The following Special Provisions modify, amplify, or amend the General
Provisions with respect to the clauses cited below and no other clauses or
requirements of these items are waived or changed hereby. The Special Provisions
shall take precedence over the General Provisions.
SP-1. Modify Section 10 - Definition of Terms
SP-2. Modify Section 20 - Proposal Requirements and Conditions
SP-3. Modify Section 30 - Award and Execution of Contract
SP-4. Modify Section 40 - Scope of Work
SP-5. Modify Section 50 - Control of Work
SP-6. Add to Section 60 - Control of Materials
SP-7 Modify Section 70 - Legal Regulations and Responsibility
to Public
SP-8. Modify Section 80 - Prosecution and Progress
SP-9. Modify Section 90 - Measurement and Payment
SP-10. Certification of NPDES Permit
SP-4. Modify SECTION 40 - SCOPE OF WORK as follows:
In Paragraph 40-02 ALTERATION OF WORK AND QUANTITIES, add the following:
For AIP contracts all supplemental agreements shall be approved by TxDOT
and shall include valid wage determinations of the U.S. Secretary of Labor
when the amount of the supplemental agreement exceeds $2000. However, if the
contractor elects to waive the limitations on work that increases or
decreases the originally awarded contract or any major contract item by more
than 25 percent, the supplemental agreement shall be subject to the same
U.S. Secretary of Labor wage determination as was included in the originally
awarded contract.
All supplemental agreements shall require consent of the Contractor's
surety and separate performance and payment bonds.
|