Detail Letting Schedule for Uvalde County (FY 2015)

Last Update: Tuesday, September 29, 2015
Uvalde County (FY 2015)

CCSJ: 0023-05-081

District: San Antonio Let Date: DEC 2014
Highway: US 90 Let Status: Actual
Project ID: STP 2015(367)HES CSJ: 0023-05-081
Description: FLATTEN SIDE SLOPES, SAFETY TREAT FIXED OBJECTS, AND PLACE Handling
Code:
 
Limits From: KINNEY COUNTY LINE Fund Cat: 8
Limits To: FM 481 Estimate: $1,069,138
Length: 18.6 Miles Actual: $1,411,821
 
Back...

Totals for 0023-05-081
Length: 18.6 Miles
Estimate: $1,069,138
Actual: $1,411,821

CCSJ: 0036-08-051

District: San Antonio Let Date: JUN 2015
Highway: US 83 Let Status: Actual
Project ID: STP 1502(265)HES CSJ: 0036-08-051
Description: CONSTRUCT LEFT TURN LN, INSTALL INT FLASHING BEACON, SAFETY Handling
Code:
 
Limits From: SH 55 Fund Cat: 8
Limits To: 0.2 MI N OF FM 1051 Estimate: $1,832,201
Length: 17.8 Miles Actual: $1,685,721
 
District: San Antonio Let Date: JUN 2015
Highway: FM 140 Let Status: Actual
Project ID: STP 1502(264)HRR CSJ: 0875-01-017
Description: WIDEN NARROW ROADWAY, INSTALL ADVANCED WARNING SIGNALS AND Handling
Code:
 
Limits From: 1.2 MI E FM 117 Fund Cat: 8
Limits To: 1.6 MI E FM 117 Estimate: $342,147
Length: 0.4 Miles Actual: $480,173
 
Back...

Totals for 0036-08-051
Length: 18.2 Miles
Estimate: $2,174,348
Actual: $2,165,894

CCSJ: 0236-01-022

District: San Antonio Let Date: DEC 2014
Highway: FM 117 Let Status: Actual
Project ID: STP 2015(369) CSJ: 0236-01-022
Description: RESTORATION, SURFACE AND PAVEMENT MARKINGS Handling
Code:
 
Limits From: US 83 Fund Cat: 1
Limits To: 2.0 MILES NORTH OF ZAVALA C/L Estimate: $2,821,398
Length: 6.7 Miles Actual: $2,075,091
 
Back...

Totals for 0236-01-022
Length: 6.7 Miles
Estimate: $2,821,398
Actual: $2,075,091


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract