Contact Us | Site Map | Home      
TxDOT Home
About Us  |  Careers  |  Local Information  |  News  |  Programs  |  Services
Execute Search
TxDOT employees discussing plans
Citizen
Business
Government
Travel
FAQs
Tools & Plug-Ins

Senate Bill 370 Report – Construction Contracts

A. Construction Contracts

1. A+B bidding and incentive/disincentive provisions.

In contrast to traditional bidding procedures which require acceptance of only the lowest responsive bid, "A+B" bidding involves time, with its associated cost, in the low bid determination. Under this method, each bid submitted consists of two components. The cost or "A" component is the traditional bid for the contract items and is the dollar amount of all work to be performed under the contract. The time or "B" component is a bid of the total number of calendar days estimated by the contractor to complete the project.

In A+B bidding, the bid for award consideration is based on a combination of the bid for the contract items and the associated cost of the time needed to complete the work based upon the following formula: (A) + [(B) x (daily road user cost + estimated contract administration liquidated damage rate)]. This formula is used only for award determination; contract payments are based solely upon the "A" component. If awarded, the days for project completion included in a contractor’s proposal become a part of the contract entered into by the contractor and department. Advantages of A+B bidding include:

  • Consideration is provided for the time component of a construction contract.
  • Favors contractor with most available resources to complete the project.
  • Encourages contractors to seek ways to compress the construction schedule. The potential for early project completion is therefore enhanced.

As required by Transportation Code, Section 223.012(a)(1), a disincentive provision that assesses road user (travel delay) costs can be incorporated into the contract to discourage the contractor from overrunning the time "bid" for the project. In addition, an incentive provision could be included to reward the contractor if the work is completed earlier than the time bid.

A+B bidding and road-user cost liquidated damages are not applicable to all projects. In some cases, calculation of travel delays do not generate values justifying the use of higher road user costs. In addition, A+B projects are more limited in application. When the benefits for early completion are outweighed by the cost of construction, higher road-user costs are not considered beneficial to the public. Also, before a project can be considered for A+B bidding, all right of way must first be acquired, and utilities adjusted or relocated. This is so that a contractor can’t later claim that the department caused an inability to meet the contracted time frame.

Currently the department is working to train employees in all districts about how to calculate road user costs. Additionally, contractual language is being developed that can be utilized in construction contracts at the Commission’s discretion. Once this language is approved by the department, it will be available to be implemented state-wide.

Status: A+B bidding has been used by TxDOT on a limited, trial-run basis. Results from the trial have been encouraging. The department has implemented policies and strategies for the greater use of incentive/disincentive on projects.

2. Use of intermediate milestones.

The A+B bidding and incentive/disincentive contracting strategies referred to previously were discussed as being applied to a project as a whole. They may also be applied to projects on a phase-by-phase basis or to only a critical portion of a project. The contractual approach is to establish a completion milestone to the phase or portion of the project which is deemed most important. The allowable time to complete the work tied to the milestone is established by the department or by the contractor if A+B bidding is used. If the contractor fails to complete the intermediate milestone work, then the travel delay, or road user costs associated with the work, are assessed on a day-by-day basis. An incentive may also be included to credit the contractor for early completion.

Intermediate milestones provide flexibility to address the specific areas of projects that will have the most impact on the public. For instance, a contract may provide for the reconstruction of a five-mile section of roadway, a half-mile of which is through an urban area. An intermediate milestone could be established in the contract to provide for the accelerated completion of the urban section only. Other examples of where TxDOT has used intermediate milestones include: Work areas affecting malls, specific intersections, portions of a project to provide access to a university, and portions of a project to extend a toll road. In the last example, the daily value of the incentive/disincentive was based on an estimate of the daily tolls that would be received.

The same concerns cited in the previous section regarding outstanding right-of-way acquisitions and utility relocation are also applicable to intermediate milestones.

Status: Intermediate milestones have been used by TxDOT successfully in the past, and continue to be used. Department staff statewide is being made more aware of the tool and how to utilize it in contracts.

 
Transportation Planning & Programming
Transportation Planning
Highway Designation Files
Additional Plans & Projects
Rail Information
Other Resources
 
 

Contact Us | Site Map | Home

Citizen | Business | Government | Travel | FAQs | Tools & Plug-Ins

About Us | Careers | Local Information | News | Programs | Services

Disclaimer | Privacy and Security Policy | Accessibility Policy


125 East 11th Street . Austin, Texas 78701
Copyright 2008 Texas Department of Transportation . All Rights Reserved