| Date |
Action |
|
| March 30, 2006 |
Authorization by the Texas Transportation Commission to issue request for proposals and qualifications |
| Dec. 8, 2006 |
TxDOT issues request for proposals and qualifications |
| March 15, 2007 |
Deadline to submit proposals and qualifications
- Acciona-Omega
- B3 Connect Texas*
- FCC Construccion, S.A.
- Itinere Infrastructure, LLC*
- NTE Mobility Partners*
- OHL Infrastructure, Inc.*
- T-Bar Mobility Alliance
|
| Completed |
TxDOT evaluation and
short list of teams* |
| Dec. 13, 2007 |
Authorization by the Texas
Transportation Commission to issue Request for Proposals |
| March 3, 2008 |
TxDOT issues Request for Proposals |
| Nov. 17, 2008 |
Deadline to submit detailed proposals |
| TBA |
TxDOT evaluation |
| TBA |
Selection of best-value proposal |