|
Rail Capacity Enhancements |
Improvement Classification Level |
Estimated Cost |
Estimated Public
Benefit* |
Ratio:
Benefit/Cost |
|
Second Main: Dawes to Sheldon |
2 |
$43,000,000 |
NA |
NA |
|
Second Main: Sheldon to Dayton Jct |
4 |
$117,000,000 |
NA |
NA |
|
Total Identified Improvements |
$160,000,000 |
|
|
*No public benefits of individual rail improvements were identified.
The identified rail improvements represent what may be considered the
ultimate build-out. It should be noted, however, that incrementally phasing in
the rail improvements may also provide near to immediate private and public
benefits. Railroad infrastructure improvements and at-grade crossing
closure/separation could be phased in as follows:
- Phase I – Dawes to Sheldon, approximately 8 miles
- Phase II – Sheldon to Dayton, approximately 17 miles
Addition of Second Mainline from Dawes to Dayton
Junction
A single mainline of track currently makes up the Lafayette Subdivision between
Dayton and Dawes. Limited passing sidings combined with a large local industry
base along the corridor do not allow trains to pass one another, nor are there
adequate locations for trains entering into the Houston rail network to sit and
wait their turn to get into the queue for movement to one of the rail yards or
outlying locations. The addition of a second mainline of track ultimately from
Dayton to Dawes will improve the mobility of train traffic moving through this
corridor, and may reduce westbound train re-crew requirements.
Analysis
Mobility would essentially be improved because the local trains could perform
their daily pick-up and delivery requirements, ultimately providing a more
reliable level of service to the industries served, while allowing through
trains to pass by on the new line. Currently, the predominant flow on this route
is westbound; however a second mainline may ultimately accommodate bidirectional
traffic.
Phase I
The first phase may include constructing approximately 8 miles of a second
mainline between Dawes and Sheldon to a point just west of the San Jacinto River
crossing. An alignment shift may be necessary so that the second mainline can be
constructed between the existing rail line and Business US Hwy 90. Concurrently,
however, for this improvement to have merit, an additional mainline between East
Settegast and Dawes may be required.
The addition of a second mainline along the subdivision from Dawes to Sheldon
is estimated to cost $42,080,000 and is classified as a level 2 mid-range
railroad improvement.
Phase II The second phase may include the addition of a second mainline along the
subdivision from Sheldon to Dayton Junction is estimated to cost $117,000,000
and is classified as a level 4 long-range improvement. The addition of a second
mainline should undergo further testing to determine the extent of the
improvement’s impact on the region’s rail network, and to quantify the
associated public and private benefits that may be attained.
Back to top
Identified Improvements
|