Letting Schedule for San Antonio District (FY 2013)
| San Antonio District (FY 2013) |
| Atascosa | Bandera | Bexar | Comal | Frio | Guadalupe | Kendall | Kerr | McMullen | Medina | Uvalde | Wilson | ||||||
Atascosa County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
|---|---|---|---|---|---|---|
| 0073-05-065 | IH 37 | Approved | JUN 2013 | $5,863,916 | 1 | MILL, BASE REPAIR, SEAL COAT, OVERLAY, PAVEMENT MARKINGS |
| 2975-01-008 | FM 2924 | Actual | JAN 2013 | $2,186,637 | 1 | REHABILITATE AND WIDEN NARROW ROADWAY TO ADD SHOULDERS |
Bandera County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 1066-01-022 | PR 37 | Actual | NOV 2012 | $792,516 | 8 | WIDEN NARROW ROADWAY TO ADD SHOULDERS |
Bexar County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0016-07-132 | IH 35 | Actual | FEB 2013 | $287,875 | 10 | LANDSCAPE DEVELOPMENT |
| 0017-02-075 | IH 35 | Actual | SEP 2012 | $6,192,763 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0017-09-094 | IH 35 | Actual | DEC 2012 | $1,079,436 | 1 | OVERLAY AND PAVEMENT MARKINGS |
| 0017-10-261 | IH 35 | Approved | JUL 2013 | $67,348,688 | 1 | EXPAND FROM 6 TO 8 LANE EXPRESSWAY AND OPERATIONAL |
| 0025-02-192 | IH 10 | Actual | DEC 2012 | $1,073,789 | 1 | RECONSTRUCT AND RECONFIGURE INTERSECTION, RAMP & FRONTAGE RD |
| 0025-02-194 | IH 10 | Actual | APR 2013 | $12,027,793 | 3 | IMPROVE VERTICAL CLEARANCE AT S. NEW BRAUNFELS, GEVERS, AND |
| 0072-07-060 | IH 10 | Approved | JUN 2013 | $6,425,745 | 3 | RECONSTRUCT BRIDGE AT FM 3351 AND RESTRIPE FRONTAGE ROADS |
| 0072-08-136 | LP 345 | Actual | APR 2013 | $13,883,097 | ROW | GRADE SEPARATION @ MEDICAL & OPERATIONAL IMPVMNTS ON MEDICAL |
| 0072-12-190 | IH 10 | Actual | DEC 2012 | $3,140,320 | 1 | MILL, SC, OVERLAY AND RESTRIPE FOR OPERATIONAL IMPROVEMENTS |
| 0073-08-172 | IH 37 | Actual | FEB 2013 | $6,991,145 | 1 | MILL, OVERLAY, & PAVEMENT MARKINGS (SB MAINLANES ONLY) |
| 0073-08-173 | US 281 | Actual | MAY 2013 | $143,550 | 10 | LANDSCAPE DEVELOPMENT |
| 0253-06-035 | SP 536 | Approved | JUN 2013 | $1,977,660 | ROW | WIDEN ROADWAY TO PROVIDE CONTINUOUS LEFT TURN LANE, BIKE |
| 0465-02-024 | FM 1518 | Actual | SEP 2012 | $1,138,014 | 1 | REPLACE CULVERT WITH SLAB SPAN BRIDGE |
| 0521-01-045 | LP 13 | Approved | JUL 2013 | $1,824,817 | ROW | CONSTRUCT SIDEWALK |
| 0915-00-160 | VA | Actual | FEB 2013 | $1,179,951 | 1 | DISTRICTWIDE NON - SITE SPECIFIC TRAFFIC SIGNALS |
| 0915-00-164 | VA | Actual | FEB 2013 | $1,218,087 | 1 | DISTRICTWIDE NON - SITE SPECIFIC TRAFFIC SIGNALS |
| 0915-12-394 | CS | Approved | AUG 2013 | $676,938 | 7 | CONSTRUCT BIKE LANE |
| 0915-12-481 | CS | Actual | APR 2013 | $10,662,561 | 3 | RECONSTRUCT EXISTING 4 LANES WITH SIDEWALKS, CURBS, DRAINAGE |
| 0915-12-510 | CS | Approved | AUG 2013 | $3,940,630 | 7 | RECONSTRUCT ROADWAY AND INCLUDES SIDEWALKS, CURB, DRAINAGE |
| 0915-12-523 | VA | Actual | DEC 2012 | $407,180 | 1 | INSTALL WARNING DEVICES AT LOW WATER CROSSINGS |
| 0915-12-524 | VA | Actual | JAN 2013 | $105,353 | 10 | PURCHASE AND INSTALL WRONG WAY SIGNS AND DETECTION EQUIPMENT |
| 0915-12-526 | VA | Actual | MAY 2013 | $10,000,000 | 7 | CONSTRUCTION OF NORTH - SOUTH & EAST - WEST STREETCAR SYSTEM |
| 0915-12-528 | VA | Actual | FEB 2013 | $92,000,000 | 3 | MODERN STREET CAR, BUS RAPID TRANSIT, PARK & RIDE FACILITIES |
| 2452-01-051 | LP 1604 | Actual | SEP 2012 | $11,250,794 | 8 | CONSTRUCT GRADE SEPARATION |
Comal County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0215-02-048 | BS 46-C | Approved | AUG 2013 | $10,796,401 | 3 | EXPAND FROM 2 LANES TO 4 LANES |
| 0253-03-068 | US 281 | Approved | AUG 2013 | $3,000,000 | 3 | CONSTRUCT TURNAROUNDS |
| 0857-01-028 | FM 306 | Actual | OCT 2012 | $3,508,596 | 1 | WIDEN TO PROVIDE TURN LANES |
Frio County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0017-07-132 | IH 35 | Approved | AUG 2013 | $980,000 | 8 | INSTALL TRAFFIC SIGNAL |
| 0017-15-021 | BI 35-E | Actual | NOV 2012 | $161,457 | 1 | SEAL COAT AND PAVEMENT MARKINGS |
| 1729-01-015 | FM 462 | Actual | OCT 2012 | $4,686,835 | 1 | REHAB EXISTING ROADWAY & SHOULDERS |
Guadalupe County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0025-03-092 | US 90 | Actual | MAY 2013 | $3,965,069 | 6 | SCOUR REPAIR |
| 0025-03-095 | IH 10 | Actual | NOV 2012 | $685,062 | 1 | SEAL COAT AND PAVEMENT MARKINGS (EB FRONTAGE RDS) |
| 0025-10-073 | FM 78 | Actual | JAN 2013 | $4,136,147 | 1 | RECONSTRUCT AND WIDEN EXISTING ROADWAY |
| 0366-02-082 | SH 123 | Actual | DEC 2012 | $4,567,416 | 1 | RECONSTRUCT ROADWAY TO IMPROVE SIGHT DISTANCE AND UPGRADE |
| 0535-01-069 | IH 10 | Approved | JUL 2013 | $3,900,250 | 3 | RECONSTRUCT & RECONFIGURE RAMPS AND FRONTAGE ROAD |
Kendall County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0072-14-025 | US 87 | Actual | OCT 2012 | $733,996 | 1 | UPGRADE EXISTING TRAFFIC SIGNALS |
Kerr County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0142-08-006 | FM 394 | Actual | NOV 2012 | $727,371 | 1 | REHAB & WIDEN NARROW ROADWAY TO ADD SHOULDERS |
McMullen County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0915-51-009 | PW | Actual | NOV 2012 | $308,546 | 10 | SURFACE ENTRANCE EXISTING ROAD AND CONSTRUCT PARKING LOTS |
Medina County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0017-05-092 | IH 35 | Approved | JUL 2013 | $1,660,160 | 3 | RELOCATE EXISTING ENTRANCE RAMP & CONSTRUCT PARTIAL |
| 0848-01-038 | FM 462 | Actual | SEP 2012 | $3,295,349 | 1 | REHAB & WIDEN NARROW ROADWAY TO ADD SHOULDERS |
Uvalde County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0235-05-030 | SH 55 | Approved | JUL 2013 | $2,570,113 | ROW | RECONSTRUCT ROADWAY TO IMPROVE DRAINAGE AND OPERATIONAL |
Wilson County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0100-03-076 | US 181 | Approved | AUG 2013 | $1,240,000 | 8 | INSTALL TRAFFIC SIGNAL |
|