Detail Letting Schedule for Navarro County (FY 2014)

Last Update: Monday, May 20, 2013
Navarro County (FY 2014)

CCSJ: 0092-06-100

District: Dallas Let Date: MAR 2014
Highway: IH 45 Let Status: Tentative
Project ID: IM ( ) CSJ: 0092-06-100
Description: INSTALL GUIDE SIGNS Handling
Code:
 
Limits From: NORTH OF US 287 Fund Cat: 1
Limits To: ELLIS/NAVARRO COUNTY LINE Estimate: $67,640
Length: 13.2 Miles Actual:  
 
District: Dallas Let Date: MAR 2014
Highway: IH 45 Let Status: Tentative
Project ID: IM ( ) CSJ: 0093-01-091
Description: INSTALL GUIDE SIGNS Handling
Code:
 
Limits From: NORTH OF FM 1394 Fund Cat: 1
Limits To: NORTH OF US 287 Estimate: $67,640
Length: 13.7 Miles Actual:  
 
District: Dallas Let Date: MAR 2014
Highway: IH 45 Let Status: Tentative
Project ID: IM ( ) CSJ: 0166-01-048
Description: INSTALL GUIDE SIGNS Handling
Code:
 
Limits From: NAVARRO/FREESTONE COUNTY LINE Fund Cat: 1
Limits To: NORTH OF FM 1394 Estimate: $45,117
Length: 6.6 Miles Actual:  
 
Back...

Totals for 0092-06-100
Length: 33.5 Miles
Estimate: $180,397
Actual:  

CCSJ: 0997-01-042

District: Dallas Let Date: OCT 2013
Highway: FM 639 Let Status: Tentative
Project ID: STP ( ) CSJ: 0997-01-042
Description: SEAL COAT, PVMT MKGS, MAILBOXES Handling
Code:
 
Limits From: FM 744 Fund Cat: 1
Limits To: SH 22 Estimate: $181,000
Length: 6.4 Miles Actual:  
 
Back...

Totals for 0997-01-042
Length: 6.4 Miles
Estimate: $181,000
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract