Special Construction Contract Provisions (September, 1997) - SP-8

The following Special Provisions modify, amplify, or amend the General Provisions with respect to the clauses cited below and no other clauses or requirements of these items are waived or changed hereby. The Special Provisions shall take precedence over the General Provisions.

SP-1. Modify Section 10 - Definition of Terms
SP-2. Modify Section 20 - Proposal Requirements and Conditions
SP-3. Modify Section 30 - Award and Execution of Contract
SP-4. Modify Section 40 - Scope of Work
SP-5. Modify Section 50 - Control of Work
SP-6. Add to Section 60 - Control of Materials
SP-7 Modify Section 70 - Legal Regulations and Responsibility to Public
SP-8. Modify Section 80 - Prosecution and Progress
SP-9. Modify Section 90 - Measurement and Payment
SP-10. Certification of NPDES Permit

SP-8. Modify SECTION 80 - PROSECUTION AND PROGRESS as follows:

Add to Paragraph 80-01 SUBLETTING OF CONTRACT, the following:

If a Storm Water Pollution Prevention Plan (SW3P) is included in this project, no subcontractor who is to implement any measure identified on the Storm Water Pollution Prevention Plan, will be approved for work until the subcontractor has submitted a signed copy of the certification statement described in Part IV.E.2 of the National Pollutant Discharge Elimination System (NPDES) permit (40 CFR Part 122) and in the Special Provision SP-9, "Certification of NPDES Permit". If an approved subcontractor does not comply with the provisions of the NPDES permit, approval may be revoked.

In Paragraph 80-02 NOTICE TO PROCEED, change the last sentence to read:

The contractor shall begin the work to be performed under the contract not later than the effective date by the Engineer in the written notice to proceed, but in any event, the Contractor shall notify the Engineer at least 48 hours in advance of the time actual construction operations will begin.

In Paragraph 80-03 PROSECUTION AND PROGRESS, change the fifth sentence to read:

Should the prosecution of the work be discontinued for any reason, the Contractor shall notify the Engineer at least 48 hours in advance of resuming operations.

Add to Paragraph 80-03 PROSECUTION AND PROGRESS, the following:

If a Storm Water Pollution Prevention Plan (SW3P) is included in this project, the Contractor, and all subcontractors implementing any measure identified on the SW3P, must submit to the Engineer a signed copy of the certification statement as described in Part IV.E.2 of the NPDES permit (40 CFR Part 122) no later than 48 hours prior to beginning work.

 
Aviation
Services
Airport Rules & Standards
Events
Programs
Pilot Information
Other Resources
 
 

Home

About Us | Careers | Local Information | News

125 East 11th Street . Austin, Texas 78701 . Disclaimer . Privacy Policy . Accessibility Policy
Copyright 2008 Texas Department of Transportation . All Rights Reserved