The SH 161 project is a four-phase proposal consisting of tolled main
lanes and tolled managed lanes using existing TxDOT corridors along portions of
SH 161, I-20, SH 360 and US 287.
| Date |
Action |
|
| August 1, 2005 |
Unsolicited proposal submitted by AECOM |
| September 29, 2005 |
Authorization by the Texas Transportation Commission to issue request for competing proposals and qualifications |
| May 5, 2006 |
TxDOT issued request for
competing proposals and qualifications |
| August 31, 2006 |
Deadline to submit competing
proposals:
- Accoina Concessiones USA LLC
- ACS-ZAI SH 161 Team
- Babcock & Brown, Transurnban & Fluor*
- B3 ConnecTexas
- DFW Southern Gateway
- FCC Construccion S.A.-SNC-Lavalin
- Mid-Cities Transportation Partners*
- OHL Infrastructure*
- Prairie Highway Group
- Skanska*
|
| November 15, 2006 |
TxDOT evaluation and short list of teams
(*see list above) |
| TBA |
Authorization by the Texas Transportation Commission to issue request for detailed proposals |
| TBA |
TxDOT issues request for detailed proposals |
| TBA |
Deadline to submit detailed proposals |
| TBA |
TxDOT evaluation |
| TBA |
Selection of best-value proposal |