FM 1518 from FM 78 to I-10

FM 1518 Expansion

TxDOT is moving forward with the expansion of FM 1518 from FM 78 to I-10 in Bexar County. The FM 1518 Expansion project will include $73 million of transportation improvements designed to increase mobility and safety along 5.6 miles of the corridor.

Improvements 

The project will include the following improvements:

  • Expansion of the existing roadway to include two 11-ft. lanes in each direction;
  • Construction of a 34-f.t wide raised center median
  • Construction of a 10-ft. wide shared-use path along the eastside of the roadway; and,
  • Construction of a 6-ft. wide sidewalk along the westside of the roadway

Benefits

Once complete, the FM 1518 Expansion will improve mobility and enhance safety by:

  • Increasing connectivity
  • Separating opposing lanes of traffic
  • Integrating bike and pedestrian access with the construction of sidewalk and shared-use path accommodations

Timeline

The project will be constructed in phases beginning in spring 2024 and is expected to be completed in 2028.

Phase I

  • Utility work throughout the corridor
  • Work on FM 78 and FM 1518 intersection

Phase II

  • Work between Lisa Meadows and I-10
  • Bridge widening at Woman Hollering Creek

Phase III

  • Work between Lisa Meadows and Aztec Lane

Phase IV

  • Sidewalks, median and final paving

Construction

Throughout construction, drivers will experience temporary traffic shifts and daytime lane closures between the hours of 9 AM and 4 PM. When lane closures are scheduled, advance notice will be given to the public.

Work is anticipated to take place on weekdays, generally from 8 a.m. to 5 p.m., Monday through Friday. Occasional night-time work will be performed to limit impacts to traffic. Weekend closures may be needed when major construction operations are taking place.

Project updates

TxDOT is committed to providing timely information and updates on the project. If you are interested in receiving updates, please subscribe.

You may submit questions, comments or concerns about the project by emailing FM1518@TxDOTSA.com or calling 210-321-2021.