Monthly State Let Construction Report For Brownwood District As Of Apr 10, 2018 Page 2 Of 2

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To2.15 MI S OF FM 2309
CSJ1102-01-042
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, STR, SURFACE
 
2.1612316169.672303303.3799.4
CountyMCCULLOCH
HighwaySH 71
From0.54 MI. W OF FM 2309
ToNEAR FM 2309
CSJ2561-01-013
Proj IDSTP 1502(081)
Work TypeWDN SUBGRADE, SURFACE
 
0.5661026756.54805612.8178.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-15
Work Began11-02-15
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged255
Percent Time Used83
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1102-01-042
J & M CONTRACTING, COMPANY (14.87)
WILLIS ELECTRIC CO., LP (0.54)
HJC FARMS, INC. (1.67)
D.I.J. CONSTRUCTION, INC (2.29)
TEXAS ALTERNATIVE GRASSER, INC. (0.36)
Contract #05153232
Totals3342926.21141513.903108916.1892.9

CountyBROWN
HighwayFM 1176
FromFM 586
ToUS 377
CSJ1365-05-015
Proj IDSTP 2018(768)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
11.077250586.500.000.0
CountyBROWN
HighwayFM 2125
From3.5 MI. N OF FM 2632
ToSH 279
CSJ2013-01-012
Proj IDSTP 2018(768)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
6.415621072.000.000.0
CountySTEPHENS
HighwayFM 2231
From2.6 MI. N OF US 180
ToUS 180
CSJ2095-01-015
Proj IDSTP 2018(768)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
2.630152678.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days174
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1365-05-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183005
Totals1024336.500.000.000.0

page 1 | page 2