Monthly State Let Construction Report For Brownwood District As Of Jul 13, 2018 Page 1 Of 2

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND ETC
HighwaySH 206 ETC
FromFM 2943
To.1 MI N OF IH 20 S.F.R IN CISCO
CSJ0007-04-126
Proj IDSTP 1702(798)
Work TypeSEAL COAT
 
158.0726070587.661353834.2422.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-126
BARRICADES PLUS, LLC (0.00)
FLATE LINE, INC. (5.58)
Contract #11173017
Totals6070587.66425409.271353834.2422.3

CountyEASTLAND
HighwayIH 20
FromAT 0.5 MI. W OF FM 571 AND ALSO AT
To2.5 MI. W OF SH 16
CSJ0007-06-070
Proj IDSTP 2005(276)TEG
Work TypeCONSTRUCT TWO SAFETY REST AREAS
 
3.11916358386.5816466163.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-13
Work Began02-01-13
Work Completed
Time Computed01-20-13
Contract Working Days415
Addl Days Granted180
Working Days Charged628
Percent Time Used105
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES (0.83)
ABILENE SHEET METAL (1.43)
CURTIS MECHANICAL CONTRACTORS, INC. (2.10)
GRIZZLY GLASS & MIRROR, INC. (1.01)
LONE OAK LANDSCAPE LLC (0.38)
LONE STAR BARRIER SERVICES, LLC (0.66)
PEACHTREE CONSTRUCTION, LTD. (4.79)
SCR CONSTRUCTION CO., INC. (0.18)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
TIPPENN FABRICATION & ERECTION (5.06)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53)
CORPUS CHRISTI STAMP WORKS, INC. (0.05)
FINLEY TERMITE AND PEST CONTROL, INC. (0.01)
SOLID ROCK LAWN & LANDSCAPE (0.21)
TEX OP CONSTRUCTION, LP (0.20)
GOMEZ FLOOR COVERING, INC. (1.55)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07)
B.A.D.J., INC. DBA THE TOPSPOT (0.21)
WILKS MASONRY CORPORATION (4.34)
LIBERTY PAINTING & DRYWALL (0.65)
HUNTER KNEPSHIELD COMPANY (0.73)
CLLA GROUP, LLC (1.46)
AMERITEX FLAG & FLAGPOLE, LLC (0.03)
A & A CONSTRUCTION (0.26)
LIBERTY PAINTING & DRYWALL (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11)
CONROE WOOD PRODUCTS INC. (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
SAR TRANSPORTATION, LLC (0.00)
CHAMPION FUEL SOLUTIONS (0.00)
Contract #10123203
Totals16358386.580.0016466163.6299.9

CountySTEPHENS
HighwayUS 180
From@ HUBBARD CREEK LAKE BRIDGE
To.
CSJ0011-07-051
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.7002875191.47648320.6822.5
CountySTEPHENS
HighwayUS 180
FromAT SOUR BRANCH BRIDGE
To.
CSJ0011-09-070
Proj IDBR 1702(472)
Work TypeREHAB BRIDGE
 
0.020363962.60291514.1080.0
CountySTEPHENS
HighwayUS 183
FromAT SNAKE DEN CREEK
To.
CSJ0404-02-039
Proj IDBR 1702(472)
Work TypeREPLACE BRIDGE RAIL
 
0.100244990.50253920.1599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began10-24-17
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged93
Percent Time Used46
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-051
BARRICADES UNLIMITED (1.58)
HJC FARMS, INC. (4.38)
ROCK SOLID, INC. (3.33)
S & S BRIDGE PAINTING, INC. (10.30)
SCR CIVIL CONSTRUCTION, LLC (3.13)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (2.77)
TEXOP CONSTRUCTION (0.50)
CROSSROADS, L.P. (0.62)
Contract #07173038
Totals3484144.57109546.841193754.9334.2

CountySTEPHENS
HighwayUS 180
FromGONZALES CREEK
ToFM 287
CSJ0011-08-026
Proj IDSTP 1602(051)
Work TypeRECONSTRUCT URBAN ROADWAY
 
5.12913412991.587953811.9659.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began09-15-16
Work Completed
Time Computed00-00-00
Contract Working Days459
Addl Days Granted79
Working Days Charged299
Percent Time Used55
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-08-026
CHEROKEE SERVICES (0.17)
D. I. J. CONSTRUCTION, INC. (1.17)
GIBSON & ASSOCIATES, INC. (0.66)
HJC FARMS, INC. (0.63)
(USE 05113)J&M CONTRACTING COMPANY (14.52)
PENHALL COMPANY (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.49)
WILLIS ELECTRIC CO., LP (2.37)
FAMBRO CONSTRUCTION, INC. (12.03)
NELSON INDUSTRIAL SERVICES, INC. (0.05)
GM MASONRY (0.22)
Contract #05163002
Totals13412991.58102563.667953811.9659.2

CountyBROWN
HighwayUS 84
FromAT FT. WORTH & WESTERN RAILROAD
To.
CSJ0054-07-069
Proj IDSTP 1302(079)RGS
Work TypeRAILROAD BRIDGE REPLACEMENT
 
0.5208488149.706806413.3480.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began09-07-16
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted0
Working Days Charged312
Percent Time Used78
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-069
GRANBURY EXCAVATING, INC. (24.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.86)
TEXAS SHAFTS, INC. (4.37)
ODUM SERVICES, L.P. (0.58)
MCL CONTRACTING, LLC (0.25)
CHOCTAW ERECTORS, INC. (2.69)
TEXAS HIGHWAY MAINTENANCE, LLC (0.81)
CROCKER CRANE RENTALS, L.P. (0.05)
FARR FOUNDATION, INC. (1.14)
Contract #02163207
Totals8488149.70163607.426806413.3480.1

CountyCOLEMAN
HighwayUS 67
FromSH 206
To.584 MI W OF CR 368
CSJ0078-03-055
Proj IDSTP 2017(457)HES
Work TypeIMPRV GR, SFT TREAT OBJECTS, ADD PA
 
8.2471678694.191718915.0199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged146
Percent Time Used78
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0078-03-055
CONTRACTORS SERVICE COMPANY (0.93)
DOUBLE A CONTRACTING, L.P. (2.72)
HJC FARMS, INC. (3.55)
TEXOP CONSTRUCTION (2.05)
Contract #01173215
Totals1678694.19146861.111718915.0199.9

CountyEASTLAND
HighwayUS 183
FromIH 20
ToCR 181
CSJ0127-01-030
Proj IDSTP 1702(236)
Work TypeADD PASSING LANES
 
4.2433372833.812334966.8669.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began09-11-17
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted30
Working Days Charged154
Percent Time Used61
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-01-030
D.I.J. CONSTRUCTION, INC (1.86)
GIBSON & ASSOCIATES, INC. (2.02)
HJC FARMS, INC. (3.06)
LUZ LERMA CONSTRUCTION, INC. (2.01)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.24)
TEXAS ALTERNATIVE GRASSER, INC. (0.30)
PENHALL COMPANY (0.20)
Contract #05173045
Totals3372833.81364165.752334966.8669.2

CountyEASTLAND
HighwayUS 183
FromCR 181
ToCR 173
CSJ0127-01-031
Proj IDC 127-1-31
Work TypeREHABILITATE EXISTING ROADWAY
 
4.1152366163.030.000.0
CountyEASTLAND
HighwayUS 183
FromCR 181
ToCR 173
CSJ0127-01-034
Proj IDSTP 2018(807)HES
Work TypeIMPROVE GUARDRAIL TO DESIGN STANDAR
 
4.154846859.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days214
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0127-01-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183235
Totals3213022.130.000.000.0

CountyEASTLAND
HighwayUS 183
FromCR 173
To5 MI. N OF RISING STAR NCL
CSJ0127-02-043
Proj IDC 127-2-43
Work TypeADD PASSING LANES
 
5.3224526012.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-29-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days332
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-043
D. I. J. CONSTRUCTION, INC. (2.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.82)
TEXAS ALTERNATIVE GRASSER, INC. (0.25)
HJC FARMS, INC. (1.89)
GIBSON & ASSOCIATES, INC. (1.67)
PENHALL COMPANY (0.17)
Contract #04183036
Totals4526012.960.000.000.0

CountyEASTLAND
HighwayUS 183
From5 MI. N OF RISING STAR NCL
ToRISING STAR NCL
CSJ0127-02-141
Proj IDSTP 2018(542)
Work TypeADD PASSING LANES
 
5.0003673746.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days260
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-141
D. I. J. CONSTRUCTION, INC. (1.92)
SAN-ANN-CO., INC. (1.36)
WOLFE CONSTRUCTION GROUP, INC. (0.78)
W.S. CONSTRUCTION COMPANY (7.95)
Contract #02183234
Totals3673746.040.000.000.0

CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-142
Proj IDSTP 2018(829)
Work TypeRECONSTRUCT URBAN ROADWAY
 
1.47611116710.550.000.0
CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-146
Proj IDSTP 2018(212)
Work TypeACQUISITION AND UTILITY ADJUSTMENTS
 
0.8093038242.000.000.0
CountyEASTLAND
HighwayUS 183
FromNEAR SH 36
ToNEAR RISING STAR SCL
CSJ0127-02-147
Proj IDSTP 2018(211)
Work TypeUTILITY ADJUSTMENTS
 
0.6672732059.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days790
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-142
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183221
Totals16887011.550.000.000.0

CountyMCCULLOCH
HighwayUS 190
FromUS 87
ToUS 377
CSJ0128-04-035
Proj IDSTP 2017(458)
Work TypeRECONSTRUCT URBAN ROAD
 
17.5745261640.44514800.389.7
CountyMCCULLOCH
HighwayUS 190
FromUS 87
ToUS 377
CSJ0128-04-036
Proj IDROW 128-4-36
Work TypeROW ACQUISITION
 
0.8803315712.431103993.2333.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began05-16-18
Work Completed
Time Computed00-00-00
Contract Working Days446
Addl Days Granted0
Working Days Charged31
Percent Time Used6
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0128-04-035
KASPARIAN UNDERGROUND (2.57)
S & H POWERLINE (3.88)
W.S. CONSTRUCTION COMPANY (4.05)
F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (3.37)
D. I. J. CONSTRUCTION, INC. (0.62)
TEXAS STATE UTILITIES, INC. (7.34)
ROADWAY SPECIALTIES, INC. (2.08)
FLASHER LIMITED (0.76)
B-CORP UTILITIES, INC. (9.96)
PIPE WHOLESALERS OF TEXAS, INC. (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
Contract #01183224
Totals8577352.87861163.271618793.6118.8

CountyCOMANCHE
HighwaySH 36
FromEASTLAND C/L
ToFM 1477
CSJ0182-02-038
Proj IDC 182-2-38
Work TypeBASE OVERLAY,2 COURSE SURF TRT, ACP
 
10.0005024304.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days235
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0182-02-038
D. I. J. CONSTRUCTION, INC. (2.00)
DIIBS SPECIALISTS (0.74)
MARCOM"S MOWING SERVICE, LLC (0.44)
TEXAS ALTERNATIVE GRASSER, INC. (0.17)
LONE STAR PAVING (43.74)
Contract #03183238
Totals5024304.050.000.000.0

CountyCOMANCHE
HighwaySH 36
From1 MI. S. OF 1702
ToHAMILTON C/L
CSJ0183-01-043
Proj IDSTP 2018(227)
Work TypeACP OVERLAY
 
5.909918207.812085.200.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-043
D. I. J. CONSTRUCTION, INC. (3.14)
FLASHER LIMITED (0.47)
Contract #10173015
Totals918207.810.002085.200.2

CountyLAMPASAS
HighwayUS 190
From0.1 MI EAST US 183
To0.1 MI WEST LP 257
CSJ0231-01-056
Proj IDC 231-1-56
Work TypePLANING AND ACP OVERLAY
 
1.094667334.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0231-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183252
Totals667334.230.000.000.0

CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-041
Proj IDSTP 1602(303)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.7343157515.042073305.7365.6
CountySTEPHENS
HighwayUS 183
FromUS 180
ToBRECKENRIDGE SCL
CSJ0257-01-044
Proj IDROW 257-1-44
Work TypeUTILITY ADJUSTMENTS
 
0.734580454.40610526.7099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began10-16-17
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged158
Percent Time Used66
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0257-01-041
D.I.J. CONSTRUCTION, INC (1.53)
FAMBRO CONSTRUCTION, INC. (13.08)
HJC FARMS, INC. (1.46)
J & M CONTRACTING COMPANY (17.96)
TEXAS ALTERNATIVE GRASSER, INC. (0.13)
WILLIS ELECTRIC CO., LP (0.53)
Contract #04173226
Totals3737969.44239490.552683832.4371.7

CountyBROWN
HighwaySH 279
FromFM 2632
To1.2 MI E OF FM 2632
CSJ0480-01-039
Proj IDSTP 1802(256)HES
Work TypeCURVE IMPROVEMENTS
 
1.1551175289.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0480-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183255
Totals1175289.000.000.000.0

CountyMILLS
HighwayFM 45
FromBROWN C/L
ToSAN SABA C/L
CSJ0480-07-009
Proj IDSTP 1602(052)
Work TypeGRADING, STRUCTURES, BASE, AND SURF
 
4.3624563803.884626370.0199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted124
Working Days Charged359
Percent Time Used94
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0480-07-009
D.I.J. CONSTRUCTION, INC (1.28)
TEXAS ALTERNATIVE GRASSER, INC. (0.60)
HJC FARMS, INC. (0.95)
J&M CONTRACTING COMPANY (14.23)
Contract #05163004
Totals4563803.8885577.074626370.0199.9

CountyCOLEMAN ETC
HighwaySH 153 ETC
FromRUNNELS C/L
To0.013 MI. W OF CR 407
CSJ0636-01-038
Proj IDSTP 1802(202)HES
Work TypeMILLED EDGELINE/CENTERLINE RUMBLE
 
55.0991682223.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days114
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0636-01-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183257
Totals1682223.990.000.000.0

CountyCOMANCHE
HighwayCR
FromON CR 403 AT DRAW
To.
CSJ0923-17-076
Proj IDBR 2015(346)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100217652.00223423.0099.9
CountyCOMANCHE
HighwayCR
FromON CR 304 AT INDIAN CREEK
To.
CSJ0923-17-078
Proj IDBR 2016(003)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100568174.50561378.5098.8
CountyCOMANCHE
HighwayFM 1689
FromAT WALNUT CREEK
To.
CSJ1033-04-021
Proj IDBR 1602(572)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100994764.15908795.4591.8
CountyCOMANCHE
HighwayFM 1477
FromAT N COPPERAS CREEK
To.
CSJ1366-01-009
Proj IDBR 1602(573)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100684261.20662386.4096.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began12-07-16
Work Completed
Time Computed00-00-00
Contract Working Days264
Addl Days Granted13
Working Days Charged283
Percent Time Used102
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-076
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.69)
ODUM SERVICES, L.P. (2.90)
PEACHTREE CONSTRUCTION, LTD. (3.50)
STRIPE-A-ZONE, INC. (0.53)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
DFW REBAR, INC. (0.28)
Contract #08163217
Totals2464851.8539919.402355983.3595.7

page 1 | page 2