Monthly State Let Construction Report For Amarillo District As Of Jul 13, 2018 Page 2 Of 2

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOTTER
HighwayIH 40
From0.15 MILES WEST OF WASHINGTON ST
ToNELSON STREET
CSJ0275-01-177
Proj IDNH 1602(189)
Work TypeREHAB EXISTING ROADWAY
 
2.97736259776.7022346465.4561.6
Work Order09-26-16
Work Began11-01-16
Work Completed
Time Computed10-31-16
Contract Working Days332
Addl Days Granted32
Working Days Charged342
Percent Time Used93
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-177
BARRICADES UNLIMITED (1.47)
TRUMBLE CRANE & RIGGING (0.15)
HOWELL SAND CO. (1.54)
A BROTHERS MILLING, LLC (0.52)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.33)
BOWMAN ENGINEERING & CONSULTING, INC (2.70)
ER HAWKINS, LLC (1.81)
UNDER CONSTRUCTION INC. (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (12.18)
W. W. FOUNDATION DRILLING, LTD. (1.81)
HJC FARMS, INC. (2.16)
WILLIS ELECTRIC CO., LP (3.73)
OSCAR ORDUNO, INC. (1.49)
SOUTH TEXAS PAINTING COMPANY (0.59)
MICA CORPORATION (0.72)
LMN TRANSPORT (0.15)
ANTIGO CONSTRUCTION, INC. (0.04)
HOWELL SAND CO. (0.02)
COLTON GRADING & EXCAVATION (0.16)
PANHANDLE STEEL ERECTORS (0.30)
ALAMO BROTHERS CONCRETE, INC. (0.70)
MCM (1.55)
SOUTHEAST GRINDING & GROOVING, LLC (0.00)
Contract #06163003
Totals36259776.701387900.6722346465.4561.6

CountyPOTTER
HighwayIH 40
FromAT WHITAKER STREET
To.
CSJ0275-01-180
Proj IDBR 2018(359)
Work TypeREPLACE EXISTING BRIDGE
 
8.37450440638.563828180.737.5
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-16-18
Contract Working Days696
Addl Days Granted0
Working Days Charged66
Percent Time Used9
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-180
BARRICADES UNLIMITED (1.72)
ANTIGO CONSTRUCTION, INC. (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.19)
HJC FARMS, INC. (1.10)
PRIMATE CONSTRUCTION, INC. (0.27)
ALAMO BROTHERS CONCRETE, INC. (7.92)
WOLFE CONSTRUCTION GROUP, INC. (0.12)
OSCAR ORDUNO, INC. (5.20)
WILLIS ELECTRIC CO., LP (3.07)
L A FULLER & SONS CONSTRUCTION, LTD. (2.10)
MCL CONTRACTING, LLC (0.88)
SLATON BROTHERS, INC. (3.63)
Contract #01183002
Totals50440638.56466183.063828180.737.5

CountyHANSFORD
HighwaySH 15
FromSH 136 IN GURVER
ToSH 207 IN SPEARMAN
CSJ0308-02-029
Proj IDSTP 1602(139)
Work TypeRESTORATION OF EXISTING ROADWAY
 
19.9009135715.429795073.7799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-28-16
Work Began00-00-00
Work Completed
Time Computed08-26-16
Contract Working Days210
Addl Days Granted30
Working Days Charged218
Percent Time Used90
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-02-029
H & F TRUCKING (22.50)
WOLFE CONSTRUCTION GROUP, INC. (0.08)
DUSTROL, INC. (0.37)
BARRICADES UNLIMITED (1.27)
HJC FARMS, INC. (0.00)
Contract #05163030
Totals9135715.420.009795073.7799.9

CountyLIPSCOMB
HighwaySH 15
FromFM 1455
ToOKLAHOMA STATE LINE
CSJ0355-01-048
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
12.3624980635.654901180.5199.3
CountyLIPSCOMB
HighwaySH 15
FromOCHILTREE COUNTY LINE
To1000' EAST OF COUNTY ROAD 4
CSJ0355-02-031
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
3.118986876.401009670.5799.9
CountyLIPSCOMB
HighwaySH 23
FromFM 377
To11.05 MILES NORTH OF US 83
CSJ1337-01-023
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
10.0632183107.752279683.8499.9
Work Order08-05-16
Work Began00-00-00
Work Completed
Time Computed09-04-16
Contract Working Days77
Addl Days Granted15
Working Days Charged136
Percent Time Used147
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-048
BARRICADES UNLIMITED (2.40)
DUSTROL, INC. (0.89)
Contract #06163023
Totals8150619.801383352.038190534.9299.9

CountyARMSTRONG
HighwaySH 207
FromFM 1151
ToFM 2272
CSJ0357-03-025
Proj IDSTP 1802(471)HES
Work TypeIMPROVE GRDRAIL TO DESIGN STANDARDS
 
13.077185271.000.000.0
CountyARMSTRONG
HighwaySH 207
FromFM 2272
ToBRISCOE COUNTY LINE
CSJ0357-05-025
Proj IDSTP 1802(471)HES
Work TypeIMPROVE GRDRAIL TO DESIGN STANDARDS
 
13.481983692.000.000.0
CountyGRAY
HighwaySH 273
FromLP 171 SOUTH OF PAMPA
To0.452 MI N OF FM 291
CSJ0560-01-032
Proj IDSTP 1802(570)
Work TypeSAFETY IMPROVEMENT TYPE PROJECT
 
11.101482496.500.000.0
CountyGRAY
HighwaySH 273
From0.452 MI N OF FM 291
ToBI 40-H IN MCLEAN
CSJ0560-02-036
Proj IDSTP 1802(471)HES
Work TypeIMPROVE GRDRAIL TO DESIGN STANDARDS
 
19.708606497.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0357-03-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183219
Totals2257957.000.000.000.0

CountyROBERTS
HighwayFM 282
FromAT RED DEER CREEK IN MIAMI
To.
CSJ0798-01-025
Proj IDBR 2018(223)
Work TypeBRIDGE REPLACEMENT
 
0.1702093931.75848182.0240.5
Work Order03-07-18
Work Began00-00-00
Work Completed
Time Computed04-06-18
Contract Working Days242
Addl Days Granted0
Working Days Charged58
Percent Time Used23
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0798-01-025
BARRICADES UNLIMITED (1.18)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (10.39)
BOWMAN ENGINEERING & CONSULTING, INC (0.42)
DIIBS SPECIALISTS (0.85)
DUSTROL, INC. (0.62)
PANOLA SIGN & BARRICADE, INC. (1.12)
PENHALL COMPANY (0.35)
WOLFE CONSTRUCTION GROUP, INC. (0.27)
Contract #02183237
Totals2093931.75282011.70848182.0240.5

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-180
Proj IDSTP 2018(521)
Work TypeTHERMOPLASTIC STRIPING
 
100.000482197.49467648.4096.9
Work Order03-15-18
Work Began00-00-00
Work Completed
Time Computed05-15-18
Contract Working Days36
Addl Days Granted0
Working Days Charged26
Percent Time Used72
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-180
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183207
Totals482197.49374554.59467648.4096.9

CountyARMSTRONG
HighwayCR
FromON CR 25
ToAT WEST FORK COTTONWOOD CREEK
CSJ0904-06-010
Proj IDBR 1702(575)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100193932.00156607.0080.7
CountyGRAY
HighwayCR
FromON CR 17
ToAT GRAPEVINE CRK
CSJ0904-13-024
Proj IDBR 1702(577)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.010677227.00245821.4036.2
CountyGRAY
HighwayCR
FromON HOG FARM ROAD
ToAT TURKEY CREEK BR
CSJ0904-13-025
Proj IDBR 1702(574)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.010255185.0010000.003.9
CountyGRAY
HighwayCR
FromON WEST LINE ROAD
ToAT MCCLELLAN CREEK
CSJ0904-13-026
Proj IDBR 1702(576)
Work TypeREPLACE BRIDGE
 
0.100398982.0018119.004.5
Work Order03-07-18
Work Began00-00-00
Work Completed
Time Computed04-06-18
Contract Working Days185
Addl Days Granted3
Working Days Charged46
Percent Time Used24
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-06-010
MORRIS COUNTY CONTRACTORS, LLC (5.23)
PANOLA SIGN & BARRICADE, INC. (1.53)
WOLFE CONSTRUCTION GROUP, INC. (1.55)
Contract #02183014
Totals1525326.00119268.40430547.4028.2

CountyHARTLEY
HighwayFM 767
FromAT PUNTA DE AGUA CREEK
To.
CSJ1108-01-020
Proj IDBR 2018(436)
Work TypeBRIDGE REPLACEMENT
 
0.5314253525.12499201.9911.7
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-16-18
Contract Working Days280
Addl Days Granted0
Working Days Charged38
Percent Time Used13
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1108-01-020
ALTUS TRAFFIC MANAGEMENT LLC (0.42)
WOLFE CONSTRUCTION GROUP, INC. (0.40)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.33)
GARY A. CRAIN, INC. (0.23)
DUSTY ALLEN, INC. (0.80)
L A FULLER & SONS CONSTRUCTION, LTD. (20.27)
BOWMAN ENGINEERING & CONSULTING, INC. (0.55)
Contract #01183019
Totals4253525.12395197.19499201.9911.7

CountyRANDALL
HighwayLP 335
FromIH 27, E
ToBNSF RR
CSJ2635-02-022
Proj IDDMO 2012(189)
Work TypeADDITIONAL 2 LANES AND BRIDGES
 
3.00032232646.8632354997.7194.8
Work Order03-04-14
Work Began11-03-14
Work Completed
Time Computed03-20-14
Contract Working Days645
Addl Days Granted180
Working Days Charged312
Percent Time Used67
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE, INC. (7.46)
BARRICADES UNLIMITED (1.53)
LONE STAR PRODUCTS (FLOWER MOUND) (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73)
MCL CONTRACTING, LLC (0.04)
PENHALL COMPANY (AUSTIN) (0.02)
WILLIS ELECTRIC CO., LP (2.97)
SCOTT DERR PAINTING CO, LLC (0.12)
DUSTIN ALLEN, INC. (0.00)
Contract #12133202
Totals32232646.86657760.5132354997.7194.8

page 1 | page 2