Detail Letting Schedule for Fort Bend County (FY 2013)
| Fort Bend County (FY 2013) |
CCSJ: 0187-05-050 | |||
| District: | Houston | Let Date: | AUG 2013 |
| Highway: | SP 10 | Let Status: | Approved |
| Project ID: | C 187-5-50 | CSJ: | 0187-05-050 |
| Description: | CONSTRUCT 2 - LANE RURAL FACILITY ON A NEW LOCATION AND REMOVE | Handling Code: |
|
| Limits From: | US 59 SOUTH | Fund Cat: | 3 |
| Limits To: | SH 36 | Estimate: | $21,999,740 |
| Length: | 5.0 Miles | Actual: | |
|
Back... |
Totals for 0187-05-050 | ||
|---|---|---|---|
| Length: | 5.0 Miles | ||
| Estimate: | $21,999,740 | ||
| Actual: | |||
CCSJ: 0271-05-039 | |||
| District: | Houston | Let Date: | JUL 2013 |
| Highway: | IH 10 | Let Status: | Approved |
| Project ID: | IM 0107(439) | CSJ: | 0271-05-039 |
| Description: | LANDSCAPE | Handling Code: |
|
| Limits From: | AT PIN OAK ROAD | Fund Cat: | 10 |
| Limits To: | . | Estimate: | $191,002 |
| Length: | 0.0 Miles | Actual: | |
|
Back... |
Totals for 0271-05-039 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $191,002 | ||
| Actual: | |||
CCSJ: 0912-34-146 | |||
| District: | Houston | Let Date: | APR 2013 |
| Highway: | CS | Let Status: | Actual |
| Project ID: | STP 2009(806)MM | CSJ: | 0912-34-146 |
| Description: | CONSTRUCT 4 - LANE ROADWAY | Handling Code: |
LC |
| Limits From: | UNIVERSITY BLVD, US 90A | Fund Cat: | 3 |
| Limits To: | CURRENT TERMINUS S OF DITCH-H | Estimate: | $4,364,246 |
| Length: | 0.3 Miles | Actual: | $4,836,269 |
|
Back... |
Totals for 0912-34-146 | ||
| Length: | 0.3 Miles | ||
| Estimate: | $4,364,246 | ||
| Actual: | $4,836,269 | ||
CCSJ: 0912-34-147 | |||
| District: | Houston | Let Date: | MAR 2013 |
| Highway: | VA | Let Status: | Actual |
| Project ID: | CM 2013(712) | CSJ: | 0912-34-147 |
| Description: | WESTPARK TOLLROAD PARK & RIDE | Handling Code: |
TR |
| Limits From: | WESTPARK TOLLWAY AT SH 99 | Fund Cat: | 5 |
| Limits To: | . | Estimate: | $3,130,219 |
| Length: | 0.0 Miles | Actual: | $3,130,219 |
|
Back... |
Totals for 0912-34-147 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $3,130,219 | ||
| Actual: | $3,130,219 | ||
CCSJ: 0912-34-158 | |||
| District: | Houston | Let Date: | JUL 2013 |
| Highway: | CR | Let Status: | Approved |
| Project ID: | BR 2011(988) | CSJ: | 0912-34-158 |
| Description: | REPLACE BRIDGE AND APPROACHES (NBI# 12080AA0962002) | Handling Code: |
|
| Limits From: | FENSKE LANE AT FAIRCHILDS CRK TRIB | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $233,803 |
| Length: | 0.0 Miles | Actual: | |
|
Back... |
Totals for 0912-34-158 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $233,803 | ||
| Actual: | |||
CCSJ: 0912-34-159 | |||
| District: | Houston | Let Date: | AUG 2013 |
| Highway: | CR | Let Status: | Approved |
| Project ID: | BR 2011(853) | CSJ: | 0912-34-159 |
| Description: | REPLACE BRIDGE AND APPROACHES (NBI# 12080AA0905001) | Handling Code: |
|
| Limits From: | WALKER ROAD AT TURKEY CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $279,000 |
| Length: | 0.0 Miles | Actual: | |
|
Back... |
Totals for 0912-34-159 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $279,000 | ||
| Actual: | |||
CCSJ: 0912-34-171 | |||
| District: | Houston | Let Date: | OCT 2012 |
| Highway: | VA | Let Status: | Actual |
| Project ID: | STP 2013(126) | CSJ: | 0912-34-171 |
| Description: | CIPP PIPE LINER AT CROSS CULVERTS | Handling Code: |
|
| Limits From: | VARIOUS LOCATIONS COUNTYWIDE | Fund Cat: | 1 |
| Limits To: | . | Estimate: | $762,380 |
| Length: | 0.0 Miles | Actual: | $591,980 |
|
Back... |
Totals for 0912-34-171 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $762,380 | ||
| Actual: | $591,980 | ||
CCSJ: 0912-34-178 | |||
| District: | Houston | Let Date: | MAY 2013 |
| Highway: | CS | Let Status: | Approved |
| Project ID: | STP 2012(734)MM | CSJ: | 0912-34-178 |
| Description: | WIDEN 2 - LANE ROADWAY TO 4 - LANE BOULEVARD WITH CURB & GUTTER | Handling Code: |
|
| Limits From: | STAFFORDSHIRE ROAD; 5TH ST | Fund Cat: | 3 |
| Limits To: | SCANLIN/LEXINGTON RD | Estimate: | $3,681,745 |
| Length: | 0.6 Miles | Actual: | |
|
List Showing Order Proposal Req Form Bidders List Back... |
Totals for 0912-34-178 | ||
| Length: | 0.6 Miles | ||
| Estimate: | $3,681,745 | ||
| Actual: | |||
CCSJ: 1258-02-033 | |||
| District: | Houston | Let Date: | MAR 2013 |
| Highway: | FM 1093 | Let Status: | Actual |
| Project ID: | STP 2013(461) | CSJ: | 1258-02-033 |
| Description: | BASE REPAIR & OVERLAY | Handling Code: |
|
| Limits From: | BRAZOS RIVER | Fund Cat: | 1 |
| Limits To: | FM 1489 | Estimate: | $633,891 |
| Length: | 2.7 Miles | Actual: | $535,317 |
|
Bid Tabulations Back... |
Totals for 1258-02-033 | ||
| Length: | 2.7 Miles | ||
| Estimate: | $633,891 | ||
| Actual: | $535,317 | ||
CCSJ: 1258-03-042 | |||
| District: | Houston | Let Date: | AUG 2013 |
| Highway: | FM 1093 | Let Status: | Approved |
| Project ID: | CC 1258-3-42 | CSJ: | 1258-03-042 |
| Description: | CONSTRUCT 4 TOLL LANES WITH TWO 2 - LANE FRONTAGE ROADS | Handling Code: |
LC |
| Limits From: | W OF KATY GASTON ROAD | Fund Cat: | 3 |
| Limits To: | SH 99 | Estimate: | $32,000,000 |
| Length: | 4.2 Miles | Actual: | |
|
Back... |
Totals for 1258-03-042 | ||
| Length: | 4.2 Miles | ||
| Estimate: | $32,000,000 | ||
| Actual: | |||
CCSJ: 1258-03-043 | |||
| District: | Houston | Let Date: | AUG 2013 |
| Highway: | FM 1093 | Let Status: | Approved |
| Project ID: | CC 1258-3-43 | CSJ: | 1258-03-043 |
| Description: | 4 TOLL LNS FROM W OF SPRING GREEN TO W OF KATY - GASTON & TWO | Handling Code: |
LC |
| Limits From: | FM 1463/FM 359 | Fund Cat: | 3 |
| Limits To: | W OF KATY GASTON ROAD | Estimate: | $28,000,000 |
| Length: | 2.8 Miles | Actual: | |
|
Back... |
Totals for 1258-03-043 | ||
| Length: | 2.8 Miles | ||
| Estimate: | $28,000,000 | ||
| Actual: | |||
CCSJ: 1415-02-045 | |||
| District: | Houston | Let Date: | JUL 2013 |
| Highway: | FM 1464 | Let Status: | Approved |
| Project ID: | STP 2013(848) | CSJ: | 1415-02-045 |
| Description: | CONSTRUCT 1 DETENTION POND | Handling Code: |
|
| Limits From: | AT PUMPKIN LAKE | Fund Cat: | 1 |
| Limits To: | . | Estimate: | $517,005 |
| Length: | 0.1 Miles | Actual: | |
|
Back... |
Totals for 1415-02-045 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $517,005 | ||
| Actual: | |||
CCSJ: 2105-01-046 | |||
| District: | Houston | Let Date: | JUL 2013 |
| Highway: | FM 2234 | Let Status: | Approved |
| Project ID: | C 2105-1-46 | CSJ: | 2105-01-046 |
| Description: | RECONSTRUCT AND WIDEN FROM 2 LANES TO 4 - LANE DIVIDED RURAL | Handling Code: |
|
| Limits From: | FM 3345 | Fund Cat: | 3 |
| Limits To: | FORT BEND TOLL ROAD | Estimate: | $9,577,047 |
| Length: | 1.5 Miles | Actual: | |
|
Back... |
Totals for 2105-01-046 | ||
| Length: | 1.5 Miles | ||
| Estimate: | $9,577,047 | ||
| Actual: | |||
CCSJ: 2105-01-047 | |||
| District: | Houston | Let Date: | MAY 2013 |
| Highway: | FM 2234 | Let Status: | Approved |
| Project ID: | STP 2013(698)MM | CSJ: | 2105-01-047 |
| Description: | SIGNAL SYSTEM UPGRADE AND RECONFIGURATION | Handling Code: |
|
| Limits From: | US 90A | Fund Cat: | 3 |
| Limits To: | TURTLE CREEK DR | Estimate: | $1,506,548 |
| Length: | 0.3 Miles | Actual: | |
|
List Showing Order Proposal Req Form Project Addenda Bidders List Back... |
Totals for 2105-01-047 | ||
| Length: | 0.3 Miles | ||
| Estimate: | $1,506,548 | ||
| Actual: | |||
CCSJ: 3048-01-014 | |||
| District: | Houston | Let Date: | NOV 2012 |
| Highway: | FM 2977 | Let Status: | Actual |
| Project ID: | STP 2012(712)MM | CSJ: | 3048-01-014 |
| Description: | INSTALL LEFT TURN LANES | Handling Code: |
|
| Limits From: | EB AT FAIRCHILDS LONGPOINT/FM 361, | Fund Cat: | 1 |
| Limits To: | NB AT BRYAN & NB AT KOEBLEN | Estimate: | $1,360,165 |
| Length: | 0.9 Miles | Actual: | $1,473,222 |
|
Back... |
Totals for 3048-01-014 | ||
| Length: | 0.9 Miles | ||
| Estimate: | $1,360,165 | ||
| Actual: | $1,473,222 | ||
CCSJ: 3510-04-047 | |||
| District: | Houston | Let Date: | OCT 2012 |
| Highway: | SH 99 | Let Status: | Actual |
| Project ID: | CC 3510-4-47 | CSJ: | 3510-04-047 |
| Description: | CONSTRUCT OVERPASS AND APPROACHES | Handling Code: |
LC |
| Limits From: | 0.38 MILES S OF HARLEM ROAD | Fund Cat: | 3 |
| Limits To: | 0.44 MILES N OF HARLEM ROAD | Estimate: | $12,731,338 |
| Length: | 0.8 Miles | Actual: | $10,475,279 |
| District: | Houston | Let Date: | OCT 2012 |
| Highway: | SH 99 | Let Status: | Actual |
| Project ID: | CC 3510-4-48 | CSJ: | 3510-04-048 |
| Description: | CONSTRUCT OVERPASS AND APPROACHES (SEGMENT D TOLL) | Handling Code: |
LC |
| Limits From: | 0.27 MILES SOUTH OF W BELLFORT RD | Fund Cat: | 3 |
| Limits To: | 0.51 MILES NORTH OF W BELLFORT RD | Estimate: | $10,722,990 |
| Length: | 0.8 Miles | Actual: | $6,736,511 |
| District: | Houston | Let Date: | OCT 2012 |
| Highway: | SH 99 | Let Status: | Actual |
| Project ID: | CC 3510-4-52 | CSJ: | 3510-04-052 |
| Description: | CONSTRUCT OVERPASS AND APPROACHES | Handling Code: |
LC |
| Limits From: | 0.48 MILES SOUTH OF MASON RD | Fund Cat: | 3 |
| Limits To: | 0.30 MILES NORTH OF MASON RD | Estimate: | $10,722,000 |
| Length: | 0.8 Miles | Actual: | $8,766,219 |
|
Back... |
Totals for 3510-04-047 | ||
| Length: | 2.4 Miles | ||
| Estimate: | $34,176,328 | ||
| Actual: | $25,978,009 | ||
|