Detail Letting Schedule for McMullen County (FY 2016)

Last Update: Tuesday, December 6, 2016
McMullen County (FY 2016)

CCSJ: 0483-03-033

District: San Antonio Let Date: DEC 2015
Highway: SH 72 Let Status: Actual
Project ID: STP 2015(728)HES CSJ: 0483-03-032
Description: TEXTURIZE SHOULDERS AND CENTELINE Handling
Code:
 
Limits From: FM 99 Fund Cat: 8
Limits To: LIVE OAK COUNTY LINE Estimate: $131,101
Length: 6.6 Miles Actual: $104,738
 
District: San Antonio Let Date: DEC 2015
Highway: SH 72 Let Status: Actual
Project ID: STP 1502(273) CSJ: 0483-03-033
Description: REHAB OF EXISTING ROADWAY Handling
Code:
 
Limits From: 1.5 MI EAST OF SH 16 Fund Cat: 1
Limits To: LIVE OAK COUNTY LINE Estimate: $12,955,234
Length: 12.2 Miles Actual: $11,844,943
 
Back...

Totals for 0483-03-033
Length: 18.8 Miles
Estimate: $13,086,335
Actual: $11,949,681

CCSJ: 0915-51-011

District: San Antonio Let Date: JAN 2016
Highway: VA Let Status: Actual
Project ID: C 915-51-11 CSJ: 0915-51-011
Description: CONSTRUCT 12 NEW GRAVEL PARKING LOTS AND DRIVEWAYS Handling
Code:
 
Limits From: JAMES E DAUGHTEY WMA Fund Cat: 10
Limits To: . Estimate: $251,264
Length: 0.0 Miles Actual: $454,942
 
Back...

Totals for 0915-51-011
Length: 0.0 Miles
Estimate: $251,264
Actual: $454,942


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract