Letting Schedule for Amarillo District (FY 2016)
Amarillo District (FY 2016) |
Deaf Smith | Hansford | Hartley | Hemphill | Lipscomb | Moore | Ochiltree | Potter | Randall | Roberts | Sherman | ||||||
Deaf Smith County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0226-04-025 | US 385 | Actual | FEB 2016 | $8,318,208 | 1 | OVERLAY |
Hansford County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0308-02-029 | SH 15 | Actual | MAY 2016 | $9,135,716 | 1 | MINOR REPAIRS AND OVERLAY |
Hartley County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0041-02-014 | US 385 | Actual | JAN 2016 | $6,104,316 | 8 | OVERLAY |
Hemphill County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
2612-01-011 | RM 2654 | Actual | JUL 2016 | $5,653,752 | 8 | SAFETY WIDENING OF ROADWAY |
Lipscomb County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0355-01-048 | SH 15 | Actual | JUN 2016 | $8,150,620 | 1 | OVERLAY |
Moore County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0557-01-028 | SH 152 | Actual | FEB 2016 | $15,561,611 | 1 | OVERLAY |
Ochiltree County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0030-01-032 | US 83 | Actual | DEC 2015 | $7,967,740 | 1 | SEALCOAT |
Potter County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0168-10-069 | US 60 | Actual | MAY 2016 | $2,147,565 | 3 | CONSTRUCT PED. IMPROVEMENTS, REHAB STREETSCAPE IN ROW PED |
0275-01-177 | IH 40 | Actual | JUN 2016 | $36,259,778 | 1 | REHAB, CONCRETE PAV, RAMP IMPROVEMENTS, AND MISC CONSTRUCTION |
0904-00-157 | VA | Actual | SEP 2015 | $490,788 | 1 | CRACK SEAL |
0904-00-159 | VA | Actual | FEB 2016 | $1,028,989 | 1 | THERMOPLASTIC STRIPING |
0904-00-161 | VA | Actual | OCT 2015 | $1,946,236 | 10 | CONSTRUCT CURB RAMPS AT VARIOUS LOCATIONS IN ARMSTRONG |
0904-00-168 | VA | Actual | SEP 2015 | $225,675 | 1 | HARDWARE UPGRADE TO EXISTING SYSTEM |
0904-02-037 | CR | Actual | APR 2016 | $1,220,117 | 6 | REPLACE BRIDGE AND APPROACHES |
Randall County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0904-11-059 | CS | Actual | JAN 2016 | $43,673 | 8 | 2016 FED RAILROAD SIGNAL PR2016 FED |
Roberts County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0169-08-022 | US 60 | Actual | JAN 2016 | $996,579 | 8 | CENTERLINE TEXTURING |
Sherman County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0238-06-029 | US 54 | Actual | FEB 2016 | $7,825,684 | 1 | OVERLAY |
|