2004 English Special Provisions by Item (Statewide & Districtwide, Current)
|
Specification Information
|
Search For a Special Provision or Specification
|
|
SP008-162 |
PDF |
RTF |
- Removes software specific references. As a result, the scheduling software preference must be stated in the general notes to Item 8. For One-Time-Use only until approval for a state-wide special provision is received.
(Change Memo: de-05-14). Statewide Use.
|
SP008-119 |
PDF |
RTF |
- Removes the requirement to execute the subcontractor agreement between the prime contractor and the subcontractor prior to receiving the approval from the Engineer to sublet a portion of the construction. Required for all federally funded projects beginning with the July 2010 letting.
Replaces SP008-084 . (Change Memo: de-10-10). Statewide Use.
|
SP008-092 |
PDF |
RTF |
- Imposes a 60 delay for beginning work and time charges. For projects accelerated to March 2009 and not funded with Proposition 14
Statewide Use.
|
SP008-086 |
PDF |
RTF |
- This special provision replaces 008---049 and 008---050 and is for use in contracts requiring CPM scheduling.
Replaces SP008-049 SP008-050 . (Change Memo: de-11-08). Statewide Use.
|
SP008-070 |
PDF |
RTF |
- Providers for incentives using Road-User Cost or Contract Administration Liquidated Damages and disincentives using Road-User Cost. May used at the districts option.
Replaces SP008-001 SP008-004 SP008-005 SP008-025 SP008-026 . (Change Memo: de-08-07). Statewide Use.
|
SP008-069 |
PDF |
RTF |
- Providers for no excuse incentives using Road-User Cost or Contract Administration Liquidated Damages and disincentives using Road-User Cost. May be used at the districts option.
Replaces SP008-001 SP008-004 SP008-005 SP008-025 SP008-026 . (Change Memo: de-08-07). Statewide Use.
|
SP008-063 |
PDF |
RTF |
- Clarifies that time charges begin when the plans specify a start work date.
Replaces SP008-003 . (Change Memo: de-35-06). Statewide Use.
|
SP008-030 |
PDF |
RTF |
- Clarifies that liquidated damages will be imposed if call out work is not completed on time. Use at the districts option.
(Change Memo: de-38-05). Statewide Use.
|
SP008-017 |
PDF |
RTF |
- Allows for a lane rental charge for each lane or lanes closed or obstructed by Contractor.
(Change Memo: de-02-05). Statewide Use.
|
SP008-011 |
PDF |
RTF |
- Provides for open season for application of asphalt for selected projects. To be used for surface treatment-only, asphaltic-concrete-overlay-only and micro-surfacing-only contracts
(Change Memo: de-33-04). Statewide Use.
|
SP008-009 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 180 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
SP008-008 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 120 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
SP008-007 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 90 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
SP008-006 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 60 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
|
|
DALLAS - DISTRICT 18 |
SP008-125 |
PDF |
RTF |
- Provides for a daily “intersection rental charge” based on road user costs.
Districtwide Use.
|
SP008-097 |
PDF |
RTF |
- This special provision removes items associated with production rates, activity pace, and resource loading from the statewide version.
Districtwide Use.
|
|
|
AUSTIN - DISTRICT 14 |
SP008-013 |
PDF |
RTF |
- Lane closure assessment fees
Districtwide Use.
|
|
|
DALLAS - DISTRICT 18 |
SP008-013 |
PDF |
RTF |
- Lane closure assessment fees
Districtwide Use.
|
|
|
HOUSTON - DISTRICT 12 |
SP008-013 |
PDF |
RTF |
- Lane closure assessment fees
Districtwide Use.
|