Monthly State Let Construction Report For Amarillo District As Of Apr 10, 2018 Page 2 Of 2

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOTTER
HighwayIH 40
FromAT SL335 (LAKESIDE)
To.
CSJ0275-01-168
Proj IDNH 1502(349)
Work TypeCONSTRUCT TURNAROUNDS
 
0.3402519584.252637488.3899.9
CountyRANDALL
HighwaySL 335
From0.13 MILES EAST OF GEORGIA ST.
To0.26 MILES WEST OF FM 1541
CSJ2635-02-028
Proj IDSTP 2013(605)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
0.80817821897.2017817008.8399.4
Work Order07-31-15
Work Began08-10-15
Work Completed
Time Computed08-10-15
Contract Working Days460
Addl Days Granted10
Working Days Charged468
Percent Time Used99
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-168
TRUMBLE CRANE & RIGGING (0.21)
DUSTIN ALLEN, INC. (1.07)
L. A. FULLER & SONS CONSTRUCTION, LTD. (22.92)
WILLIS ELECTRIC CO., LP (1.80)
OSCAR ORDUNO, INC. (3.65)
BARRICADES UNLIMITED (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.67)
INDUS CONSTRUCTION, L.P. (1.34)
MCL CONTRACTING, LLC (0.13)
BREDA COMPANY, INC. (3.57)
ALAMO BROTHERS CONCRETE (0.42)
CINTEREX US, INC. (1.46)
WOLFE CONSTRUCTION GROUP, INC. (0.07)
A BROTHERS MILLING, LLC (0.64)
PENHALL COMPANY (0.09)
LLOYD D. NABORS DEMOLITION LLC (0.62)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
J. LEE MILLIGAN, INC. (0.55)
DISCOUNT FENCE COMPANY (0.10)
WEBBER BARRIER SERVICES, LLC. (1.04)
BILL AYRES LAWN & TREE SERVICE (0.12)
Contract #04153057
Totals20341481.45282035.0620454497.2199.9

CountyPOTTER
HighwayIH 40
From0.15 MILES WEST OF WASHINGTON ST
ToNELSON STREET
CSJ0275-01-177
Proj IDNH 1602(189)
Work TypeREHAB EXISTING ROADWAY
 
2.97736259776.7017851979.5549.2
Work Order09-26-16
Work Began11-01-16
Work Completed
Time Computed10-31-16
Contract Working Days332
Addl Days Granted49
Working Days Charged281
Percent Time Used73
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-177
BARRICADES UNLIMITED (1.47)
TRUMBLE CRANE & RIGGING (0.15)
HOWELL SAND CO. (1.54)
A BROTHERS MILLING, LLC (0.52)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.33)
BOWMAN ENGINEERING & CONSULTING, INC (2.70)
ER HAWKINS, LLC (1.81)
UNDER CONSTRUCTION INC. (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (12.18)
W. W. FOUNDATION DRILLING, LTD. (1.81)
HJC FARMS, INC. (2.16)
WILLIS ELECTRIC CO., LP (3.73)
OSCAR ORDUNO, INC. (1.49)
SOUTH TEXAS PAINTING COMPANY (0.59)
MICA CORPORATION (0.72)
LMN TRANSPORT (0.15)
ANTIGO CONSTRUCTION, INC. (0.04)
HOWELL SAND CO. (0.02)
COLTON GRADING & EXCAVATION (0.16)
PANHANDLE STEEL ERECTORS (0.30)
ALAMO BROTHERS CONCRETE, INC. (0.70)
Contract #06163003
Totals36259776.701541390.4317851979.5549.2

CountyPOTTER
HighwayIH 40
FromAT WHITAKER STREET
To.
CSJ0275-01-180
Proj IDBR 2018(359)
Work TypeREPLACE EXISTING BRIDGE
 
8.37450440638.56291900.000.5
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-16-18
Contract Working Days696
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-180
BARRICADES UNLIMITED (1.72)
ANTIGO CONSTRUCTION, INC. (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.19)
Contract #01183002
Totals50440638.560.00291900.000.5

CountyHANSFORD
HighwaySH 15
FromSH 136 IN GURVER
ToSH 207 IN SPEARMAN
CSJ0308-02-029
Proj IDSTP 1602(139)
Work TypeRESTORATION OF EXISTING ROADWAY
 
19.9009135715.429679615.8299.9
Work Order07-28-16
Work Began00-00-00
Work Completed
Time Computed08-26-16
Contract Working Days210
Addl Days Granted30
Working Days Charged213
Percent Time Used88
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-02-029
H & F TRUCKING (22.50)
WOLFE CONSTRUCTION GROUP, INC. (0.08)
DUSTROL, INC. (0.37)
BARRICADES UNLIMITED (1.27)
HJC FARMS, INC. (0.00)
Contract #05163030
Totals9135715.421085326.769679615.8299.9

CountyLIPSCOMB
HighwaySH 15
FromFM 1455
ToOKLAHOMA STATE LINE
CSJ0355-01-048
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
12.3624980635.651306504.7626.2
CountyLIPSCOMB
HighwaySH 15
FromOCHILTREE COUNTY LINE
To1000' EAST OF COUNTY ROAD 4
CSJ0355-02-031
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
3.118986876.400.000.0
CountyLIPSCOMB
HighwaySH 23
FromFM 377
To11.05 MILES NORTH OF US 83
CSJ1337-01-023
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
10.0632183107.752255986.8499.9
Work Order08-05-16
Work Began00-00-00
Work Completed
Time Computed09-04-16
Contract Working Days77
Addl Days Granted0
Working Days Charged77
Percent Time Used100
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-048
BARRICADES UNLIMITED (2.40)
Contract #06163023
Totals8150619.80653404.763562491.6043.7

CountyMOORE
HighwaySH 152
FromDUMAS CITY LIMITS
ToHUTCHINSON COUNTY LINE
CSJ0557-01-028
Proj IDSTP 2016(683)
Work TypeRESTORATION
 
47.26315561610.5317528755.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-24-16
Work Began07-06-16
Work Completed
Time Computed06-23-16
Contract Working Days130
Addl Days Granted20
Working Days Charged129
Percent Time Used86
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84)
DUSTROL, INC. (2.04)
W.S. CONSTRUCTION COMPANY (1.58)
CF TRUCKING, LLC (1.46)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.15)
HJC FARMS, INC. (0.21)
VANCE BROTHERS, INC. (5.72)
Contract #02163003
Totals15561610.530.0017528755.8499.9

CountyROBERTS
HighwayFM 282
FromAT RED DEER CREEK IN MIAMI
To.
CSJ0798-01-025
Proj IDBR 2018(223)
Work TypeBRIDGE REPLACEMENT
 
0.1702093931.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days242
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0798-01-025
BOWMAN ENGINEERING & CONSULTING, INC (0.42)
Contract #02183237
Totals2093931.750.000.000.0

CountyPOTTER
HighwayVA
FromAT VARIOUS LOCATIONS IN AMARILLO
To.
CSJ0904-00-160
Proj IDSTP 2015(649)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012895601.552981454.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-15
Work Began07-06-15
Work Completed
Time Computed05-24-15
Contract Working Days274
Addl Days Granted14
Working Days Charged300
Percent Time Used104
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE (56.56)
BTA SERVICES, LTD. (1.91)
W.A. ROBBINS CONSTRUCTION CO., INC. (6.35)
QLVS, INC. DBA PHASE 3 ELECTRIC (1.30)
PAVEMENT MARKINGS INC. (2.36)
Contract #03153026
Totals2895601.550.002981454.2599.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-169
Proj IDSTP 2018(003)
Work TypeCRACK SEAL
 
1.000839950.50833033.7599.1
CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-177
Proj IDC 904-00-177
Work TypeCRACK SEAL
 
1.000155791.90162868.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed11-13-17
Contract Working Days60
Addl Days Granted0
Working Days Charged29
Percent Time Used48
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-169
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173224
Totals995742.400.00995901.9599.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-180
Proj IDSTP 2018(521)
Work TypeTHERMOPLASTIC STRIPING
 
100.000482197.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-180
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183207
Totals482197.490.000.000.0

CountyARMSTRONG
HighwayCR
FromON CR 25
ToAT WEST FORK COTTONWOOD CREEK
CSJ0904-06-010
Proj IDBR 1702(575)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100193932.000.000.0
CountyGRAY
HighwayCR
FromON CR 17
ToAT GRAPEVINE CRK
CSJ0904-13-024
Proj IDBR 1702(577)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.010677227.000.000.0
CountyGRAY
HighwayCR
FromON HOG FARM ROAD
ToAT TURKEY CREEK BR
CSJ0904-13-025
Proj IDBR 1702(574)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.010255185.000.000.0
CountyGRAY
HighwayCR
FromON WEST LINE ROAD
ToAT MCCLELLAN CREEK
CSJ0904-13-026
Proj IDBR 1702(576)
Work TypeREPLACE BRIDGE
 
0.100398982.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days185
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-06-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183014
Totals1525326.000.000.000.0

CountyHARTLEY
HighwayFM 767
FromAT PUNTA DE AGUA CREEK
To.
CSJ1108-01-020
Proj IDBR 2018(436)
Work TypeBRIDGE REPLACEMENT
 
0.5314253525.120.000.0
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-16-18
Contract Working Days280
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1108-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183019
Totals4253525.120.000.000.0

CountyPOTTER
HighwayRM 1061
FromFM 2381
To7.5 MILES NORTH OF FM 2381
CSJ1245-02-043
Proj IDSTP 1502(299)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
10.5397907537.757987700.5099.9
CountyPOTTER
HighwayRM 1061
From10.50 MILES NORTH OF FM 2381
ToOLDHAM COUNTY LINE
CSJ1245-02-044
Proj IDSTP 1502(355)
Work TypeADD PASSING LANES FOR SAFETY
 
12.8372230786.342425197.5399.9
Work Order08-20-15
Work Began02-03-16
Work Completed
Time Computed08-03-15
Contract Working Days234
Addl Days Granted19
Working Days Charged238
Percent Time Used94
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85)
HJC FARMS, INC. (1.25)
W.S. CONSTRUCTION COMPANY (9.93)
WILLIS ELECTRIC CO., LP (0.46)
Contract #06153245
Totals10138324.096582.7810412898.0399.9

CountyRANDALL
HighwayLP 335
FromIH 27, E
ToBNSF RR
CSJ2635-02-022
Proj IDDMO 2012(189)
Work TypeADDITIONAL 2 LANES AND BRIDGES
 
3.00032232646.8629877936.5587.1
Work Order03-04-14
Work Began11-03-14
Work Completed
Time Computed03-20-14
Contract Working Days645
Addl Days Granted180
Working Days Charged248
Percent Time Used53
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE, INC. (7.46)
BARRICADES UNLIMITED (1.53)
LONE STAR PRODUCTS (FLOWER MOUND) (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73)
MCL CONTRACTING, LLC (0.04)
PENHALL COMPANY (AUSTIN) (0.02)
WILLIS ELECTRIC CO., LP (2.97)
SCOTT DERR PAINTING CO, LLC (0.12)
DUSTIN ALLEN, INC. (0.00)
Contract #12133202
Totals32232646.86548375.5029877936.5587.1

page 1 | page 2