Detail Letting Schedule for Panola County (FY 2017)

Last Update: Monday, October 16, 2017
Panola County (FY 2017)

CCSJ: 0063-03-060

District:ATLANTALet Date:Jan 2017
Highway:US 59Let Status:Actual
Project ID:STP 2017(505)HESCSJ:0063-03-060
Description:IMPROVE TRAFFIC SIGNAL & SAFETY LIGHTINGHandling
Code:
 
Limits From:AT US 79 INTERSECTIONFund Cat:8
Limits To:.ESTIMATE:$155,645
Length:0.0Actual$145,519
 
District:ATLANTALet Date:Jan 2017
Highway:US 79Let Status:Actual
Project ID:STP 2017(506)HESCSJ:0063-11-057
Description:IMPROVE TRAFFIC SIGNAL & SAFETY LIGHTINGHandling
Code:
 
Limits From:AT SH 149 INTERSECTIONFund Cat:8
Limits To:.ESTIMATE:$186,715
Length:0.0Actual$173,967
 
District:ATLANTALet Date:Jan 2017
Highway:US 80Let Status:Actual
Project ID:STP 2017(507)HESCSJ:0096-09-075
Description:IMPROVE TRAFFIC SIGNAL, INSTALL ADVANCE WARNING SIGNS,Handling
Code:
 
Limits From:AT FRANKLIN INTERSECTIONFund Cat:8
Limits To:.ESTIMATE:$151,845
Length:0.0Actual$204,949
 
Bid Tabulations
Back...
Totals for 0063-03-060
Length:0
Estimate:$494,205
Actual:$524,436

CCSJ: 0246-02-049

District:ATLANTALet Date:Mar 2017
Highway:BU 79-GLet Status:Actual
Project ID:STP 2017(884)CSJ:0246-02-049
Description:RESURFACE EXISTING 2-LANE HIGHWAYHandling
Code:
 
Limits From:BU 59-D IN CARTHAGEFund Cat:1
Limits To:0.3 MI E. OF US 79ESTIMATE:$630,153
Length:1.7Actual$582,438
 
District:ATLANTALet Date:Mar 2017
Highway:BU 79-GLet Status:Actual
Project ID:STP 2017(884)CSJ:0247-01-055
Description:RESURFACE EXISTING 2-LANE HIGHWAYHandling
Code:
 
Limits From:BU 59-D IN CARTHAGEFund Cat:1
Limits To:US 79ESTIMATE:$321,074
Length:1.0Actual$294,422
 
Proposal Request
List Showing Order
Bid Tabulations
Bid List
Award Status
Back...
Totals for 0246-02-049
Length:2.7
Estimate:$951,227
Actual:$876,859

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract