Work Order

On construction,
Section 130
, and replanking projects, TxDOT issues a Work Order to the railroad company to provide labor for installation, modification, and removal of crossing surface panels, railroad warning devices, track and/or other railroad equipment. A Work Order
will also
be required for railroad flagging. On
Section 130
projects, a Work Order is issued to the local government for any work to be reimbursed by TxDOT.
The Work Order is issued after the district has identified a proper means to inspect the work to be performed, including any traffic control performed by the railroad company’s contractor. The railroad company will request the Work Order after materials have been assembled and 2 weeks prior to a crew beginning work.
The district will issue the Work Order on all types of projects.