Contact:
Telephone: |
|
Val Lopez
(817) 370-6630 |
|
|
August 4,
2008 |
|
FORTH WORTH - Work begins
Wednesday, August 6, 2008, on the
reconstruction of the Vickery Street
bridge over U.S. 287 in Fort Worth
that will close the bridge for
approximately 10 months. The $2.89
million project will include the
rebuilding of the bridge and the
addition of sidewalks.
Motorists will be detoured to the
frontage roads and directed to the
nearest crossovers at Rosedale
Street and Riverside Drive for the
Vickery Street bridge closure.
Removal of the bridge is scheduled
for the weekend of August 15-17,
weather permitting, and will
required U.S.. 287 to be closed
north and southbound. Traffic will
be diverted to the frontage roads
during the removal.
TxDOT awarded the project to SCR
Construction Co., Inc. of Richmond.
The project is estimated for
completion by summer 2009.
Project daily lane closures are
accessible
here. |