
Contract #07163026
Totals2254488.4571990.901812637.6681.9

CountyDALLAS
HighwayIH 30
FromW OF GUS THOMASSON RD
ToE OF N GALLOWAY AVE
CSJ0009-11-244
Proj IDNH 2018(735)
Work TypeFULL DEPTH CONCRETE PAVEMENT
 
1.1772069851.67272688.9013.1
Work Order05-17-18
Work Began07-20-18
Work Completed
Time Computed07-20-18
Contract Working Days85
Addl Days Granted0
Working Days Charged1
Percent Time Used1
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0009-11-244
CROSSROADS, L.P. (0.56)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (16.57)
TOTAL HIGHWAY MAINTENANCE, LLC (2.37)
W.O.E. CONSTRUCTION (0.79)
PREMIER PAVING, LTD. (5.19)
BRENDA PRICE TRUCKING (1.69)
Contract #04183008
Totals2069851.6720780.00272688.9013.1

CountyROCKWALL
HighwayIH 30
FromAT FM 3549
To.
CSJ0009-12-072
Proj IDPTF 2015(062)
Work TypeSTR, GRD, BASE & CONC PAVT
 
1.70432882301.0024408876.2674.2
Work Order08-05-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days600
Addl Days Granted10
Working Days Charged589
Percent Time Used96
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-072
HAYDON BUILDING CORP. (19.74)
TOTAL HIGHWAY MAINTENANCE, LLC (0.82)
SOUTH TEXAS PAINTING COMPANY (0.24)
K & S UTILITY CONTRACTORS, INC. (7.08)
FARR FOUNDATION, INC. (0.73)
MARCOM"S MOWING SERVICE, LLC (0.13)
HOUSTON SAWING & DRILLING (0.01)
MEL"S ELECTRIC SERVICE, INC. (1.48)
PRIMATE CONSTRUCTION, INC. (0.07)
WOLFE CONSTRUCTION GROUP, INC. (0.85)
MCL CONTRACTING, LLC (0.09)
LINDAMOOD DEMOLITION, INC. (0.19)
WYLIE DRILLING & DRAINAGE, INC. (0.46)
FORTSON CONTRACTING, INC. (0.28)
BRJ PAVING INCORPORATION (1.01)
PREMIER PAVING, LTD. (11.94)
RAMBO CONTRACTING, INC. (1.24)
PERFORMANCE EQUIPMENT SERVICE (1.47)
W.O.E. CONSTRUCTION (0.15)
ROYAL REBAR (0.44)
OSCAR ORDUNO, INC. (0.57)
ROADWAY SPECIALTIES, INC. (0.07)
FISHER SAND & GRAVEL CO. (0.72)
BOWMAN ENGINEERING & CONSULTING, INC (0.02)
URBAN INFRACONSTRUCTION, LLC. (0.01)
SLATON BROTHERS, INC. (2.86)
SOUTHEAST GRINDING & GROOVING, LLC (0.00)
W.O.E. CONSTRUCTION (0.62)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (0.03)
ALLIED DRILLING COMPANY (0.12)
HIGH QUALITY ELECTRIC (0.10)
RICE TUNNELING & BORING, INC. (0.06)
Contract #02163002
Totals32882301.001747778.9624408876.2674.2

CountyROCKWALL
HighwayIH 30
From0.1 MI W END OF RAY HUBBARD BR
ToHUNT COUNTY LINE
CSJ0009-12-211
Proj IDC 9-12-211
Work TypeREHABILITATION OF EXISTING ROADWAY
 
13.3113411242.52523432.3215.3
Work Order05-17-18
Work Began09-04-18
Work Completed
Time Computed09-04-18
Contract Working Days144
Addl Days Granted0
Working Days Charged25
Percent Time Used17
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-12-211
ALTUS TRAFFIC MANAGEMENT LLC (0.79)
DUSTROL, INC. (3.66)
FORTSON CONTRACTING, INC. (0.36)
J & M CONTRACTING COMPANY (1.80)
STRIPING TECHNOLOGY, L.P. (3.50)
Contract #04183033
Totals3411242.52523432.32523432.3215.3

CountyCOLLIN
HighwayUS 75
FromPGBT
ToPARK BLVD
CSJ0047-06-133
Proj IDSTP 1502(083)MM
Work TypeSTR, PVMT, SIGNS, PVMT MKGS
 
1.39137466722.1829288102.1278.1
Work Order02-26-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days750
Addl Days Granted40
Working Days Charged702
Percent Time Used88
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-133
MOBILE ENTERPRISES, INC. (0.11)
HIRSCHFELD STEEL CO. (2.12)
HEIDENFELS ENTERPRISES (2.95)
HERDEZ TRUCKING, INC. (2.44)
MICA CORPORATION (5.14)
TOTAL HIGHWAY MAINTENANCE, LLC (1.49)
ANTIGO CONSTRUCTION, INC. (0.15)
EROSION CONTROL MANAGEMENT SERVICES (0.25)
UNDER CONSTRUCTION INC. (0.14)
PREMIER PAVING, LTD. (3.74)
PANIOLO CONSTRUCTION SERVICES, LLC (1.65)
ANCORTEX, INC. (8.32)
ROYAL REBAR (5.66)
DURABLE SPECIALTIES, INC. (1.36)
LAYFIELD CONSTRUCTION, INC (0.15)
RG PAINTING, INC. (0.12)
ACT SAW CUTTING & REMOVAL (0.00)
A-CORE CONCRETE CUTTING, INC. (0.10)
A & A CONSTRUCTION (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.29)
DUSTROL, INC. (0.25)
ATS DRILLING, INC. (0.39)
BURKHALTER RIGGING, INC. (0.86)
ALPHA RAILROAD & PILING, LLC (0.26)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.33)
Contract #11153202
Totals37466722.181145315.5129288102.1278.1

CountyCOLLIN
HighwayUS 75
FromSPRING CREEK PARKWAY
ToSH 121 (SAM RAYBURN TOLLWAY)
CSJ0047-06-139
Proj IDC 47-6-139
Work TypeGRADE, PAVEMENT, DRAINAGE, STRUCTUR
 
6.50947531666.9451534378.9099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-04-14
Work Began04-24-14
Work Completed
Time Computed03-20-14
Contract Working Days766
Addl Days Granted104
Working Days Charged875
Percent Time Used100
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-139
DALLAS LITE AND BARRICADE INC. (3.21)
RUSSO CORPORATION (0.66)
TOTAL HIGHWAY MAINTENANCE, LLC (1.07)
INTEGRATED ROADWAY SERVICES, INC. (12.66)
FORTSON CONTRACTING, INC. (0.79)
GHB EQUIPMENT COMPANY, L.L.C. (0.36)
W.O.E. CONSTRUCTION (7.22)
USA SWPPP INSPECTIONS, INC. (1.34)
ROBERTS TRUCKING (1.66)
SIERRA HORIZONTAL BORING, LLC (0.05)
SLATON BROTHERS, INC. (14.18)
CRAIG OLDEN, INC. (3.06)
JAGOE-PUBLIC COMPANY (3.57)
GREENER PASTURES LANDSCAPE, INC. (1.25)
Contract #12133001
Totals47531666.940.0051534378.9099.9

CountyCOLLIN
HighwayUS 75 ETC
FromSH 121
ToPGBT
CSJ0047-06-162
Proj IDNH 2018(576)
Work TypeFULL DEPTH CONCRETE REPAIR
 
29.9321230202.68746322.1860.6
Work Order04-18-18
Work Began06-11-18
Work Completed
Time Computed06-11-18
Contract Working Days83
Addl Days Granted26
Working Days Charged73
Percent Time Used66
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-06-162
W.O.E. CONSTRUCTION (5.89)
BRENDA PRICE TRUCKING (4.52)
ALTUS TRAFFIC MANAGEMENT LLC (0.96)
STRIPING TECHNOLOGY, L.P. (4.88)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (1.60)
Contract #03183218
Totals1230202.68141396.97746322.1860.6

CountyDALLAS
HighwayUS 75
FromSP 366/WOODALL RODGERS FWY
ToIH 635 IN DALLAS
CSJ0047-07-229
Proj IDNH 2016(511)
Work TypeLANDSCAPE
 
9.113834793.50398832.0851.9
Work Order09-15-16
Work Began11-29-16
Work Completed
Time Computed10-31-16
Contract Working Days148
Addl Days Granted0
Working Days Charged205
Percent Time Used138
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-07-229
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163219
Totals834793.5028156.98398832.0851.9

CountyCOLLIN ETC
HighwaySH 5 ETC
FromS SLOAN CREEK PKWY
ToSH 121
CSJ0047-09-036
Proj IDSTP 2019(135)
Work TypeSEAL COAT, PVMT MKGS
 
262.25215172926.190.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days242
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0047-09-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10183205
Totals15172926.190.000.000.0

CountyCOLLIN
HighwayUS 75
FromNORTH OF MELISSA RD
ToSOUTH OF FM 455 INTERCHANGE
CSJ0047-14-069
Proj IDC 47-14-69
Work TypeGRADING, BASE, PVMT, STR, SIGNS
 
5.94779417673.4357484864.5172.3
Work Order03-16-16
Work Began07-05-16
Work Completed
Time Computed06-14-16
Contract Working Days884
Addl Days Granted0
Working Days Charged659
Percent Time Used74
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-069
DALLAS LITE AND BARRICADE INC. (0.18)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.41)
GJ SEEDING, LLC (0.28)
HOUSTON SAWING & DRILLING (0.02)
JAGOE-PUBLIC COMPANY (0.86)
LAYFIELD CONSTRUCTION, INC (0.48)
MICA CORPORATION (1.11)
NE-TEX CONSTRUCTION, LTD. (0.15)
NORTH TEXAS CONTRACTING, INC. (4.64)
PANIOLO CONSTRUCTION SERVICES, LLC (1.22)
ROYAL REBAR (1.72)
SOUTHERN CROSS CONTRACTORS, LLC (0.39)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.00)
TEXAS SHAFTS, INC. (0.92)
RMI WORLDWIDE, LLC (0.09)
STRIPING TECHNOLOGY, L.P. (0.67)
RG PAINTING, INC. (0.07)
LMH SAW & SEAL, LLC (0.25)
MCL CONTRACTING, LLC (0.04)
ANCORTEX, INC. (0.19)
W.O.E. CONSTRUCTION (1.72)
HULCHER SERVICES INC. (0.02)
PREMIER PAVING, LTD. (0.07)
DALLAS LITE AND BARRICADE, INC. (0.18)
Contract #12153234
Totals79417673.431507564.2957484864.5172.3

CountyCOLLIN
HighwayUS 75
FromSOUTH OF US 380
ToNORTH OF FM 455
CSJ0047-14-080
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
10.258966634.97424745.5543.9
CountyDALLAS
HighwayIH 20
FromIH 635
ToKAUFMAN COUNTY LINE
CSJ0095-13-037
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
6.415697636.68952274.6399.9
CountyKAUFMAN
HighwayIH 20
FromDALLAS COUNTY LINE
ToROSEHILL RD
CSJ0095-14-026
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
12.895830467.70682209.7982.1
CountyKAUFMAN
HighwayIH 20
FromROSEHILL RD
ToVAN ZANDT COUNTY LINE
CSJ0495-01-072
Proj IDCM 2017(920)
Work TypeINSTALLATION OF WIRELESS ITS
 
14.044919417.69869626.8594.5
Work Order07-20-17
Work Began10-18-17
Work Completed
Time Computed10-18-17
Contract Working Days218
Addl Days Granted3
Working Days Charged179
Percent Time Used80
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-080
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.71)
ALTUS TRAFFIC MANAGEMENT LLC (1.46)
COMEN ENTERPRISE LLC (1.87)
DALLAS FOUNDATION DRILLING CO., INC. (1.34)
TX DOWN UNDER CONSTRUCTION LLC (1.13)
Contract #06173209
Totals3414157.0472413.282928856.8285.7

CountyCOLLIN
HighwayUS 75
FromAT SH 121 INTERCHANGE
To.
CSJ0047-14-082
Proj IDNH 1702(450)
Work TypeLANDSCAPE ENHANCEMENT
 
0.9302750000.00998948.5736.3
Work Order08-23-17
Work Began03-13-18
Work Completed
Time Computed02-19-18
Contract Working Days378
Addl Days Granted0
Working Days Charged154
Percent Time Used40
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-14-082
BUYERS BARRICADES, INC. (0.47)
STOIC CIVIL CONSTRUCTION, INC. (2.96)
T & R EXCAVATION, INC. (0.90)
INCON-TROL CONSTRUCTION, LLC (5.45)
CONTAIN WATER SYSTEMS INC. (0.91)
TX DOWN UNDER CONSTRUCTION, LLC (0.71)
RELIANT HAULERS LLC (3.00)
Contract #07173222
Totals2750000.00250015.11998948.5736.3

CountyDALLAS ETC
HighwaySH 342 ETC
FromELLIS COUNTY LINE
ToWEST BELTLINE
CSJ0048-01-064
Proj IDNH 2018(118)
Work TypeSEAL COAT,PVMT MKGS
 
248.25211384511.2010650366.3593.5
Work Order11-10-17
Work Began01-22-18
Work Completed
Time Computed01-22-18
Contract Working Days150
Addl Days Granted53
Working Days Charged203
Percent Time Used100
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0048-01-064
BARRICADES PLUS, LLC (1.53)
STRIPE-A-ZONE, INC. (16.77)
BRYDL CONTRACTING, INC. (0.52)
Contract #10173202
Totals11384511.2073575.0510650366.3593.5

CountyELLIS
HighwayUS 77
FromSOUTH COLLEGE STREET
ToPARK HILLS DRIVE
CSJ0048-03-091
Proj IDSTP 2018(541)
Work TypePVMT REPAIR,LEVEL-UP AND OVERLAY
 
2.740829774.11704326.7784.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-18
Work Began06-15-18
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged68
Percent Time Used83
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0048-03-091
ALTUS TRAFFIC MANAGEMENT LLC (1.06)
O. TREVINO CONSTRUCTION, LLC (8.87)
STRIPING TECHNOLOGY, L.P. (2.65)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (6.90)
BRENDA PRICE TRUCKING (1.01)
W.O.E. CONSTRUCTION (0.27)
Contract #02183211
Totals829774.1120655.36704326.7784.8

CountyELLIS
HighwayIH 35E
FromUS 77 SOUTH OF WAXAHACHIE
ToUS 77 NORTH OF WAXAHACHIE
CSJ0048-04-079
Proj IDNH 1502(531)
Work TypeGR, STRS & PAVT
 
10.976126414963.9767796681.8553.6
Work Order01-29-16
Work Began03-15-16
Work Completed
Time Computed03-15-16
Contract Working Days797
Addl Days Granted18
Working Days Charged611
Percent Time Used78
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0048-04-079
GJ SEEDING, LLC (0.12)
ALTUS TRAFFIC MANAGEMENT LLC (0.08)
TOTAL HIGHWAY MAINTENANCE, LLC (1.07)
PREMIER PAVING, LTD. (12.43)
A BROTHERS MILLING, LLC (0.81)
INTEGRATED ROADWAY SERVICES, INC. (4.30)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.53)
W.O.E. CONSTRUCTION (7.93)
A & R DEMOLITION (0.44)
P G SERVICES (0.07)
DBI SERVICES, LLC (0.03)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.90)
HOUSTON SAWING & DRILLING (0.02)
UNDER CONSTRUCTION INC. (0.31)
OSAGE COMPANIES, LLC (0.18)
ANCORTEX, INC. (1.66)
EL CAMINO TRUCKING, INC. (1.95)
SAR TRANSPORTATION, LLC (1.94)
BREDA COMPANY, INC. (0.72)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.07)
PANTHER CREEK TRANSPORTATION, INC. (4.01)
BIG BIRD TREE SERVICE, INC. (0.00)
FABCO, LLC (0.56)
J.H. PAINTING COMPANY (0.52)
SWEEPER KING SERVICES, LLC (0.09)
J & K EXCAVATION, LLC (0.47)
PRIMATE CONSTRUCTION, INC. (0.06)
Contract #08153201
Totals126414963.971989557.4867796681.8553.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8