December 8, 2006
TxDOT issues request for proposals and qualifications.
March 15, 2007
Deadline to submit proposals and qualifications
Completed
TxDOT evaluation and short list of teams.*
December 13, 2007
Authorization by the Texas Transportation Commission to issue request for
detailed proposals.
March 3, 2008
TxDOT issues Request for Proposals.
December 1, 2008
Deadline to submit detailed proposals.
January 29, 2009
Selection of best-value proposal and conditional award to NTE Mobility Partners
April 14, 2009
CDA Public Hearing
June 23, 2009
Commercial close
Summer 2009
Team opens local office and begins design
Summer 2009
Team begins master plan for Phase 2
Late 2009
Financial close
Early 2010
Begin right of way purchases and utility relocations
Early 2011
Construction begins on Phase 1
Late 2010
Master plan developed