Detail Letting Schedule for Crane County (FY 2017)
Last Update: Monday, September 25, 2017
CCSJ: 0229-03-035
|
District: | ODESSA | Let Date: | May 2018 |
Highway: | US 385 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 0229-03-035 |
Description: | WIDENING TO AN ULTIMATE 4-LANE DIVIDED HIGHWAY | Handling Code: | |
Limits From: | CASTLE GAP ROAD | Fund Cat: | 11 |
Limits To: | UPTON COUNTY LINE | ESTIMATE: | $30,000,000 |
Length: | 6.5 | Actual | $0 |
|
Back...
| Totals for 0229-03-035 |
Length: | 6.5 |
Estimate: | $30,000,000 |
Actual: | |
Handling Code | Definition |
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |