Monthly State Let Maintenance Report For Maintenance Division As Of Nov 20, 2014 Page 1 Of 1

Last Update: Thursday, November 20, 2014
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway 0000000
From 3712 JACKSON AVE AUSTIN TX 78731
To 3712 JACKSON AVE AUSTIN TX 78731
CSJ 4704-01-226
Proj ID CBC - 470401226
Work Type RENOVATION OR REPAIRS
 
0.001 407980.00 0.00 507802.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-30-13
Work Began 09-15-13
Work Completed 04-30-14
Time Computed 09-15-13
Contract Working Days 140
Addl Days Granted 60
Working Days Charged 197
Percent Time Used 98
Contractor(s)
HOT ROD MECHANICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-226
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07134032
Totals 407980.00 0.00 507802.35 100.0

CountyWILLIAMSON
Highway 0000000
From 9500 LAKE CREEK PARKWAY AUSTIN TX
To WILLIAMSON COUNTY
CSJ 4704-01-345
Proj ID CBC - 470401345
Work Type RENOVATION OR REPAIR
 
0.001 401323.00 0.00 116123.97 30.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-23-14
Work Began 00-00-00
Work Completed  
Time Computed 08-08-14
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 22
Contractor(s)
HOT ROD MECHANICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-345
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144214
Totals 401323.00 0.00 116123.97 30.4

CountyGILLESPIE
Highway US0290
From GILLESPIE, MEDINA, GUADALUPE AND
To COLORARO CO REST AREAS
CSJ 6114-25-001
Proj ID SUP - 611425001
Work Type TOTAL REST AREA OPS AND MNT
 
0.010 2997984.00 0.00 10019311.79 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-07
Work Began 05-01-07
Work Completed  
Time Computed 05-01-07
Contract Working Days 731
Addl Days Granted 1
Working Days Charged 2,191
Percent Time Used 299
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6114-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04074032
Totals 2997984.00 0.00 10019311.79 99.9

CountyKERR
Highway IH0010
From KERR COUNTY IH10 EB AND IH10 WB
To MEDINA COUNTY US 90
CSJ 6116-27-001
Proj ID SUP - 611627001
Work Type REST AREA MAINTENANCE AND REPAIR
 
0.001 1171200.00 0.00 4062344.92 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-07
Work Began 05-01-07
Work Completed  
Time Computed 05-01-07
Contract Working Days 731
Addl Days Granted 1
Working Days Charged 2,192
Percent Time Used 299
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6116-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04074030
Totals 1171200.00 0.00 4062344.92 99.9

CountyWICHITA
Highway US0287
From WICHITA CO US0287 NB
To WICHITA CO US0287 SB
CSJ 6123-71-001
Proj ID SUP - 612371001
Work Type REST AREA MAINTENANCE AND REPAIR
 
0.001 528000.00 25092.74 2145879.34 99.9
Work Order 05-01-07
Work Began 05-01-07
Work Completed  
Time Computed 05-01-07
Contract Working Days 731
Addl Days Granted 1,552
Working Days Charged 2,741
Percent Time Used 120
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6123-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04074031
Totals 528000.00 25092.74 2145879.34 99.9

CountyTRAVIS
Highway IH0035
From MAIN OFFICE, BULL CREEK, RIVERSIDE,
To CEDAR PARK, PRINT SHOP, ETC.
CSJ 6135-67-001
Proj ID SUP - 613567001
Work Type AIR CONDITIONER FILTER REPLACEMENT
 
0.001 444983.40 0.00 321376.90 72.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-21-05
Work Began 08-15-05
Work Completed  
Time Computed 08-15-05
Contract Working Days 777
Addl Days Granted 0
Working Days Charged 777
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
PCSI, INC
SUBCONTRACTOR(S) FOR CCSJ: 6135-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08054999
Totals 444983.40 0.00 321376.90 72.2

CountyTRAVIS
Highway IH0035
From MAIN OFFICE, BULL CREEK, RIVERSIDE,
To CEDAR PARK, PRINT SHOP, ETC.
CSJ 6201-68-001
Proj ID SUP - 620168001
Work Type AIR CONDITIONING FILTER REPLACEMENT
 
0.001 502250.40 15975.07 856886.48 99.9
Work Order 10-01-09
Work Began 10-01-09
Work Completed  
Time Computed 10-01-09
Contract Working Days 1,096
Addl Days Granted 1,094
Working Days Charged 1,826
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
PCSI, INC
SUBCONTRACTOR(S) FOR CCSJ: 6201-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08094999
Totals 502250.40 15975.07 856886.48 99.9

CountyBELL
Highway IH0035
From NB IH 35 BELL COUNTY
To SB IH 35 BELL COUNTY
CSJ 6202-33-001
Proj ID SUP - 620233001
Work Type REST AREA TOTAL MAINTENANCE BELL CO IH35
 
1.000 768750.00 0.00 1955502.16 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-09
Work Began 09-15-09
Work Completed  
Time Computed 09-15-09
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 1,324
Percent Time Used 181
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6202-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09094011
Totals 768750.00 0.00 1955502.16 99.9

CountyNOLAN
Highway IH0020
From VARIOUS COUNTIES WITHIN THE
To NORTH TEXAS REGION
CSJ 6221-71-001
Proj ID RMC - 622171001
Work Type TOTAL REST AREA MAINTENANCE
 
0.010 3889872.00 154793.97 7008466.18 99.9
Work Order 04-18-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 731
Working Days Charged 1,280
Percent Time Used 87
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114017
Totals 3889872.00 154793.97 7008466.18 99.9

CountyCOMAL
Highway IH0035
From VARIOUS COUNTIES WITHIN THE
To SOUTHERN REGION
CSJ 6221-72-001
Proj ID RMC - 622172001
Work Type TOTAL REST AREA MAINTENANCE
 
0.010 2775840.00 0.00 2637799.36 95.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-18-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 1
Working Days Charged 731
Percent Time Used 100
Contractor(s)
APECK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114018
Totals 2775840.00 0.00 2637799.36 95.0

CountyFRANKLIN
Highway IH0030
From VARIOUS COUNTIES WITHIN THE
To EASTERN REGION
CSJ 6221-73-001
Proj ID RMC - 622173001
Work Type TOTAL REST AREA MAINTENANCE
 
0.010 3785300.00 172787.65 7287933.90 99.9
Work Order 04-18-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 731
Working Days Charged 1,280
Percent Time Used 87
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6221-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114037
Totals 3785300.00 172787.65 7287933.90 99.9

CountyEL PASO
Highway IH0010
From VARIOUS COUNTIES WITHIN THE
To WESTERN TEXAS REGION
CSJ 6221-74-001
Proj ID RMC - 622174001
Work Type TOTAL REST AREA MAINTENANCE
 
0.010 3328800.00 0.00 3574411.39 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-18-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 93
Working Days Charged 823
Percent Time Used 100
Contractor(s)
APECK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114038
Totals 3328800.00 0.00 3574411.39 99.9

CountyCROSBY
Highway US0082
From VARIOUS COUNTIES WITHIN THE
To NORTHWESTERN TEXAS REGION
CSJ 6221-75-001
Proj ID RMC - 622175001
Work Type TOTAL REST AREA MAINTENANCE
 
0.010 3737760.00 186007.38 6979397.69 99.9
Work Order 04-18-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 730
Working Days Charged 1,280
Percent Time Used 87
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114019
Totals 3737760.00 186007.38 6979397.69 99.9

CountyNAVARRO
Highway IH0045
From NAVARRO COUNTY
To NAVARRO COUNTY
CSJ 6227-15-001
Proj ID SUP - 622715001
Work Type TOTAL REST AREA OPS, MNT, RPRS
 
1.000 42000.00 0.00 84000.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 200
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6227-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04114039
Totals 42000.00 0.00 84000.00 99.9

CountyNAVARRO
Highway IH0045
From IH0045 NB, SUP 15
To IH0045 SB, SUP 16
CSJ 6232-35-001
Proj ID SUP - 623235001
Work Type TOTAL RA MNT, OPS, RPR 24 / 7
 
0.010 1008000.00 0.00 797473.70 79.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-11
Work Began 08-01-11
Work Completed  
Time Computed 08-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 639
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6232-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08114029
Totals 1008000.00 0.00 797473.70 79.1

CountyGILLESPIE
Highway US0290
From US 290, IH 35, US 77, US 281
To IH 45
CSJ 6258-24-001
Proj ID SUP - 625824001
Work Type TOTAL REST AREA OPS MNT & REPAIR
 
0.010 7789411.36 370158.48 5759634.23 73.9
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 549
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134031
Totals 7789411.36 370158.48 5759634.23 73.9

CountyBEXAR
Highway IH0010
From KERR CO,MEDINA LIVE OAK
To COKE, CONCHO COUNTIES
CSJ 6258-25-001
Proj ID SUP - 625825001
Work Type REST AREA TOTAL; OPS. MNT, & RPR
 
0.010 2602160.16 110526.11 1996968.06 76.7
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 549
Percent Time Used 75
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6258-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134030
Totals 2602160.16 110526.11 1996968.06 76.7

CountyEL PASO
Highway IH0010
From VARIOUS COUNTIES WITHIN THE
To WESTERN TEXAS REGION
CSJ 6258-50-001
Proj ID RMC - 625850001
Work Type TOTAL REST AREA MAINTENANCE
 
0.001 7060800.00 21850.00 2226808.40 31.5
Work Order 08-01-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 1,460
Addl Days Granted 0
Working Days Charged 457
Percent Time Used 31
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06134018
Totals 7060800.00 21850.00 2226808.40 31.5

page 1