Letting Schedule for Brownwood District (FY 2013)
| Brownwood District (FY 2013) |
| Brown | Comanche | Eastland | Lampasas | McCulloch | Mills | San Saba | Stephens | ||||||
Brown County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
|---|---|---|---|---|---|---|
| 0128-01-102 | US 377 | Actual | NOV 2012 | $6,328,264 | 1 | SEAL COAT |
| 0923-06-062 | CS | Approved | JUN 2013 | $1,408,391 | 3 | CONSTRUCT NEW 2 LANE ROADWAY WITH CONTINUOUS LEFT TURN LANE |
| 2377-01-039 | FM 2524 | Actual | APR 2013 | $4,694,757 | ROW | RECONSTRUCT EXISTING ROADWAY INCLUDING ACP, CURB & GUTTER, |
Comanche County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0923-17-073 | CR | Approved | AUG 2013 | $1,136,623 | 6 | REPLACE BRIDGE AND APPROACHES |
| 1039-01-033 | FM 1476 | Actual | FEB 2013 | $948,319 | 6 | REPLACE BRIDGE AND APPROACHES |
| 2992-01-010 | FM 2861 | Approved | JUL 2013 | $600,541 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
Eastland County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0007-03-086 | IH 20 | Actual | SEP 2012 | $1,384,989 | 8 | INSTALL MEDIAN BARRIER |
| 0007-06-070 | IH 20 | Actual | OCT 2012 | $16,358,387 | 9 | CONSTRUCT TWO SAFETY REST AREAS |
Lampasas County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 1032-01-032 | FM 580 | Actual | SEP 2012 | $2,683,161 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
McCulloch County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 1102-01-041 | SH 71 | Approved | JUL 2013 | $12,250,899 | 6 | WIDEN SUBGRADE, ADD PASSING LANES, STRUCTURE, AND SURFACE |
Mills County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0923-23-026 | CS | Approved | JUL 2013 | $1,131,348 | 3 | CONSTRUCT WELCOME CENTER |
San Saba County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0923-25-021 | CS | Approved | MAY 2013 | $110,000 | 1 | LANDSCAPE DEVELOPMENT |
Stephens County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0714-03-022 | FM 717 | Actual | SEP 2012 | $2,554,818 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
|