Monthly Local Let Maintenance Report For Corpus Christi District As Of Apr 10, 2018 Page 4 Of 4

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN PATRICIO
HighwayUS0181
FromUS181, SH35, AND US77
To.
CSJ6326-15-001
Proj IDEMC - 632615001
Work TypeLARGE SIGN REPLACEMENT
 
0.999714159.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-09-18
Work Began00-00-00
Work Completed
Time Computed03-12-18
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181642
Totals714159.400.000.000.0

CountyBEE
HighwayUS0181
FromVARIOUS
To.
CSJ6326-54-001
Proj IDSUP - 632654001
Work TypePICNIC AREA MAINTENANCE
 
0.99960724.728479.7313.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged121
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6326-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171630
Totals60724.722608.488479.7313.9

CountyARANSAS
HighwaySH0035
FromSH 35
To12TH ST
CSJ6327-21-001
Proj IDEMC - 632721001
Work TypeDEBRIS SITE MANAGEMENT
 
0.100747502.00866546.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted92
Working Days Charged71
Percent Time Used58
Contractor(s)
FAULKNER LAND CLEARING AND SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6327-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171642
Totals747502.00385164.85866546.6099.9

CountyARANSAS
HighwaySH0035
FromVARIOUS
To.
CSJ6328-25-001
Proj IDSUP - 632825001
Work TypePICNIC AREA MAINTENANCE
 
0.99959043.047380.3812.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged90
Percent Time Used12
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171639
Totals59043.042502.097380.3812.5