Overpass to Be Constructed on US 271 at FM 3417


Contact: Marcus Sandifer

Phone: (903) 799-1306

Date: May 25, 2017


ATLANTA – A section of US 271 south of Mount Pleasant will be upgraded, extending the current bypass and constructing an overpass and interchange at FM 3417 according to plans approved in May by the Texas Department of Transportation (TxDOT).

“We will be extending the freeway section of US 271 south about one mile from where it ends now,” said Bill Compton, area engineer for TxDOT in Mount Pleasant. “This will include constructing an overpass and interchange at FM 3417, as well as new entrance/exit ramps and turnarounds under the overpass to help improve traffic flow.”

East Texas Bridge Inc. of Longview was awarded the contract for the construction project with a bid of $12.3 million.

Work on the project should begin in August and take about 17 months to complete, Compton said.

###

The Texas Department of Transportation is responsible for maintaining 80,000 miles of road and for supporting aviation, rail, and public transportation across the state. Through collaboration and leadership, we deliver a safe, reliable, and integrated transportation system that enables the movement of people and goods.  Find out more at TxDOT.gov. "Like" us on Facebook and follow us on Twitter.