Section 80 - Prosecution and Progress
Section 90 - Measurement and Payment
Section 100 - Contractor Quality Control Program
Section 110 - Methods
of Estimating Percentage of Material within Specifications
(PWL) [pdf, 5 pages, 21kb]
Section 80 - Prosecution and Progress
80-01 SUBLETTING OF CONTRACT. The owner will not recognize any subcontractor
on the work. The Contractor shall at all times when work is in progress be
represented either in person, by a qualified superintendent, or by other
designated, qualified representative who is duly authorized to receive and
execute orders of the Engineer.
Should the Contractor elect to assign his/her contract, said assignment shall
be concurred in by the surety, shall be presented for the consideration and
approval of the owner, and shall be consummated only on the written approval of
the owner. In case of approval, the Contractor shall file copies of all
subcontracts with the Engineer.
80-02 NOTICE TO PROCEED. The notice to proceed shall state the date on which
it is expected the Contractor will begin the construction and from which date
contract time will be charged. The Contractor shall begin the work to be
performed under the contract within 10 days of the date set by the Engineer in
the written notice to proceed, but in any event, the Contractor shall notify the
Engineer at least 24 hours in advance of the time actual construction operations
will begin.
80-03 PROSECUTION AND PROGRESS. Unless otherwise specified, the Contractor
shall submit his/her progress schedule for the Engineer's approval within 10
days after the effective date of the notice to proceed. The Contractor's
progress schedule, when approved by the Engineer, may be used to establish major
construction operations and to check on the progress of the work. The Contractor
shall provide sufficient materials, equipment, and labor to guarantee the
completion of the project in accordance with the plans and specifications within
the time set forth in the proposal.
If the Contractor falls significantly behind the submitted schedule, the
Contractor shall, upon the Engineer's request, submit a revised schedule for
completion of the work within the contract time and modify his/her operations to
provide such additional materials, equipment, and labor necessary to meet the
revised schedule. Should the prosecution of the work be discontinued for any
reason, the Contractor shall notify the Engineer at least 24 hours in advance of
resuming operations.
For AIP contracts, the Contractor shall not commence any actual construction
prior to the date on which the notice to proceed is issued by the owner.
80-04 LIMITATION OF OPERATIONS. The Contractor shall control his/her
operations and the operations of his/her subcontractors and all suppliers so as
to provide for the free and unobstructed movement of aircraft in the AIR
OPERATIONS AREAS of the airport.
When the work requires the Contractor to conduct his/her operations within an
AIR OPERATIONS AREA of the airport, the work shall be coordinated with airport
management (through the Engineer) at least 48 hours prior to commencement of
such work. The Contractor shall not close an AIR OPERATIONS AREA until so
authorized by the Engineer and until the necessary temporary marking and
associated lighting is in place as provided in the subsection titled BARRICADES,
WARNING SIGNS, AND HAZARD MARKINGS of Section 70.
When the contract work requires the Contractor to work within an AIR
OPERATIONS AREA of the airport on an intermittent basis (intermittent opening
and closing of the AIR OPERATIONS AREA), the Contractor shall maintain constant
communications as hereinafter specified; immediately obey all instructions to
vacate the AIR OPERATIONS AREA; immediately obey all instructions to resume work
in such AIR OPERATIONS AREA. Failure to maintain the specified communications or
to obey instructions shall be cause for suspension of the Contractor's
operations in the AIR OPERATIONS AREA until the satisfactory conditions are
provided. The following AIR OPERATIONS AREA (AOA) cannot be closed to operating
aircraft to permit the Contractor's operations on a continuous basis and will
therefore be closed to aircraft operations intermittently as described in the
special conditions, or on the plans.
80-05 CHARACTER OF WORKERS, METHODS, AND EQUIPMENT. The Contractor shall, at
all times, employ sufficient labor and equipment for prosecuting the work to
full completion in the manner and time required by the contract, plans, and
specifications.
All workers shall have sufficient skill and experience to perform properly
the work assigned to them. Workers engaged in special work or skilled work shall
have sufficient experience in such work and in the operation of the equipment
required to perform the work satisfactorily.
All equipment which is proposed to be used on the work shall be of sufficient
size and in such mechanical condition as to meet requirements of the work and to
produce a satisfactory quality of work. Equipment used on any portion of the
work shall be such that no injury to previously completed work, adjacent
property, or existing airport facilities will result from its use.
When the methods and equipment to be used by the Contractor in accomplishing
the work are not prescribed in the contract, the Contractor is free to use any
methods or equipment that will accomplish the work in conformity with the
requirements of the contract, plans, and specifications. When the contract
specifies the use of certain methods and equipment, such methods and equipment
shall be used unless others are authorized by the Engineer. If the Contractor
desires to use a method or type of equipment other than specified in the
contract, he may request authority from the Engineer to do so. The request shall
be in writing and shall include a full description of the methods and equipment
proposed and of the reasons for desiring to make the change. If approval is
given, it will be on the condition that the Contractor will be fully responsible
for producing work in conformity with contract requirements. If, after trial use
of the substituted methods or equipment, the Engineer determines that the work
produced does not meet contract requirements, the Contractor shall discontinue
the use of the substitute method or equipment and shall complete the remaining
work with the specified methods and equipment. The Contractor shall remove any
deficient work and replace it with work of specified quality, or take such other
corrective action as the Engineer may direct. No change will be made in basis of
payment for the contract items involved nor in contract time as a result of
authorizing a change in methods or equipment under this subsection.
80-06 TEMPORARY SUSPENSION OF THE WORK. The Engineer shall have the authority
to suspend the work wholly, or in part, for such period or periods as he may
deem necessary, due to unsuitable weather, or such other conditions as are
considered unfavorable for the prosecution of the work, or for such time as is
necessary due to the failure on the part of the Contractor to carry out orders
given or perform any or all provisions of the contract.
In the event that the Contractor is ordered by the Engineer, in writing, to
suspend work for some unforeseen cause not otherwise provided for in the
contract and over which the Contractor has no control, the Contractor may be
reimbursed for actual money expended on the work during the period of shutdown.
No allowance will be made for anticipated profits. The period of shutdown shall
be computed from the effective date of the Engineer's order to suspend work to
the effective date of the Engineer's order to resume the work. Claims for such
compensation shall be filed with the Engineer within the time period stated in
the Engineer's order to resume work. The Contractor shall submit with his/her
claim information substantiating the amount shown on the claim. The Engineer
will forward the Contractor's claim to the owner for consideration in accordance
with local laws or ordinances. No provision of this article shall be construed
as entitling the Contractor to compensation for delays due to inclement weather,
for suspensions made at the request of the Contractor, or for any other delay
provided for in the contract, plans, or specifications.
If it should become necessary to suspend work for an indefinite period, the
Contractor shall store all materials in such manner that they will not become an
obstruction nor become damaged in any way. He shall take every precaution to
prevent damage or deterioration of the work performed and provide for normal
drainage of the work. The Contractor shall erect temporary structures where
necessary to provide for traffic on, to, or from the airport. 80-07
DETERMINATION AND EXTENSION OF CONTRACT TIME. The number of calendar or working
days allowed for completion of the work shall be stated in the proposal and
contract and shall be known as the CONTRACT TIME.
Should the contract time require extension for reasons beyond the
Contractor's control, it shall be adjusted as follows:
CONTRACT TIME based on WORKING DAYS shall be calculated weekly by the
Engineer. The Engineer will furnish the Contractor a copy of his/her weekly
statement of the number of working days charged against the contract time during
the week and the number of working days currently specified for completion of
the contract (the original contract time plus the number of working days, if
any, that have been included in approved CHANGE ORDERS or SUPPLEMENTAL
AGREEMENTS covering EXTRA WORK).
The Engineer shall base his/her weekly statement of contract time charged on
the following considerations:
- No time shall be charged for days on which the Contractor is unable to
proceed with the principal item of work under construction at the time for
at least 6 hours with the normal work force employed on such principal item.
Should the normal work force be on a double-shift, 12 hours shall be used.
Should the normal work force be on a triple-shift, 18 hours shall apply.
Conditions beyond the Contractor's control such as strikes, lockouts,
unusual delays in transportation, temporary suspension of the principal item
of work under construction or temporary suspension of the entire work which
have been ordered by the Engineer for reasons not the fault of the
Contractor, shall not be charged against the contract time.
- The Engineer will not make charges against the contract time prior to
the effective date of the notice to proceed.
- The Engineer will begin charges against the contract time on the first
working day after the effective date of the notice to proceed.
- The Engineer will not make charges against the contract time after the
date of final acceptance as defined in the subsection titled FINAL
ACCEPTANCE of Section 50.
- The Contractor will be allowed 1 week in which to file a written protest
setting forth his/her objections to the Engineer's weekly statement. If no
objection is filed within such specified time, the weekly statement shall be
considered as acceptable to the Contractor.
The contract time (stated in the proposal) is based on the originally
estimated quantities as described in the subsection titled INTERPRETATION OF
ESTIMATED PROPOSAL QUANTITIES of Section 20. Should the satisfactory
completion of the contract require performance of work in greater quantities
than those estimated in the proposal, the contract time shall be increased
in the same proportion as the cost of the actually completed quantities
bears to the cost of the originally estimated quantities in the proposal.
Such increase in contract time shall not consider either the cost of work or
the extension of contract time that has been covered by change order or
supplemental agreement and shall be made at the time of final payment.
CONTRACT TIME based on CALENDAR DAYS shall consist of the number of
calendar days stated in the contract counting from the effective date of the
notice to proceed and including all Saturdays, Sundays, holidays, and
nonwork days. All calendar days elapsing between the effective dates of the
Engineer's orders to suspend and resume all work, due to causes not the
fault of the Contractor, shall be excluded.
At the time of final payment, the contract time shall be increased in the
same proportion as the cost of the actually completed quantities bears to
the cost of the originally estimated quantities in the proposal. Such
increase in the contract time shall not consider either cost of work or the
extension of contract time that has been covered by a change order or
supplemental agreement. Charges against the contract time will cease as of
the date of final acceptance.
When the contract time is a specified completion date, it shall be the
date on which all contract work shall be substantially completed.
If the Contractor finds it impossible for reasons beyond his/her control
to complete the work within the contract time as specified, or as extended
in accordance with the provisions of this subsection, he may, at any time
prior to the expiration of the contract time as extended, make a written
request to the Engineer for an extension of time setting forth the reasons
which he believes will justify the granting of his/her request. The
Contractor's plea that insufficient time was specified is not a valid reason
for extension of time. If the Engineer finds that the work was delayed
because of conditions beyond the control and without the fault of the
Contractor, he may extend the time for completion in such amount as the
conditions justify. The extended time for completion shall then be in full
force and effect, the same as though it were the original time for
completion.
80-08 FAILURE TO COMPLETE ON TIME. For each calendar day or working day,
as specified in the contract, that any work remains uncompleted after the
contract time (including all extensions and adjustments as provided in the
subsection titled DETERMINATION AND EXTENSION OF CONTRACT TIME of this
Section) the sum specified in the contract and proposal as liquidated
damages will be deducted from any money due or to become due the Contractor
or his/her surety. Such deducted sums shall not be deducted as a penalty but
shall be considered as liquidation of a reasonable portion of damages that
will be incurred by the owner should the Contractor fail to complete the
work in the time provided in his/her contract.
Permitting the Contractor to continue and finish the work or any part of
it after the time fixed for its completion, or after the date to which the
time for completion may have been extended, will in no way operate as a
wavier on the part of the owner of any of its rights under the contract.
80-09 DEFAULT AND TERMINATION OF CONTRACT. The Contractor shall be
considered in default of his/her contract and such default will be
considered as cause for the owner to terminate the contract for any of the
following reasons if the Contractor:
- Fails to begin the work under the contract within the time specified
in the "Notice to Proceed," or
- Fails to perform the work or fails to provide sufficient workers,
equipment or materials to assure completion of work in accordance with
the terms of the contract, or
- Performs the work unsuitably or neglects or refuses to remove
materials or to perform a new such work as may be rejected as
unacceptable and unsuitable, or
- Discontinues the prosecution of the work, or
- Fails to resume work which has been discontinued within a reasonable
time after notice to do so, or
- Becomes insolvent or is declared bankrupt, or commits any act of
bankruptcy or insolvency, or
- Allows any final judgment to stand against him unsatisfied for a
period of 10 days, or
- Makes an assignment for the benefit of creditors, or
- For any other cause whatsoever, fails to carry on the work in an
acceptable manner.
Should the Engineer consider the Contractor in default of the
contract for any reason hereinbefore, he shall immediately give written
notice to the Contractor and the Contractor's surety as to the reasons
for considering the Contractor in default and the owner's intentions to
terminate the contract.
If the Contractor or surety, within a period of 10 days after such
notice, does not proceed in accordance therewith, then the owner will,
upon written notification from the Engineer of the facts of such delay,
neglect, or default and the Contractor's failure to comply with such
notice, have full power and authority without violating the contract, to
take the prosecution of the work out of the hands of the Contractor. The
owner may appropriate or use any or all materials and equipment that
have been mobilized for use in the work and are acceptable and may enter
into an agreement for the completion of said contract according to the
terms and provisions thereof, or use such other methods as in the
opinion of the Engineer will be required for the completion of said
contract in an acceptable manner.
All costs and charges incurred by the owner, together with the cost
of completing the work under contract, will be deducted from any monies
due or which may become due the Contractor. If such expense exceeds the
sum which would have been payable under the contract, then the
Contractor and the surety shall be liable and shall pay to the owner the
amount of such excess.
80-10 TERMINATION FOR NATIONAL EMERGENCIES. The owner shall terminate
the contract or portion thereof by written notice when the Contractor is
prevented from proceeding with the construction contract as a direct
result of an Executive Order of the President with respect to the
prosecution of war or in the interest of national defense.
When the contract, or any portion thereof, is terminated before
completion of all items of work in the contract, payment will be made
for the actual number of units or items of work completed at the
contract price or as mutually agreed for items of work partially
completed or not started. No claims or loss of anticipated profits shall
be considered.
Reimbursement for organization of the work, and other overhead
expenses, (when not otherwise included in the contract) and moving
equipment and materials to and from the job will be considered, the
intent being that an equitable settlement will be made with the
Contractor.
Acceptable materials, obtained or ordered by the Contractor for the
work and that are not incorporated in the work shall, at the option of
the Contractor, be purchased from the Contractor at actual cost as shown
by receipted bills and actual cost records at such points of delivery as
may be designated by the Engineer.
Termination of the contract or a portion thereof shall neither
relieve the Contractor of his/her responsibilities for the completed
work nor shall it relieve his/her surety of its obligation for and
concerning any just claim arising out of the work performed. |