Three districts in the West Region currently have State Infrastructure Bank (SIB) loans.

SIB loan interest rates are based on credit of the borrower, years borrowed and the Municipal Market Index at the time of SIB application.

Abilene District
Borrower County Project Minute Order & Date Interest Rate % Loan Length Project Estimate SIB Loan
Stamford Jones County Utility relocation along FM 1226 111788
04/30/2009
4.00 10 years $2.876 million $300 thousand

 

Amarillo District
Borrower County Project Minute Order & Date Interest Rate % Loan Length Project Estimate SIB Loan
Stratford Sherman County Utility relocations for realignment of SH 15
114040
08/28/2014
1.95 5 years $150 thousand
$125 thousand

 

El Paso District
Borrower County Project Minute Order & Date Interest Rate % Loan Length Project Estimate SIB Loan
Camino Real RMA* El Paso County Direct connectors at FM 659 (Zaragoza) and Loop 375
112668
04/28/2011
4.95 30 years $32 million $20 million
Camino Real RMA*
El Paso County
Loop 375 northeast mainlane extension project
112667
04/28/2011
4.05 20 years $53 million $6 million
Camino Real RMA*
El Paso County
Direct connectors at I-10 and
Loop 375
112295
06/08/2010
4.95 30 years $156 million $30 million

*Regional Mobility Authority