Monthly Local Let Maintenance Report For Corpus Christi District As Of Aug 16, 2018 Page 3 Of 4

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNUECES
HighwaySH0286
FromDISTRICT HEADQUARTERS
To.
CSJ6318-08-001
Proj IDSUP - 631808001
Work TypeSERVICE STATION ATTENDANT
 
0.99944706.5625569.2057.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged457
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
THE EB FOUNDATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171630
Totals44706.561687.0425569.2057.1

CountyJIM WELLS
HighwayUS0281
FromVARIOUS
To.
CSJ6318-16-001
Proj IDRMC - 631816001
Work TypeMOWING
 
217.730268064.80359353.6099.9
Work Order06-19-17
Work Began00-00-00
Work Completed
Time Computed06-26-17
Contract Working Days365
Addl Days Granted365
Working Days Charged406
Percent Time Used55
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171606
Totals268064.8016036.00359353.6099.9

CountyNUECES
HighwayIH0037
FromVARIOUS
To.
CSJ6318-17-001
Proj IDRMC - 631817001
Work TypeMOWING
 
50.678110157.64103865.74100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-15-17
Work Began06-06-17
Work Completed03-31-18
Time Computed06-26-17
Contract Working Days365
Addl Days Granted0
Working Days Charged278
Percent Time Used76
Contractor(s)
EPIC ENERGY SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171607
Totals110157.640.00103865.74100.0

CountyREFUGIO
HighwayUS0077
FromVARIOUS
To.
CSJ6318-19-001
Proj IDRMC - 631819001
Work TypeMOWING
 
190.445155726.50102251.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-19-17
Work Began00-00-00
Work Completed05-31-18
Time Computed06-26-17
Contract Working Days365
Addl Days Granted0
Working Days Charged344
Percent Time Used94
Contractor(s)
HAMMOND LAND DEVELOPMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171609
Totals155726.500.00102251.00100.0

CountyKARNES
HighwayUS0181
FromVARIOUS
To.
CSJ6318-20-001
Proj IDRMC - 631820001
Work TypeMOWING
 
275.064214523.50212173.5098.9
Work Order06-19-17
Work Began00-00-00
Work Completed
Time Computed06-26-17
Contract Working Days365
Addl Days Granted365
Working Days Charged401
Percent Time Used54
Contractor(s)
HAMMOND LAND DEVELOPMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171610
Totals214523.500.00212173.5098.9

CountyKLEBERG
HighwayUS0077
FromVARIOUS
To.
CSJ6318-21-001
Proj IDRMC - 631821001
Work TypeMOWING
 
222.835235303.72313604.9699.9
Work Order06-19-17
Work Began00-00-00
Work Completed
Time Computed06-26-17
Contract Working Days365
Addl Days Granted365
Working Days Charged401
Percent Time Used54
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6318-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171611
Totals235303.720.00313604.9699.9

CountyNUECES
HighwaySH0044
FromVARIOUS
To.
CSJ6320-10-001
Proj IDRMC - 632010001
Work TypeCRACK SEALING
 
151.22886164.2086656.32100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-18
Work Began00-00-00
Work Completed03-02-18
Time Computed02-19-18
Contract Working Days17
Addl Days Granted0
Working Days Charged11
Percent Time Used64
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171601
Totals86164.200.0086656.32100.0

CountySAN PATRICIO
HighwaySH0035
FromGREGORY
ToCOPANO BAY
CSJ6323-46-001
Proj IDEMC - 632346001
Work TypeSMALL SIGN REPLACEMENT
 
24.000229730.00234061.2699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged62
Percent Time Used103
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6323-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171640
Totals229730.000.00234061.2699.9

CountyNUECES
HighwaySH0361
FromPARK ROAD 22
ToSH 35
CSJ6323-99-001
Proj IDEMC - 632399001
Work TypeSMALL SIGN REPLACEMENT
 
27.560218070.00200170.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged105
Percent Time Used140
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6323-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171641
Totals218070.000.00200170.0099.9

CountySAN PATRICIO
HighwaySH0035
FromSH 35
ToFM 3036
CSJ6324-44-001
Proj IDEMC - 632444001
Work TypeSMALL SIGN REPLACEMENT
 
17.700227504.00203846.0097.6
Work Order10-26-17
Work Began00-00-00
Work Completed
Time Computed10-30-17
Contract Working Days75
Addl Days Granted0
Working Days Charged106
Percent Time Used141
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171642
Totals227504.000.00203846.0097.6

CountyNUECES
HighwaySH0361
FromAT 1852 PASS AND NEWPORT PASS
To.
CSJ6324-54-001
Proj IDEMC - 632454001
Work TypeEMERGENCY BRIDGE REPAIR
 
0.300507958.00120671.3023.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged47
Percent Time Used69
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181643
Totals507958.0046621.80120671.3023.7

CountyNUECES
HighwaySH0361
FromAT CORPUS CHRISTI PASS
To.
CSJ6324-55-001
Proj IDEMC - 632455001
Work TypeBRIDGE REPAIR
 
0.999219292.0070323.6034.7
Work Order01-24-18
Work Began00-00-00
Work Completed
Time Computed03-15-18
Contract Working Days34
Addl Days Granted30
Working Days Charged74
Percent Time Used115
Contractor(s)
TEXCAVATION COMPANY LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171642
Totals219292.003904.0070323.6034.7

CountySAN PATRICIO
HighwaySH0188
FromPORT BAY
To.
CSJ6324-62-001
Proj IDEMC - 632462001
Work TypeEMERGENCY BRIDGE REPAIR
 
0.379267685.00128560.0048.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged35
Percent Time Used102
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181644
Totals267685.0082260.00128560.0048.2

CountyREFUGIO
HighwayUS0077
FromUS 77A, US183
ToFM 774
CSJ6324-83-001
Proj IDEMC - 632483001
Work TypeSMALL SIGN REPLACEMENT
 
4.180134694.00135225.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed03-01-18
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged70
Percent Time Used93
Contractor(s)
TRIPLE R CONTRACTING, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6324-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171643
Totals134694.000.00135225.00100.0

CountyARANSAS
HighwayFM1069
FromSL 70
ToEND OF STATE MAINTENANCE
CSJ6325-55-001
Proj IDEMC - 632555001
Work TypeSMALL SIGN REPLACEMENT
 
21.090248688.00244808.0098.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted45
Working Days Charged120
Percent Time Used100
Contractor(s)
TRIPLE R CONTRACTING, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6325-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171644
Totals248688.000.00244808.0098.4

CountyNUECES
HighwayIH0037
FromVARIOUS
To.
CSJ6325-56-001
Proj IDSUP - 632556001
Work TypeLITTER PICKUP
 
0.999120751.1069044.0857.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
NC MHMR INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6325-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171639
Totals120751.108630.5169044.0857.1

CountyARANSAS
HighwaySH0035
From100FT N. OF CACTUS ST.
To100FT S. OF MAPLE ST.
CSJ6325-83-001
Proj IDEMC - 632583001
Work TypeTRAFFIC SIGNAL ITEM REPLACEMENT
 
2.500579805.25571808.5598.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-12-18
Work Began00-00-00
Work Completed
Time Computed01-22-18
Contract Working Days90
Addl Days Granted0
Working Days Charged67
Percent Time Used74
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171640
Totals579805.250.00571808.5598.6

CountyARANSAS
HighwayFM0136
FromSH 35 TO FM 2678 &
ToFM 2678 FROM FM 136 TO FM 774
CSJ6326-12-001
Proj IDEMC - 632612001
Work TypeSMALL SIGN REPLACEMENT
 
29.500329836.00319547.6896.8
Work Order01-24-18
Work Began00-00-00
Work Completed
Time Computed03-01-18
Contract Working Days90
Addl Days Granted0
Working Days Charged88
Percent Time Used97
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171641
Totals329836.000.00319547.6896.8

CountySAN PATRICIO
HighwaySH0188
FromBUS 35
ToFM 136
CSJ6326-13-001
Proj IDEMC - 632613001
Work TypeSMALL SIGN REPLACEMENT
 
14.240188130.00189670.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged26
Percent Time Used76
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181640
Totals188130.002240.00189670.0099.9

CountyREFUGIO
HighwayUS0077
FromVARIOUS ROADWAYS
To.
CSJ6326-14-001
Proj IDEMC - 632614001
Work TypeSMALL SIGN REPLACEMENT
 
40.420498520.00337201.8367.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged34
Percent Time Used40
Contractor(s)
TRIPLE R CONTRACTING, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6326-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181641
Totals498520.0039968.38337201.8367.6