Letting Schedule for May, 2017 County (FY 2017)
May, 2017 (FY 2017) | (see Links) |
SEP 2016 | OCT 2016 | NOV 2016 | DEC 2016 | JAN 2017 | FEB 2017 | MAR 2017 | APR 2017 | MAY 2017 | JUN 2017 | JUL 2017 | AUG 2017 | | ||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description |
---|---|---|---|---|---|---|
0991-04-011 | Bee/ Corpus Christi | FM 882 | Actual | $748,175 | 1 | REPLACE BRIDGE AND APPROACHES |
1890-01-048 | Bexar/ San Antonio | FM 1976 | Actual | $516,102 | 1 | IMPROVE TRAFFIC SIGNALS & SAFETY LIGHTING AT INTERSECTION |
2452-02-115 | Bexar/ San Antonio | SL 1604 | Actual | $16,265,624 | 1 | OVERLAY & PAVEMENT MARKINGS ON FRONTAGE ROADS & MAINLANES |
0521-04-278 | Bexar/ San Antonio | IH 410 | Actual | $5,016,840 | 1 | OVERLAY & PAVEMENT MARKINGS ON EB FRONTAGE ROAD |
0025-02-212 | Bexar/ San Antonio | IH 10 | Actual | $1,566,043 | 6 | CLEAN AND PAINT STEEL TRUSS, BRIDGE REPAIR, MILL, OVERLAY AN |
0024-08-136 | Bexar/ San Antonio | US 90 | Actual | $1,773,505 | 1 | UPGRADE FROM CONTINUOUS ILLUMINATION TO HIGH MAST |
0073-08-190 | Bexar/ San Antonio | IH 37 | Actual | $501,500 | 10 | LANDSCAPE DEVELOPMENT |
0072-07-041 | Bexar/ San Antonio | IH 10 | Actual | $66,315,206 | 1 | EXPAND FROM 4 TO 8 LANE EXPRESSWAY-2 NEW GENERAL PURPOSE & 2 |
0217-01-034 | Bowie/ Atlanta | US 59 | Actual | $2,022,920 | 1 | RESURFACE EXISTING 4-LANE HIGHWAY |
1090-05-015 | Calhoun/ Yoakum | FM 1593 | Actual | $948,670 | 1 | WIDEN ROADWAY TO ACCOMMODATE TURN LANES, SIGNAL IMPROVEMNETS |
0684-01-067 | Cameron/ Pharr | SH 550 | Actual | $6,050,529 | 3 | CONSTRUCT CONTROLLED ACCESS TOLL FACILITY |
0921-06-284 | Cameron/ Pharr | CS | Actual | $160,736 | 3 | BICYCLE LANE MARKING |
3259-01-042 | Childress/ Childress | FM 401 | Actual | $482,547 | 1 | MISCELLANEOUS WORK |
0391-02-018 | Clay/ Wichita Falls | FM 810 | Actual | $2,010,845 | 1 | EXTEND CULVERTS |
0027-01-040 | Colorado/ Yoakum | US 90 | Actual | $6,163,371 | 6 | CONSTRUCT ONE WAY BRIDGE AND APPROACHES (WESTBOUND) |
0253-03-067 | Comal/ San Antonio | US 281 | Actual | $2,774,469 | 6 | REHAB, BRIDGE DECK AND RAIL REPLACEMENT, CLEAN AND PAINT |
0070-03-057 | Concho/ San Angelo | US 87 | Actual | $1,403,939 | 8 | SAFETY TREATED FIXED OBJECTS |
0183-04-049 | Coryell/ Waco | SH 36 | Actual | $15,072,798 | 1 | ADD PASSING LANES AND WIDEN SHOULDERS |
0442-02-160 | Dallas/ Dallas | IH 35E | Actual | $607,709 | 1 | INSTALL GUIDE SIGNS |
0261-02-074 | Dallas/ Dallas | US 67 | Actual | $60,844,407 | 1 | WIDEN FREEWAY FROM FOUR TO SIX LANES |
0092-07-059 | Dallas/ Dallas | SH 356 | Actual | $306,488 | 3 | LANDSCAPE MEDIAN ENHANCEMENTS - TREE PLANTING |
1047-03-072 | Dallas/ Dallas | FM 1382 | Actual | $1,864,939 | 1 | RETAINING WALL AND BRIDGE ABUTMENT REPAIRS |
1255-02-007 | Dawson/ Lubbock | FM 2051 | Actual | $758,797 | 1 | MISCELLANEOUS CONSTRUCTION |
0127-01-030 | Eastland/ Brownwood | US 183 | Actual | $4,150,584 | 1 | ADD PASSING LANES |
0002-01-055 | El Paso/ El Paso | SH 20 | Actual | $8,862,053 | 11 | RECONSTRUCITON OF ROADWAY, INTERSECTION IMPROVEMENTS & REHAB |
0924-00-082 | El Paso/ El Paso | VA | Actual | $1,143,839 | 1 | FY 2017 STRIPING PROJECTS |
0500-01-150 | Galveston/ Houston | IH 45 | Actual | $4,349,270 | 1 | BASE REPAIR, MILLING, SEAL COAT, & TOM OVERLAY |
0901-19-190 | Grayson/ Paris | CR | Actual | $240,636 | 8 | INSTALL RAILROAD LIGHTS AND GATES |
0338-01-052 | Grimes/ Bryan | SH 105 | Actual | $7,706,155 | 1 | SAFETY IMPROVEMENT WORK CONSISTING OF GRADING, STRUCTURES, |
0042-09-126 | Hall/ Childress | US 287 | Actual | $1,522,486 | 1 | MILL & INLAY |
0258-03-042 | Hamilton/ Waco | SH 6 | Actual | $268,816 | 1 | INSTALL CONTINUOUS TURN LANE |
0813-03-043 | Hardin/ Beaumont | FM 421 | Actual | $1,486,171 | 8 | SAFETY TREAT FIXED OBJECTS, HIGH FRICTION_SURFACE TREATMENT |
3256-01-105 | Harris/ Houston | SL 8 | Actual | $3,177,561 | 1 | FULL DEPTH REPAIR, PLANING CONCRETE PAVEMENT,SEAL COAT, THIN |
8170-12-001 | Harris/ Houston | MH | Actual | $59,229,494 | 2M | CONSTR 6-LN DIVIDED (RAISED MEDIAN) URBAN ST FACILITY -PHASE |
0063-01-088 | Harrison/ Atlanta | US 59 | Actual | $6,633,457 | 1 | RESURFACE EXISTING 4-LANE HIGHWAY |
0914-33-072 | Hays/ Austin | CR | Actual | $1,159,468 | 6 | BRIDGE REPLACEMENT |
0108-04-037 | Henderson/ Tyler | SH 19 | Actual | $5,699,689 | 1 | ADD 10' SHOULDERS & RESURFACE ROADWAY |
0039-18-009 | Hidalgo/ Pharr | IH 2 | Actual | $339,950 | 6 | REPLACE BEARING PADS, JOINT SEALS & INSTALL VEHICLE |
1513-01-019 | Hood/ Ft Worth | FM 167 | Actual | $2,732,529 | 8 | SAFETY TREAT FIXED OBJECTS AND CONSTRUCT PAVED SHOULDERS |
1419-01-009 | Jasper/ Beaumont | FM 1408 | Actual | $1,978,478 | 6 | REPLACE BRIDGE AND APPROACHES |
0920-00-119 | Jefferson/ Beaumont | VA | Actual | $511,298 | 10 | INSTALL LANDSCAPING |
0086-11-048 | Jim Wells/ Corpus Christi | SH 44 | Actual | $607,464 | 8 | IMPROVE TRAFFIC SIGNALS |
0033-03-029 | Jones/ Abilene | US 83 | Actual | $4,828,063 | 1 | CEMENT TRT BASE, 1-COURSE SURFACE TREATMENT, MILL EXISTING |
2512-02-010 | Kaufman/ Dallas | FM 2728 | Actual | $4,373,443 | 1 | PROVIDE ADDITIONAL PAVEMENT SURFACE AND OVERLAY |
0335-03-042 | Leon/ Bryan | SH 7 | Actual | $2,009,281 | 6 | REPLACEMENT OF AN EXISTING BRIDGE FACILITY CONSISTING OF |
1188-02-084 | Midland/ Odessa | SL 250 | Actual | $17,691,765 | 11 | CONSTRUCT OVERPASS, MAINLANES AND RAMPS |
0013-05-060 | Montague/ Wichita Falls | US 81 | Actual | $1,403,614 | 1 | SAFETY LIGHTING, IMPROVE HORIZONTAL ALIGNMENT |
0044-04-060 | Montague/ Wichita Falls | US 82 | Actual | $270,358 | 11 | TRAFFIC SIGNAL |
1352-02-021 | Montague/ Wichita Falls | FM 455 | Actual | $586,387 | 8 | IMPROVE HORIZONTAL ALIGNMENT |
0553-03-033 | Nacogdoches/ Lufkin | SH 7 | Actual | $39,710 | 8 | INSTALL INTERSECTION FLASHING BEACON, SAFETY LIGHTING AT |
0617-01-170 | Nueces/ Corpus Christi | SH 358 | Actual | $39,434,470 | 1 | RAMP REVERSAL PHASE II-A SOUTH SIDE ONLY |
0373-01-103 | Nueces/ Corpus Christi | IH 69E | Actual | $6,316,182 | 11 | RAMP REVERSAL |
0916-00-083 | Nueces/ Corpus Christi | VA | Actual | $1,478,900 | 1 | DISTRICT WIDE PAVEMENT MARKINGS AND MARKERS-PLANNING CSJ |
0028-11-203 | Orange/ Beaumont | IH 10 | Actual | $3,045,742 | 1 | REHABILITATE EXISTING ROADWAY |
2288-01-013 | Palo Pinto/ Ft Worth | FM 1821 | Actual | $1,493,206 | 1 | BASE REPAIR AND HMAC OVERLAY |
0314-07-054 | Parker/ Ft Worth | IH 20 | Actual | $2,343,995 | 1 | MILL AND OVERLAY |
0902-38-124 | Parker/ Ft Worth | VA | Actual | $959,997 | 3 | CONSTRUCT 5 FT WIDE CONCRETE SIDEWALK ALONG WEST SIDE OF |
0075-02-027 | Pecos/ Odessa | US 67 | Actual | $4,584,655 | 8 | MILLED EDGELINE RUMBLE STRIPS, MILLED CENTERLINE RUMBLE |
0076-01-028 | Pecos/ Odessa | US 67 | Actual | $5,425,325 | 8 | SAFETY TREAT FIXED OBJECTS |
2510-01-016 | Polk/ Lufkin | FM 1316 | Actual | $688,268 | 8 | SAFETY TREAT FIXED OBJECTS |
0168-10-073 | Potter/ Amarillo | IH 27 | Actual | $7,866,464 | 6 | WIDEN BRIDGE, REPAIR BRIDGE AND APPROACHES |
0049-07-063 | Robertson/ Bryan | US 79 | Actual | $2,458,689 | 8 | SAFETY WORK CONSISTING OF MILLED EDGELINE AND CENTERLINE |
0009-12-212 | Rockwall/ Dallas | IH 30 | Actual | $2,931,419 | 1 | FULL DEPTH CONCRETE PAVEMENT REPAIR OF MAINLANES AND |
0059-05-044 | Shelby/ Lufkin | SH 7 | Actual | $1,458,486 | 8 | TEXTURIZE SHOULDERS (MILLED EDGELINE RUMBLE STRIPS; MILLED |
0911-39-050 | Shelby/ Lufkin | CR | Actual | $661,430 | 6 | REPLACE BRIDGE AND APPROACHES |
0165-01-102 | Smith/ Tyler | US 271 | Actual | $2,058,572 | 1 | PLANE & RESURFACE ROADWAY |
0067-02-068 | Swisher/ Lubbock | IH 27 | Actual | $10,819,330 | 6 | BRIDGE MAINTENANCE |
0248-01-077 | Titus/ Atlanta | US 271 | Actual | $14,887,891 | 1 | CONSTRUCT GRADE SEPARATION AND APPROACHES ON 4-LANE HIGHWAY |
0069-07-105 | Tom Green/ San Angelo | US 87 | Actual | $6,956,900 | 1 | ACP OVERLAY |
0113-08-077 | Travis/ Austin | US 290 | Actual | $1,845,787 | 1 | ADD CONT. TURN LN&PAVED SHLDRS(5FT) |
0212-02-039 | Walker/ Bryan | US 190 | Actual | $1,119,822 | 1 | OVERLAY CONSISTING OF PLANING, HMA, PAVEMENT MARKINGS AND |
0944-02-010 | Waller/ Houston | FM 362 | Actual | $653,737 | 1 | 1.5 IN ACP OVERLAY |
0004-03-049 | Ward/ Odessa | BI 20-D | Actual | $448,712 | 8 | TRAFFIC SIGNALS |
0186-05-040 | Washington/ Bryan | SH 36 | Actual | $1,376,537 | 6 | REPLACE EXISTING BRIDGE CONSISTING OF GRADING, STRUCTURES |
2150-03-025 | Webb/ Laredo | FM 1472 | Actual | $3,259,551 | 1 | FOR THE CONSTRUCTION AND REHABILITATION OF AN EXISTING |
0913-09-056 | Wharton/ Yoakum | CR | Actual | $627,438 | 6 | REPLACE BRIDGE AND APPROACHES |
0903-03-112 | Wichita/ Wichita Falls | VA | Actual | $1,482,354 | 3 | CONSTRUCT HIKE & BIKE TRAIL |
0903-03-113 | Wichita/ Wichita Falls | CS | Actual | $247,977 | 8 | 2017 FEDERAL SIGNAL PROGRAM |
0903-00-083 | Wichita/ Wichita Falls | VA | Actual | $938,295 | 10 | INSTALLATION OF ITS CAMERAS & DYNAMIC MESSAGE SIGNS ON US 82 |
0204-03-043 | Williamson/ Austin | US 79 | Actual | $1,157,694 | 1 | MILL,SEAL & OVERLAY |
0013-06-045 | Wise/ Ft Worth | US 81 | Actual | $1,253,628 | 1 | SAFETY LIGHTING, IMPROVE HORIZONTAL ALIGNMENT |
|