Detail Letting Schedule for Collin County (FY 2016)
Collin County (FY 2016) |
CCSJ: 0047-04-024 | |||
District: | Dallas | Let Date: | MAR 2016 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | STP 2016(823) | CSJ: | 0047-04-024 |
Description: | MILL, BASE REPAIR, OVERLAY | Handling Code: |
|
Limits From: | SH 121 | Fund Cat: | 1 |
Limits To: | CR 422 | Estimate: | $2,115,291 |
Length: | 3.9 Miles | Actual: | $1,706,081 |
District: | Dallas | Let Date: | MAR 2016 |
Highway: | SH 5 | Let Status: | Actual |
Project ID: | STP 2016(823) | CSJ: | 0047-04-025 |
Description: | MILL, FLEXIBLE PAVEMENT REPAIR AND 2" OVERLAY | Handling Code: |
|
Limits From: | CR 422 | Fund Cat: | 1 |
Limits To: | GRAYSON COUNTY LINE | Estimate: | $2,003,326 |
Length: | 5.2 Miles | Actual: | $1,736,133 |
Back... |
Totals for 0047-04-024 | ||
---|---|---|---|
Length: | 9.1 Miles | ||
Estimate: | $4,118,617 | ||
Actual: | $3,442,214 | ||
CCSJ: 0047-06-133 | |||
District: | Dallas | Let Date: | NOV 2015 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | STP 1502(083)MM | CSJ: | 0047-06-133 |
Description: | WIDEN D - C FROM PGBT TO NB US 75 & SB US 75 TO PGBT; EXT DART | Handling Code: |
|
Limits From: | PGBT | Fund Cat: | 3 |
Limits To: | PARK BLVD | Estimate: | $45,542,463 |
Length: | 1.4 Miles | Actual: | $37,466,722 |
Back... |
Totals for 0047-06-133 | ||
Length: | 1.4 Miles | ||
Estimate: | $45,542,463 | ||
Actual: | $37,466,722 | ||
CCSJ: 0047-06-157 | |||
District: | Dallas | Let Date: | SEP 2015 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | NH 2016(089) | CSJ: | 0047-06-157 |
Description: | FULL DEPTH CONCRETE REPAIR | Handling Code: |
|
Limits From: | SH 190 | Fund Cat: | 1 |
Limits To: | EXCHANGE PARKWAY | Estimate: | $673,222 |
Length: | 10.1 Miles | Actual: | $741,742 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | SS 359 | Let Status: | Actual |
Project ID: | STP 2016(090) | CSJ: | 0047-15-005 |
Description: | FULL DEPTH CONCRETE REPAIR | Handling Code: |
|
Limits From: | US 75 | Fund Cat: | 1 |
Limits To: | GRAVES STREET | Estimate: | $288,845 |
Length: | 0.6 Miles | Actual: | $326,697 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | SH 289 | Let Status: | Actual |
Project ID: | NH 2016(089) | CSJ: | 0091-05-069 |
Description: | FULL DEPTH CONCRETE REPAIR | Handling Code: |
|
Limits From: | FM 3537 | Fund Cat: | 1 |
Limits To: | SH 121 | Estimate: | $57,475 |
Length: | 3.9 Miles | Actual: | $61,107 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | NH 2016(089) | CSJ: | 0135-02-055 |
Description: | FULL DEPTH CONCRETE REPAIR | Handling Code: |
|
Limits From: | LAKE FOREST DR | Fund Cat: | 1 |
Limits To: | SH 5 | Estimate: | $122,306 |
Length: | 3.9 Miles | Actual: | $152,508 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | NH 2016(089) | CSJ: | 0135-02-056 |
Description: | ADD RIGHT TURN LANE, MEDIAN, FULL DEPTH REPAIR, ETC. | Handling Code: |
|
Limits From: | TREMONT BLVD | Fund Cat: | 1 |
Limits To: | GRASSMERE LN | Estimate: | $91,682 |
Length: | 0.1 Miles | Actual: | $132,645 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | NH 2016(089) | CSJ: | 0135-03-044 |
Description: | FULL DEPTH CONCRETE REPAIR | Handling Code: |
|
Limits From: | SH 5 | Fund Cat: | 1 |
Limits To: | AIRPORT ROAD | Estimate: | $25,045 |
Length: | 1.0 Miles | Actual: | $36,577 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | SH 78 | Let Status: | Actual |
Project ID: | STP 2016(090) | CSJ: | 0281-02-071 |
Description: | FULL DEPTH CONCRETE REPAIR | Handling Code: |
|
Limits From: | DALLAS COUNTY LINE | Fund Cat: | 1 |
Limits To: | SPRING CREEK PARKWAY | Estimate: | $22,195 |
Length: | 5.0 Miles | Actual: | $25,207 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | FM 3038 | Let Status: | Actual |
Project ID: | STP 2016(090) | CSJ: | 3132-01-010 |
Description: | FULL DEPTH CONCRETE REPAIR | Handling Code: |
|
Limits From: | HARDIN ROAD | Fund Cat: | 1 |
Limits To: | US 75 | Estimate: | $39,390 |
Length: | 1.6 Miles | Actual: | $50,938 |
Back... |
Totals for 0047-06-157 | ||
Length: | 26.2 Miles | ||
Estimate: | $1,320,160 | ||
Actual: | $1,527,421 | ||
CCSJ: 0047-14-069 | |||
District: | Dallas | Let Date: | DEC 2015 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | C 47-14-69 | CSJ: | 0047-14-069 |
Description: | RECONSTRUCT AND WIDEN 4 LANE TO 6 LANES AND 2 LANE FRONTAGE | Handling Code: |
|
Limits From: | NORTH OF MELISSA RD | Fund Cat: | 2M |
Limits To: | SOUTH OF FM 455 INTERCHANGE | Estimate: | $57,894,185 |
Length: | 2.6 Miles | Actual: | $52,320,789 |
District: | Dallas | Let Date: | DEC 2015 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | C 47-14-74 | CSJ: | 0047-14-074 |
Description: | CONSTRUCT INTERCHANGE | Handling Code: |
|
Limits From: | AT FM 455 INTERCHANGE IN ANNA | Fund Cat: | 2M |
Limits To: | . | Estimate: | $30,743,371 |
Length: | 2.0 Miles | Actual: | $26,871,304 |
District: | Dallas | Let Date: | DEC 2015 |
Highway: | US 75 | Let Status: | Actual |
Project ID: | C 47-14-79 | CSJ: | 0047-14-079 |
Description: | ONE COURSE SURFACE TREATMENT, BACK FILLING, RESTRIPING OF | Handling Code: |
|
Limits From: | FRONTAGE RDS NORTH OF FM 455 | Fund Cat: | 1 |
Limits To: | MANTUA RD | Estimate: | $681,838 |
Length: | 1.4 Miles | Actual: | $225,580 |
Back... |
Totals for 0047-14-069 | ||
Length: | 6.0 Miles | ||
Estimate: | $89,319,394 | ||
Actual: | $79,417,673 | ||
CCSJ: 0091-05-073 | |||
District: | Dallas | Let Date: | AUG 2016 |
Highway: | SH 289 | Let Status: | Actual |
Project ID: | NH 1602(420) | CSJ: | 0091-05-073 |
Description: | LANDSCAPE TREATMENT OF RIGHT OF WAY AND MEDIANS | Handling Code: |
|
Limits From: | PGBT | Fund Cat: | 10 |
Limits To: | SH 121 | Estimate: | $525,758 |
Length: | 6.0 Miles | Actual: | $474,268 |
Back... |
Totals for 0091-05-073 | ||
Length: | 6.0 Miles | ||
Estimate: | $525,758 | ||
Actual: | $474,268 | ||
CCSJ: 0281-01-032 | |||
District: | Dallas | Let Date: | SEP 2015 |
Highway: | SH 78 | Let Status: | Actual |
Project ID: | STP 2016(096) | CSJ: | 0280-02-042 |
Description: | MILL, BASE REPAIR AND OVERLAY | Handling Code: |
|
Limits From: | US 380 | Fund Cat: | 1 |
Limits To: | BS 78E(NORTH) | Estimate: | $545,890 |
Length: | 1.4 Miles | Actual: | $543,301 |
District: | Dallas | Let Date: | SEP 2015 |
Highway: | SH 78 | Let Status: | Actual |
Project ID: | STP 2016(096) | CSJ: | 0281-01-032 |
Description: | BASE REPAIR, MILL AND OVERLAY | Handling Code: |
|
Limits From: | FM 6 | Fund Cat: | 1 |
Limits To: | US 380 | Estimate: | $2,108,669 |
Length: | 8.9 Miles | Actual: | $2,089,993 |
Back... |
Totals for 0281-01-032 | ||
Length: | 10.3 Miles | ||
Estimate: | $2,654,559 | ||
Actual: | $2,633,294 | ||
CCSJ: 0549-03-025 | |||
District: | Dallas | Let Date: | JAN 2016 |
Highway: | SH 121 | Let Status: | Actual |
Project ID: | STP 1502(318)HES | CSJ: | 0549-03-025 |
Description: | CONSTRUCTION OF SH 160 GRADE SEPARATION | Handling Code: |
|
Limits From: | SOUTH OF SH 160 | Fund Cat: | 8 |
Limits To: | NORTH OF SH 160 | Estimate: | $14,631,220 |
Length: | 1.5 Miles | Actual: | $14,843,627 |
Back... |
Totals for 0549-03-025 | ||
Length: | 1.5 Miles | ||
Estimate: | $14,631,220 | ||
Actual: | $14,843,627 | ||
CCSJ: 0816-04-054 | |||
District: | Dallas | Let Date: | OCT 2015 |
Highway: | FM 455 | Let Status: | Actual |
Project ID: | STP 2016(144) | CSJ: | 0816-04-054 |
Description: | SHOULDER WIDENING, BASE REPAIR, OVERLAY AND GUARDRAIL | Handling Code: |
|
Limits From: | 0.21 MILE WEST OF FM 3356 | Fund Cat: | 1 |
Limits To: | US 75 | Estimate: | $3,791,485 |
Length: | 4.1 Miles | Actual: | $3,588,995 |
District: | Dallas | Let Date: | OCT 2015 |
Highway: | FM 1562 | Let Status: | Actual |
Project ID: | STP 2016(144) | CSJ: | 1492-01-010 |
Description: | PROVIDE ADDITIONAL PAVEMENT WIDTH | Handling Code: |
|
Limits From: | FM 981 | Fund Cat: | 1 |
Limits To: | HUNT COUNTY LINE | Estimate: | $303,372 |
Length: | 1.0 Miles | Actual: | $277,007 |
Back... |
Totals for 0816-04-054 | ||
Length: | 5.1 Miles | ||
Estimate: | $4,094,857 | ||
Actual: | $3,866,002 | ||
CCSJ: 0816-05-023 | |||
District: | Dallas | Let Date: | JUL 2016 |
Highway: | FM 2862 | Let Status: | Actual |
Project ID: | CRX 816-5-23 | CSJ: | 0816-05-023 |
Description: | INSTALL RAILROAD CROSSING SURFACE | Handling Code: |
XX |
Limits From: | AT BNSF RR | Fund Cat: | 10 |
Limits To: | DOT NO. 765315S | Estimate: | $22,144 |
Length: | 0.2 Miles | Actual: | $22,144 |
Back... |
Totals for 0816-05-023 | ||
Length: | 0.2 Miles | ||
Estimate: | $22,144 | ||
Actual: | $22,144 | ||
CCSJ: 0918-24-203 | |||
District: | Dallas | Let Date: | AUG 2016 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2014(149)TE | CSJ: | 0918-24-203 |
Description: | ON STREET BICYCLE FACILITIES;SIGNAGE;MARKINGS | Handling Code: |
LC |
Limits From: | ON-STREET BICYCLE TREATMENTS | Fund Cat: | 3 |
Limits To: | CITY OF MCKINNEY-CITY WIDE | Estimate: | $250,000 |
Length: | 147.3 Miles | Actual: | $249,968 |
Back... |
Totals for 0918-24-203 | ||
Length: | 147.3 Miles | ||
Estimate: | $250,000 | ||
Actual: | $249,968 | ||
CCSJ: 0918-24-237 | |||
District: | Dallas | Let Date: | AUG 2016 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2017(429)MM | CSJ: | 0918-24-237 |
Description: | UPDATE HUNT COUNTY TRANS PLAN TO IDENTIFY IMPROVEMENTS TO | Handling Code: |
XX |
Limits From: | HUNT COUNTY AND COLLIN COUNTY | Fund Cat: | 3 |
Limits To: | . | Estimate: | $1,378,874 |
Length: | 0.0 Miles | Actual: | $1,379,874 |
Back... |
Totals for 0918-24-237 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,378,874 | ||
Actual: | $1,379,874 | ||
CCSJ: 1013-01-026 | |||
District: | Dallas | Let Date: | MAY 2016 |
Highway: | FM 546 | Let Status: | Actual |
Project ID: | C 1013-1-26 | CSJ: | 1013-01-026 |
Description: | REALIGN HIGHWAY - CONSTRUCT FOUR LANE DIVIDED FACILITY | Handling Code: |
|
Limits From: | SH 5 | Fund Cat: | 3 |
Limits To: | EAST OF COUNTRY LN/AIRPORT RD | Estimate: | $19,245,166 |
Length: | 1.7 Miles | Actual: | $17,391,617 |
Back... |
Totals for 1013-01-026 | ||
Length: | 1.7 Miles | ||
Estimate: | $19,245,166 | ||
Actual: | $17,391,617 | ||
CCSJ: 2351-01-020 | |||
District: | Dallas | Let Date: | OCT 2015 |
Highway: | FM 2478 | Let Status: | Actual |
Project ID: | PTF 1502(566) | CSJ: | 2351-01-020 |
Description: | WIDEN FOUR LANE DIVIDED URBAN ROADWAY TO SIX LANES | Handling Code: |
LC |
Limits From: | SH 121 | Fund Cat: | 3 |
Limits To: | STONEBRIDGE DRIVE | Estimate: | $7,265,146 |
Length: | 2.9 Miles | Actual: | $7,473,978 |
Back... |
Totals for 2351-01-020 | ||
Length: | 2.9 Miles | ||
Estimate: | $7,265,146 | ||
Actual: | $7,473,978 |
|