Detail Letting Schedule for Hartley County (FY 2018)

Last Update: Monday, August 27, 2018
Hartley County (FY 2018)

CCSJ: 1108-01-020

District:AMARILLOLet Date:Jan 2018
Highway:FM 767Let Status:Actual
Project ID:BR 2018(436)CSJ:1108-01-020
Description:REPLACE EXISTING BRIDGEHandling
Code:
 
Limits From:AT PUNTA DE AGUA CREEKFund Cat:6
Limits To:.ESTIMATE:$5,241,495
Length:0.5Actual$4,253,525
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 1108-01-020
Length:0.5
Estimate:$5,241,495
Actual:$4,253,525