Work Order
On construction,
Section 130
, and replanking
projects, TxDOT issues a Work Order to the railroad company to provide
labor for installation, modification, and removal of crossing surface panels,
railroad warning devices, track and/or other railroad equipment.
A Work Order will also
be required for railroad
flagging. On Section 130
projects, a Work Order
is issued to the local government for any work to be reimbursed
by TxDOT.The Work Order is issued after the district has identified
a proper means to inspect the work to be performed, including any
traffic control performed by the railroad company’s contractor.
The railroad company will request the Work Order after materials
have been assembled and 2 weeks prior to a crew beginning work.
The district will issue the Work Order on all types of projects.