Letting Schedule for Childress District (FY 2014)

Last Update: Monday, May 20, 2013
Childress District (FY 2014)
Briscoe | Dickens | Donley | Foard | Hall | Hardeman | Wheeler

Briscoe County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0357-06-020 SH 207 Tentative JUL 2014 $667,198 8 REALIGN INTERSECTIONS
0453-06-011 SH 207 Tentative NOV 2013 $2,821,802 1 WIDENING OF NON - FREEWAY FACILITY
0925-12-014 PW Tentative SEP 2013 $249,412 10 REPAIR DRAINAGE FACILITIES WITHIN CAPROCK CANYON STATE PARK

Dickens County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0925-15-007 CR Tentative APR 2014 $1,105,880 6 REPLACE BRIDGE AND APPROACHES

Donley County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0042-06-067 US 287 Tentative OCT 2013 $3,023,566 1 ASPHALTIC CONCRETE PAVEMENT OVERLAY

Foard County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0098-02-025 SH 6 Tentative JUN 2014 $1,648,000 6 REPLACE BRIDGE AND APPROACHES
0146-05-033 US 70 Tentative DEC 2013 $3,329,589 1 ACP OVERLAY

Hall County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0303-05-018 SH 86 Tentative MAR 2014 $1,726,769 ROW REHABILITATION OF EXISTING ROADWAY
0541-02-031 SH 256 Tentative JUL 2014 $2,250,000 1 REHABILITATION OF EXISTING ROADWAY
0704-03-014 FM 94 Tentative JAN 2014 $3,000,000 1 WIDENING OF NON - FREEWAY FACILITY
0925-09-030 CR Tentative FEB 2014 $358,600 6 REPLACEMENT OF EXISTING BRIDGE
2253-01-014 FM 2361 Tentative JUN 2014 $192,800 6 REPLACE BRIDGE AND APPROACHES

Hardeman County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0043-02-071 US 287 Tentative OCT 2013 $1,251,359 1 ASPHALTIC CONCRETE PAVEMENT OVERLAY
0925-07-013 CR Tentative FEB 2014 $382,600 6 REPLACE EXISTING BRIDGE FACILITY

Wheeler County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0030-08-033 US 83 Tentative SEP 2013 $3,893,448 1 SEAL COAT


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract