Monthly Local Let Maintenance Report For Brownwood District As Of May 10, 2018 Page 1 Of 3

Last Update: Thursday, May 10, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBROWN
HighwayUS0067
FromBROWN COUNTY
ToBROWN COUNTY
CSJ6270-71-001
Proj IDRMC - 627071001
Work TypeROADSIDE MOWING
 
326.700288805.20602230.1899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-03-16
Work Began00-00-00
Work Completed
Time Computed10-10-16
Contract Working Days95
Addl Days Granted95
Working Days Charged105
Percent Time Used55
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6270-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04142301
Totals288805.200.00602230.1899.9

CountyBROWN
HighwayUS0377
FromDISTRICT-WIDE
ToDISTRICT-WIDE
CSJ6273-26-001
Proj IDRMC - 627326001
Work TypeTRAFFIC SIGNAL MAINTENANCE (WILL-CALL)
 
0.001379430.00513321.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-16
Work Began11-17-14
Work Completed
Time Computed04-26-16
Contract Working Days100
Addl Days Granted0
Working Days Charged74
Percent Time Used74
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6273-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06142301
Totals379430.000.00513321.3899.9

CountyCOLEMAN
HighwayUS0283
FromVARIOUS
ToVARIOUS
CSJ6279-86-001
Proj IDRMC - 627986001
Work TypeROADSIDE MOWING
 
0.001229853.73417528.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-14
Work Began12-08-14
Work Completed
Time Computed12-08-14
Contract Working Days75
Addl Days Granted91
Working Days Charged170
Percent Time Used102
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10142302
Totals229853.730.00417528.9599.9

CountyMCCULLOCH
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6279-88-001
Proj IDRMC - 627988001
Work TypeROADSIDE MOWING
 
0.001241118.00445608.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-25-14
Work Began11-29-14
Work Completed
Time Computed12-02-14
Contract Working Days55
Addl Days Granted55
Working Days Charged60
Percent Time Used54
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6279-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10142304
Totals241118.000.00445608.5099.9

CountySAN SABA
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6279-89-001
Proj IDRMC - 627989001
Work TypeROADSIDE MOWING
 
0.001206625.65136151.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-15
Work Began06-02-15
Work Completed06-01-17
Time Computed06-09-15
Contract Working Days55
Addl Days Granted0
Working Days Charged25
Percent Time Used45
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6279-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10142305
Totals206625.650.00136151.40100.0

CountyBROWN
HighwayUS0377
FromVARIOUS
ToVARIOUS
CSJ6285-71-001
Proj IDSUP - 628571001
Work TypeSU-ALDERSGATE-PICNIC
 
0.001135295.00173600.0099.9
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted735
Working Days Charged1,096
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152333
Totals135295.005465.00173600.0099.9

CountyCOMANCHE
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6285-87-001
Proj IDSUP - 628587001
Work TypeSU-ALDERSGATE-PICNIC
 
0.00154135.0035077.0064.7
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted735
Working Days Charged1,096
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152334
Totals54135.001277.0035077.0064.7

CountySTEPHENS
HighwayUS0183
FromVARIOUS
ToVARIOUS
CSJ6286-79-001
Proj IDRMC - 628679001
Work TypeROADSIDE MOWING
 
0.001178607.70281252.4599.9
Work Order06-30-15
Work Began07-07-15
Work Completed
Time Computed07-07-15
Contract Working Days58
Addl Days Granted58
Working Days Charged91
Percent Time Used78
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6286-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152303
Totals178607.700.00281252.4599.9

CountyLAMPASAS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6286-80-001
Proj IDRMC - 628680001
Work TypeROADSIDE MOWING
 
0.001250431.56372963.0899.9
Work Order06-02-17
Work Began07-01-15
Work Completed
Time Computed06-09-17
Contract Working Days60
Addl Days Granted60
Working Days Charged31
Percent Time Used25
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6286-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152304
Totals250431.560.00372963.0899.9

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6287-03-001
Proj IDSUP - 628703001
Work TypeSU-ALDERSGATE-LITTER REMOVAL
 
0.00126347.6624959.1194.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged884
Percent Time Used121
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152331
Totals26347.660.0024959.1194.7

CountyEASTLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6287-05-001
Proj IDSUP - 628705001
Work TypeSU-ALDERSGATE-PICNIC
 
0.001176400.00179620.0099.9
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted735
Working Days Charged1,096
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152335
Totals176400.006060.00179620.0099.9

CountyMILLS
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6287-12-001
Proj IDSUP - 628712001
Work TypeSU-ALDERSGATE-PICNIC
 
0.00142500.0046460.0099.9
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted735
Working Days Charged1,096
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152337
Totals42500.001195.0046460.0099.9

CountyBROWN
HighwayUS0084
FromDISTRICT-WIDE
To***
CSJ6287-33-001
Proj IDRMC - 628733001
Work TypeBRIDGE MAINTENANCE (CALL-OUT)
 
0.001434750.00779592.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-05-17
Work Began10-27-15
Work Completed12-04-17
Time Computed04-12-17
Contract Working Days75
Addl Days Granted85
Working Days Charged145
Percent Time Used90
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6287-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07152301
Totals434750.000.00779592.50100.0

CountyBROWN
HighwayUS0183
FromBWD DIST OFFICE COMPLEX
To***
CSJ6287-35-001
Proj IDSUP - 628735001
Work TypeSTATE USE-MOWING-JCI/CFLR
 
0.00134000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6287-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152340
Totals34000.000.000.000.0

CountyCOLEMAN
HighwayUS0084
FromVARIOUS
To***
CSJ6294-18-001
Proj IDSUP - 629418001
Work TypeSTATE USE-PICNIC-JCI/CFLR
 
0.00190472.0094505.0099.9
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged973
Percent Time Used133
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08152330
Totals90472.003403.0094505.0099.9

CountyMCCULLOCH
HighwayUS0377
FromVARIOUS
To***
CSJ6294-19-001
Proj IDSUP - 629419001
Work TypeSTATE USE-PICNIC-JCI/CFLR
 
0.00194927.00110243.0099.9
Work Order09-01-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged1,004
Percent Time Used137
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08152331
Totals94927.003264.00110243.0099.9

CountyBROWN
HighwayUS0183
FromBROWNWOOD AREA OFFICE
To***
CSJ6294-64-001
Proj IDSUP - 629464001
Work TypeSTATE USE JANITORIAL-JCI/CFLR
 
0.00118241.4414512.0079.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged762
Percent Time Used104
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152330
Totals18241.440.0014512.0079.5

CountyBROWN
HighwayUS0183
FromBROWN COUNTY MAINTENANCE OFFICE
To***
CSJ6294-65-001
Proj IDSUP - 629465001
Work TypeSTATE USE JANITORIAL-CFLR/JCI
 
0.00117461.6012860.3073.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged762
Percent Time Used104
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152331
Totals17461.600.0012860.3073.6

CountyMILLS
HighwayUS0084
FromMILLS COUNTY MAINTENANCE OFFICE
To***
CSJ6294-66-001
Proj IDSUP - 629466001
Work TypeSTATE USE JANITORIAL-CFLR/JCI
 
0.00115201.6811924.8381.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged762
Percent Time Used104
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6294-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152332
Totals15201.680.0011924.8381.0

CountySAN SABA
HighwayUS0190
FromVARIOUS
To***
CSJ6297-49-001
Proj IDSUP - 629749001
Work TypeSTATE USE PICNIC/ALDERSGATE
 
0.001101800.00104249.0099.9
Work Order12-01-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged882
Percent Time Used120
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152330
Totals101800.003859.00104249.0099.9

page 1 | page 2 | page 3