Detail Letting Schedule for San Jacinto County (FY 2018)
San Jacinto County (FY 2018) |
CCSJ: 0177-02-102 |
|||
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | US 59 | Let Status: | Tentative |
Project ID: | ER 1802(591) | CSJ: | 0177-02-102 |
Description: | REPAIR PAVING EROSION, REPLACE DAMAGED MBGF AND REBUILD BACK | Handling Code: | XX |
Limits From: | 2.885 MILES N OF FM 1127 | Fund Cat: | 10 |
Limits To: | 2.766 MILES S OF FM 2665 N | ESTIMATE: | $624,386 |
Length: | 2.0 | Actual | $0 |
Back... | Totals for 0177-02-102 | ||
---|---|---|---|
Length: | 2 | ||
Estimate: | $624,386 | ||
Actual: | |||
CCSJ: 0403-01-049 |
|||
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | SH 156 | Let Status: | Tentative |
Project ID: | ER ( ) | CSJ: | 0403-01-049 |
Description: | RE-ESTABLISH THE SLOPE AND RESET GUARDRAIL. CONCRETE RIRAP W | Handling Code: | XX |
Limits From: | 3.953 MILES N OF FM 946 INTERSECTIO | Fund Cat: | 10 |
Limits To: | 5.058 MILES S OF US 190 INTERSETION | ESTIMATE: | $53,076 |
Length: | 2.0 | Actual | $0 |
Back... | Totals for 0403-01-049 | ||
Length: | 2 | ||
Estimate: | $53,076 | ||
Actual: | |||
CCSJ: 0403-02-019 |
|||
District: | LUFKIN | Let Date: | Jul 2018 |
Highway: | FM 224 | Let Status: | Actual |
Project ID: | STP 1802(329)HES | CSJ: | 0403-02-019 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS | Handling Code: | |
Limits From: | SH 156 (N) | Fund Cat: | 8 |
Limits To: | SH 156 (S) | ESTIMATE: | $210,309 |
Length: | 7.7 | Actual | $233,735 |
District: | LUFKIN | Let Date: | Jul 2018 |
Highway: | FM 945 | Let Status: | Actual |
Project ID: | STP 1802(330)HES | CSJ: | 2594-01-014 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS | Handling Code: | |
Limits From: | SH 156 | Fund Cat: | 8 |
Limits To: | SH 150 | ESTIMATE: | $310,245 |
Length: | 8.9 | Actual | $282,493 |
Proposal Request Bid List List Showing Order Addenda Bid Tabulations Award Status Back... | Totals for 0403-02-019 | ||
Length: | 16.6 | ||
Estimate: | $520,554 | ||
Actual: | $516,228 | ||
CCSJ: 0756-04-013 |
|||
District: | LUFKIN | Let Date: | Aug 2018 |
Highway: | FM 2693 | Let Status: | Actual |
Project ID: | ER 2018(717) | CSJ: | 0756-04-013 |
Description: | REMOVE AND RESET SEPARATED BOX CULVERT. REPOUR NEW WINGWALL | Handling Code: | LC |
Limits From: | 0.271 MI N OF SH 150_INTERSECTION | Fund Cat: | 10 |
Limits To: | WALKER COUNTY LINE | ESTIMATE: | $25,419 |
Length: | 2.0 | Actual | $25,419 |
Back... | Totals for 0756-04-013 | ||
Length: | 2 | ||
Estimate: | $25,419 | ||
Actual: | $25,419 | ||
CCSJ: 2668-01-010 |
|||
District: | LUFKIN | Let Date: | Apr 2018 |
Highway: | FM 2666 | Let Status: | Actual |
Project ID: | ER 2018(714) | CSJ: | 2668-01-010 |
Description: | EMERGENCY ROADWAY REPAIRS | Handling Code: | XX |
Limits From: | 1.93 MI E OF INTERSECTION FM 2025 | Fund Cat: | 10 |
Limits To: | 5.362 MI SW OF SH 150 INTERSECTION | ESTIMATE: | $8,408 |
Length: | 2.0 | Actual | $8,408 |
Back... | Totals for 2668-01-010 | ||
Length: | 2 | ||
Estimate: | $8,408 | ||
Actual: | $8,408 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |