Detail Letting Schedule for Bexar County (FY 2015)
Bexar County (FY 2015) |
CCSJ: 0017-10-271 | |||
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | STP 1402(064)MM | CSJ: | 0017-10-271 |
Description: | INSTALL MEDIAN BARRIER, PAVEMENT MARKINGS AND SIGNING | Handling Code: |
|
Limits From: | 0.8 MI S OF US 281 | Fund Cat: | 7 |
Limits To: | 0.1 MI S OF US 281 | Estimate: | $1,702,594 |
Length: | 0.8 Miles | Actual: | $2,254,456 |
Back... |
Totals for 0017-10-271 | ||
---|---|---|---|
Length: | 0.8 Miles | ||
Estimate: | $1,702,594 | ||
Actual: | $2,254,456 | ||
CCSJ: 0024-07-058 | |||
District: | San Antonio | Let Date: | MAY 2015 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | NH 1502(164) | CSJ: | 0024-07-058 |
Description: | FRONTAGE ROAD, INTERSECTION & RAMP OPERATIONAL IMPROVEMENTS | Handling Code: |
|
Limits From: | LP 1604 | Fund Cat: | 1 |
Limits To: | 0.8 MI. WEST OF IH 410 | Estimate: | $20,635,737 |
Length: | 2.5 Miles | Actual: | $20,101,916 |
District: | San Antonio | Let Date: | MAY 2015 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | NH 1502(164) | CSJ: | 0024-08-130 |
Description: | FRONTAGE ROAD, INTERSECTION & RAMP OPERATIONAL IMPROVEMENTS | Handling Code: |
|
Limits From: | 0.8 MI. WEST OF IH 410 | Fund Cat: | 1 |
Limits To: | IH 410 | Estimate: | $2,632,019 |
Length: | 0.8 Miles | Actual: | $2,614,554 |
Back... |
Totals for 0024-07-058 | ||
Length: | 3.3 Miles | ||
Estimate: | $23,267,756 | ||
Actual: | $22,716,470 | ||
CCSJ: 0024-08-131 | |||
District: | San Antonio | Let Date: | JUN 2015 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | NH 1502(263) | CSJ: | 0024-08-131 |
Description: | LANDSCAPE DEVELOPMENT | Handling Code: |
|
Limits From: | 1.0 MILE WEST OF LOOP 13 | Fund Cat: | 10 |
Limits To: | 1.0 MILE EAST OF LOOP 13 | Estimate: | $359,552 |
Length: | 2.0 Miles | Actual: | $355,044 |
Back... |
Totals for 0024-08-131 | ||
Length: | 2.0 Miles | ||
Estimate: | $359,552 | ||
Actual: | $355,044 | ||
CCSJ: 0025-02-201 | |||
District: | San Antonio | Let Date: | OCT 2014 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | STP 2015(195)HESG | CSJ: | 0025-02-201 |
Description: | SAFETY LIGHTING | Handling Code: |
|
Limits From: | 0.2 MI WEST OF GRAYTOWN | Fund Cat: | 8 |
Limits To: | 0.2 MI EAST OF PFEIL | Estimate: | $214,739 |
Length: | 1.4 Miles | Actual: | $161,836 |
District: | San Antonio | Let Date: | OCT 2014 |
Highway: | IH 410 | Let Status: | Actual |
Project ID: | STP 2015(196)HESG | CSJ: | 0521-06-136 |
Description: | SAFETY LIGHTING | Handling Code: |
|
Limits From: | FM 1346 | Fund Cat: | 8 |
Limits To: | IH 37 | Estimate: | $1,491,015 |
Length: | 6.9 Miles | Actual: | $1,225,047 |
District: | San Antonio | Let Date: | OCT 2014 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2015(197)HESG | CSJ: | 2452-01-060 |
Description: | SAFETY LIGHTING | Handling Code: |
|
Limits From: | SH 16 | Fund Cat: | 8 |
Limits To: | 1.0 MI S OF SH 16 | Estimate: | $206,351 |
Length: | 1.0 Miles | Actual: | $166,393 |
District: | San Antonio | Let Date: | OCT 2014 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2015(198)HESG | CSJ: | 2452-02-086 |
Description: | SAFETY LIGHTING | Handling Code: |
|
Limits From: | SH 16 | Fund Cat: | 8 |
Limits To: | FM 1560 | Estimate: | $365,928 |
Length: | 1.5 Miles | Actual: | $296,129 |
District: | San Antonio | Let Date: | OCT 2014 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2015(451)HESG | CSJ: | 2452-03-110 |
Description: | SAFETY LIGHTING | Handling Code: |
|
Limits From: | SH 218 | Fund Cat: | 1 |
Limits To: | 0.4 MI S OF FM 78 | Estimate: | $1,008,726 |
Length: | 3.0 Miles | Actual: | $863,337 |
Back... |
Totals for 0025-02-201 | ||
Length: | 13.8 Miles | ||
Estimate: | $3,286,759 | ||
Actual: | $2,712,742 | ||
CCSJ: 0025-02-202 | |||
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | STP 2015(723)HES | CSJ: | 0025-02-202 |
Description: | TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKERS) | Handling Code: |
|
Limits From: | AT IH 35 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $100,475 |
Length: | 0.6 Miles | Actual: | $87,588 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | STP 2015(724)HES | CSJ: | 0025-02-203 |
Description: | TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKERS) | Handling Code: |
|
Limits From: | AT IH 37 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $95,962 |
Length: | 1.0 Miles | Actual: | $90,414 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | US 90A | Let Status: | Actual |
Project ID: | STP 2015(725)HES | CSJ: | 0025-04-049 |
Description: | TEXTURIZE CENTERLINE | Handling Code: |
|
Limits From: | 0.6 MI EAST OF SH 123 | Fund Cat: | 8 |
Limits To: | GONZALES COUNTY LINE | Estimate: | $314,087 |
Length: | 13.3 Miles | Actual: | $200,476 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | SH 173 | Let Status: | Actual |
Project ID: | STP 2015(726)HES | CSJ: | 0421-01-044 |
Description: | TEXTURIZE SHOULDERS AND CENTERLINE | Handling Code: |
|
Limits From: | HONDO CREEK | Fund Cat: | 8 |
Limits To: | FM 1343 | Estimate: | $164,714 |
Length: | 7.8 Miles | Actual: | $105,257 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | SH 72 | Let Status: | Actual |
Project ID: | STP 2015(727)HES | CSJ: | 0483-02-020 |
Description: | TEXTURIZE SHOULDERS AND CENTERLINE | Handling Code: |
|
Limits From: | SH 97 | Fund Cat: | 8 |
Limits To: | SH 16 | Estimate: | $301,712 |
Length: | 15.6 Miles | Actual: | $191,744 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2015(729)HES | CSJ: | 0517-01-045 |
Description: | TEXTURIZE SHOULDERS AND CENTERLINE | Handling Code: |
|
Limits From: | CR 328 | Fund Cat: | 8 |
Limits To: | MCMULLEN COUNTY LINE | Estimate: | $313,217 |
Length: | 13.5 Miles | Actual: | $199,607 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2015(730)HES | CSJ: | 0517-03-031 |
Description: | INSTALL ADVANCED WARNING SIGNALS AND SIGNS | Handling Code: |
|
Limits From: | AT FM 624 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $24,906 |
Length: | 0.1 Miles | Actual: | $31,580 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | SH 46 | Let Status: | Actual |
Project ID: | STP 2015(731)HES | CSJ: | 1042-02-020 |
Description: | TEXTURIZE SHOULDERS AND CENTERLINE | Handling Code: |
|
Limits From: | BANDERA COUNTY LINE | Fund Cat: | 8 |
Limits To: | IH 10 | Estimate: | $178,637 |
Length: | 6.7 Miles | Actual: | $114,209 |
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | FM 1560 | Let Status: | Actual |
Project ID: | STP 2015(732)HES | CSJ: | 2230-01-015 |
Description: | TEXTURIZE SHOULDERS AND CENTERLINE | Handling Code: |
|
Limits From: | SH 16 | Fund Cat: | 8 |
Limits To: | FM 471 | Estimate: | $137,555 |
Length: | 5.2 Miles | Actual: | $88,054 |
Back... |
Totals for 0025-02-202 | ||
Length: | 63.8 Miles | ||
Estimate: | $1,631,265 | ||
Actual: | $1,108,929 | ||
CCSJ: 0025-09-076 | |||
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | FM 78 | Let Status: | Actual |
Project ID: | STP 2015(580)HES | CSJ: | 0025-09-076 |
Description: | IMPROVE TRAFFIC SIGNAL, ADD LEFT AND RIGHT TURN LANES | Handling Code: |
|
Limits From: | AT LP 1604 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $2,147,085 |
Length: | 0.1 Miles | Actual: | $2,187,618 |
Back... |
Totals for 0025-09-076 | ||
Length: | 0.1 Miles | ||
Estimate: | $2,147,085 | ||
Actual: | $2,187,618 | ||
CCSJ: 0072-07-066 | |||
District: | San Antonio | Let Date: | JUL 2015 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | C 72-7-66 | CSJ: | 0072-07-066 |
Description: | CONSTRUCT GRADE SEPARATION AT OLD FREDRICKSBURG, RECONFIGURE | Handling Code: |
|
Limits From: | FAIR OAKS | Fund Cat: | 1 |
Limits To: | FM 3351 | Estimate: | $28,402,259 |
Length: | 3.4 Miles | Actual: | $31,088,817 |
District: | San Antonio | Let Date: | JUL 2015 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | ROW 72-7-71 | CSJ: | 0072-07-071 |
Description: | UTILITIES | Handling Code: |
|
Limits From: | FAIR OAKS | Fund Cat: | ROW |
Limits To: | FM 3351 | Estimate: | $6,732,000 |
Length: | 3.4 Miles | Actual: | $70,303 |
Back... |
Totals for 0072-07-066 | ||
Length: | 6.8 Miles | ||
Estimate: | $35,134,259 | ||
Actual: | $31,159,120 | ||
CCSJ: 0073-02-069 | |||
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | NH 2015(284) | CSJ: | 0024-05-096 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.627 MI E OF SH 173 | Fund Cat: | 1 |
Limits To: | 0.176 MI E OF CR 4643 | Estimate: | $714,000 |
Length: | 7.2 Miles | Actual: | $624,209 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | NH 2015(284) | CSJ: | 0073-02-069 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | LP 1604 | Fund Cat: | 1 |
Limits To: | BEXAR/ATASCOSA C/L | Estimate: | $484,259 |
Length: | 5.4 Miles | Actual: | $459,227 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | US 281A | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 0073-13-010 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 37 | Fund Cat: | 1 |
Limits To: | ATASCOSA/LIVE OAK COUNTY LINE | Estimate: | $425,652 |
Length: | 9.6 Miles | Actual: | $401,861 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | US 57 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 0276-07-030 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | ZAVALA/FRIO COUNTY LINE | Fund Cat: | 1 |
Limits To: | FM 140 | Estimate: | $570,810 |
Length: | 11.1 Miles | Actual: | $527,750 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SH 85 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 0301-06-016 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 35 BUSINESS | Fund Cat: | 1 |
Limits To: | FM 1582 | Estimate: | $450,000 |
Length: | 14.1 Miles | Actual: | $449,650 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 0613-01-060 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | LP 1604 | Fund Cat: | 1 |
Limits To: | BEXAR/ATASCOSA C/L | Estimate: | $356,116 |
Length: | 4.0 Miles | Actual: | $356,411 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | FM 462 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 0848-03-013 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 470 (TARPLEY) | Fund Cat: | 1 |
Limits To: | BANDERA/MEDINA C/L | Estimate: | $60,000 |
Length: | 2.4 Miles | Actual: | $77,609 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | FM 462 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 0848-04-047 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | BANDERA/MEDINA C/L | Fund Cat: | 1 |
Limits To: | CR 433 | Estimate: | $445,000 |
Length: | 18.6 Miles | Actual: | $437,247 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 1479-01-023 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 1937 | Fund Cat: | 1 |
Limits To: | SH 16 | Estimate: | $525,000 |
Length: | 8.9 Miles | Actual: | $457,542 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | FM 471 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 1547-01-044 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | FM 2790 | Estimate: | $196,225 |
Length: | 4.8 Miles | Actual: | $187,422 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | FM 476 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 1740-01-007 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 2790 | Fund Cat: | 1 |
Limits To: | BEXAR/ATASCOSA C/L | Estimate: | $45,000 |
Length: | 1.0 Miles | Actual: | $34,146 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | FM 2790 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 1741-02-032 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 476 | Fund Cat: | 1 |
Limits To: | SOMERSET ROAD | Estimate: | $47,000 |
Length: | 1.4 Miles | Actual: | $48,395 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | FM 2790 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 1741-02-033 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | MEDINA RIVER_BRIDGE | Fund Cat: | 1 |
Limits To: | IH 410 FRONTAGE ROAD | Estimate: | $110,000 |
Length: | 2.6 Miles | Actual: | $100,568 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 2020-02-030 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 35 | Fund Cat: | 1 |
Limits To: | 2.413 MI N OF IH 35 | Estimate: | $125,000 |
Length: | 2.4 Miles | Actual: | $108,806 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 2255-01-079 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 37 | Fund Cat: | 1 |
Limits To: | FM 1937 | Estimate: | $130,000 |
Length: | 2.0 Miles | Actual: | $114,726 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | FM 624 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 2373-03-015 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 16 | Fund Cat: | 1 |
Limits To: | MCMULLEN/LIVE OAK COUNTY LINE | Estimate: | $510,000 |
Length: | 16.1 Miles | Actual: | $451,368 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | STP 2015(283) | CSJ: | 2452-01-058 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 2.413 MI N OF IH 35 | Fund Cat: | 1 |
Limits To: | MEDINA RIVER | Estimate: | $85,000 |
Length: | 1.7 Miles | Actual: | $72,184 |
Back... |
Totals for 0073-02-069 | ||
Length: | 113.3 Miles | ||
Estimate: | $5,279,062 | ||
Actual: | $4,909,121 | ||
CCSJ: 0073-02-070 | |||
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2015(285)HES | CSJ: | 0073-02-070 |
Description: | INSTALL MEDIAN BARRIER, RESURFACING, TEXTURIZE SHOULDERS | Handling Code: |
|
Limits From: | FM 1937 | Fund Cat: | 8 |
Limits To: | ATASCOSA COUNTY LINE | Estimate: | $6,819,850 |
Length: | 11.4 Miles | Actual: | $7,142,618 |
Back... |
Totals for 0073-02-070 | ||
Length: | 11.4 Miles | ||
Estimate: | $6,819,850 | ||
Actual: | $7,142,618 | ||
CCSJ: 0073-08-170 | |||
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | IH 37 | Let Status: | Actual |
Project ID: | STP 2015(023)HESG | CSJ: | 0073-08-170 |
Description: | INSTALL CABLE BARRIER SYSTEM IN CENTER MEDIAN | Handling Code: |
|
Limits From: | US 181 | Fund Cat: | 8 |
Limits To: | 1.7 MI S OF US 181 | Estimate: | $574,034 |
Length: | 1.7 Miles | Actual: | $353,414 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | IH 37 | Let Status: | Actual |
Project ID: | STP 2015(024)HESG | CSJ: | 0073-09-033 |
Description: | INSTALL CABLE BARRIER SYSTEM IN CENTER MEDIAN | Handling Code: |
|
Limits From: | 1.7 MI S OF US 181 | Fund Cat: | 8 |
Limits To: | ATASCOSA COUNTY LINE | Estimate: | $336,170 |
Length: | 11.9 Miles | Actual: | $244,454 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | US 181 | Let Status: | Actual |
Project ID: | STP 2015(025)HESG | CSJ: | 0073-12-011 |
Description: | INSTALL CABLE BARRIER SYSTEM IN CENTER MEDIAN & MILLED - IN | Handling Code: |
|
Limits From: | 1.3 MI E OF IH 37 | Fund Cat: | 8 |
Limits To: | IH 37 | Estimate: | $186,838 |
Length: | 0.7 Miles | Actual: | $138,094 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | US 181 | Let Status: | Actual |
Project ID: | STP 2015(026)HESG | CSJ: | 0100-02-062 |
Description: | INSTALL CABLE BARRIER SYSTEM IN CENTER MEDIAN & MILLED - IN | Handling Code: |
|
Limits From: | LP 1604 | Fund Cat: | 8 |
Limits To: | 1.3 MI E OF IH 37 | Estimate: | $776,926 |
Length: | 5.6 Miles | Actual: | $571,826 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2015(027)HESG | CSJ: | 0253-03-069 |
Description: | INSTALL CABLE BARRIER SYSTEM IN CENTER MEDIAN | Handling Code: |
|
Limits From: | BEXAR COUNTY LINE | Fund Cat: | 8 |
Limits To: | GUADLUPE RIVER | Estimate: | $1,169,190 |
Length: | 9.2 Miles | Actual: | $858,394 |
Back... |
Totals for 0073-08-170 | ||
Length: | 29.1 Miles | ||
Estimate: | $3,043,158 | ||
Actual: | $2,166,182 | ||
CCSJ: 0073-08-171 | |||
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2015(028)HESG | CSJ: | 0073-08-171 |
Description: | PLACE INVERTED PROFILE PAVEMENT MARKINGS ALONG EDGELINES | Handling Code: |
|
Limits From: | SP 537 | Fund Cat: | 8 |
Limits To: | NEWELL STREET | Estimate: | $139,306 |
Length: | 8.0 Miles | Actual: | $120,755 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2015(029)HESG | CSJ: | 0253-04-145 |
Description: | PLACE INVERTED PROFILE PAVEMENT MARKINGS ALONG EDGELINES | Handling Code: |
|
Limits From: | REDLAND ROAD | Fund Cat: | 8 |
Limits To: | SP 537 | Estimate: | $62,396 |
Length: | 5.7 Miles | Actual: | $53,360 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | FM 306 | Let Status: | Actual |
Project ID: | STP 2015(030)HESG | CSJ: | 0857-01-030 |
Description: | PLACE INVERTED PROFILE PAVEMENT MARKINGS ALONG EDGELINES | Handling Code: |
|
Limits From: | FM 3424 | Fund Cat: | 8 |
Limits To: | JACOBS CREEK PARK ROAD | Estimate: | $21,924 |
Length: | 2.9 Miles | Actual: | $19,418 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | FM 306 | Let Status: | Actual |
Project ID: | STP 2015(031)HESG | CSJ: | 1728-02-056 |
Description: | PLACE INVERTED PROFILE PAVEMENT MARKINGS ON EDGELINES & | Handling Code: |
|
Limits From: | JACOBS CREEK PARK ROAD | Fund Cat: | 8 |
Limits To: | IH 35 | Estimate: | $190,467 |
Length: | 15.5 Miles | Actual: | $164,006 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | FM 2673 | Let Status: | Actual |
Project ID: | STP 2015(032)HESG | CSJ: | 2650-01-023 |
Description: | PLACE INVERTED PROFILE PAVEMENT MARKINGS ON EDGELINES & | Handling Code: |
|
Limits From: | 0.050 MI N OF CRANES MILL | Fund Cat: | 8 |
Limits To: | FM 306 | Estimate: | $122,845 |
Length: | 10.0 Miles | Actual: | $105,772 |
Back... |
Totals for 0073-08-171 | ||
Length: | 42.1 Miles | ||
Estimate: | $536,938 | ||
Actual: | $463,311 | ||
CCSJ: 0073-08-179 | |||
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | NH 2015(286) | CSJ: | 0073-08-179 |
Description: | UPGRADE EXISTING TRAFFIC SIGNALS | Handling Code: |
|
Limits From: | AT MULBERRY AND AT ST. MARYS | Fund Cat: | 1 |
Limits To: | . | Estimate: | $522,466 |
Length: | 0.1 Miles | Actual: | $498,707 |
Back... |
Totals for 0073-08-179 | ||
Length: | 0.1 Miles | ||
Estimate: | $522,466 | ||
Actual: | $498,707 | ||
CCSJ: 0073-08-180 | |||
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | IH 37 | Let Status: | Actual |
Project ID: | NH 2015(581) | CSJ: | 0073-08-180 |
Description: | LANDSCAPE DEVELOPMENT | Handling Code: |
|
Limits From: | S HACKBERRY STREET | Fund Cat: | 10 |
Limits To: | E CESAR E CHAVEZ BLVD | Estimate: | $926,498 |
Length: | 2.0 Miles | Actual: | $973,428 |
Back... |
Totals for 0073-08-180 | ||
Length: | 2.0 Miles | ||
Estimate: | $926,498 | ||
Actual: | $973,428 | ||
CCSJ: 0100-02-064 | |||
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | US 181 | Let Status: | Actual |
Project ID: | STP 2015(288)HESG | CSJ: | 0100-02-064 |
Description: | INSTALL MEDIAN BARRIER, TEXTURIZE SHOULDERS | Handling Code: |
|
Limits From: | IH 37 | Fund Cat: | 8 |
Limits To: | LOOP 1604 | Estimate: | $1,027,732 |
Length: | 5.6 Miles | Actual: | $772,166 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 2015(287)HESG | CSJ: | 0613-01-061 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | SMITH STREET | Fund Cat: | 8 |
Limits To: | ATASCOSA COUNTY LINE | Estimate: | $301,635 |
Length: | 2.2 Miles | Actual: | $235,123 |
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | SH 151 | Let Status: | Actual |
Project ID: | STP 2015(289)HESG | CSJ: | 3508-01-027 |
Description: | INSTALL MEDIAN BARRIER, TEXTURIZE SHOULDERS | Handling Code: |
|
Limits From: | LOOP 1604 | Fund Cat: | 8 |
Limits To: | US 90 | Estimate: | $720,664 |
Length: | 10.1 Miles | Actual: | $547,672 |
Back... |
Totals for 0100-02-064 | ||
Length: | 17.9 Miles | ||
Estimate: | $2,050,031 | ||
Actual: | $1,554,961 | ||
CCSJ: 0253-04-148 | |||
District: | San Antonio | Let Date: | DEC 2014 |
Highway: | SS 537 | Let Status: | Actual |
Project ID: | NH 2015(370) | CSJ: | 0253-04-148 |
Description: | MILL, BASE REPAIR, OVERLAY AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 410 | Fund Cat: | 1 |
Limits To: | US 281 | Estimate: | $1,284,726 |
Length: | 1.2 Miles | Actual: | $1,046,040 |
Back... |
Totals for 0253-04-148 | ||
Length: | 1.2 Miles | ||
Estimate: | $1,284,726 | ||
Actual: | $1,046,040 | ||
CCSJ: 0521-04-274 | |||
District: | San Antonio | Let Date: | JUN 2015 |
Highway: | IH 410 | Let Status: | Actual |
Project ID: | C 521-4-274 | CSJ: | 0521-04-274 |
Description: | EXPAND FROM 6 TO 8 LANES FROM SH 151 TO INGRAM RD AND | Handling Code: |
|
Limits From: | SH 151 | Fund Cat: | 1 |
Limits To: | INGRAM RD. | Estimate: | $84,254,460 |
Length: | 2.7 Miles | Actual: | $81,778,634 |
District: | San Antonio | Let Date: | JUN 2015 |
Highway: | IH 410 | Let Status: | Actual |
Project ID: | ROW 521-4-276 | CSJ: | 0521-04-276 |
Description: | ROW UTILITY ADJUSTMENTS | Handling Code: |
|
Limits From: | SH 151 | Fund Cat: | ROW |
Limits To: | INGRAM RD. | Estimate: | $3,291,890 |
Length: | 2.7 Miles | Actual: | $103,972 |
Back... |
Totals for 0521-04-274 | ||
Length: | 5.4 Miles | ||
Estimate: | $87,546,350 | ||
Actual: | $81,882,606 | ||
CCSJ: 0521-06-135 | |||
District: | San Antonio | Let Date: | NOV 2014 |
Highway: | IH 410 | Let Status: | Actual |
Project ID: | STP 2015(290)HES | CSJ: | 0521-06-135 |
Description: | MILL, SC, OVERLAY, PLACE MBGF & MILLED - IN RUMBLE STRIPS ALONG | Handling Code: |
|
Limits From: | IH 37 | Fund Cat: | 8 |
Limits To: | IH 10 | Estimate: | $6,151,593 |
Length: | 7.7 Miles | Actual: | $5,210,848 |
Back... |
Totals for 0521-06-135 | ||
Length: | 7.7 Miles | ||
Estimate: | $6,151,593 | ||
Actual: | $5,210,848 | ||
CCSJ: 0849-01-047 | |||
District: | San Antonio | Let Date: | APR 2015 |
Highway: | FM 471 | Let Status: | Actual |
Project ID: | STP 2015(937)HES | CSJ: | 0849-01-047 |
Description: | INSTALL RAISED MEDIAN | Handling Code: |
|
Limits From: | LP 1604 | Fund Cat: | 8 |
Limits To: | FM 3487 | Estimate: | $521,483 |
Length: | 2.5 Miles | Actual: | $485,384 |
District: | San Antonio | Let Date: | APR 2015 |
Highway: | FM 471 | Let Status: | Actual |
Project ID: | STP 2015(936) | CSJ: | 0849-01-048 |
Description: | ULTRA THIN BONDED WEARING COURSE | Handling Code: |
|
Limits From: | LP 1604 | Fund Cat: | 1 |
Limits To: | 0.1 MI NE OF LOST LANE | Estimate: | $1,397,020 |
Length: | 5.1 Miles | Actual: | $1,265,816 |
District: | San Antonio | Let Date: | APR 2015 |
Highway: | FM 471 | Let Status: | Actual |
Project ID: | ROW 849-1-50 | CSJ: | 0849-01-050 |
Description: | UTILITY RELOCATION / ADJUSTMENT | Handling Code: |
|
Limits From: | LP 1604 | Fund Cat: | ROW |
Limits To: | 0.1 MI NE OF LOST LANE | Estimate: | $60,000 |
Length: | 5.1 Miles | Actual: | $21,735 |
Back... |
Totals for 0849-01-047 | ||
Length: | 12.7 Miles | ||
Estimate: | $1,978,503 | ||
Actual: | $1,772,935 | ||
CCSJ: 0915-00-165 | |||
District: | San Antonio | Let Date: | FEB 2015 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2015(584) | CSJ: | 0915-00-165 |
Description: | DISTRICTWIDE NON - SITE SPECIFIC TRAFFIC SIGNALS - FY 2015 | Handling Code: |
|
Limits From: | DISTRICTWIDE TRAFFIC CNTRL FY 2015 | Fund Cat: | 1 |
Limits To: | . | Estimate: | $1,569,896 |
Length: | 0.0 Miles | Actual: | $1,424,347 |
Back... |
Totals for 0915-00-165 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,569,896 | ||
Actual: | $1,424,347 | ||
CCSJ: 0915-12-439 | |||
District: | San Antonio | Let Date: | JAN 2015 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2007(638) | CSJ: | 0915-12-439 |
Description: | REHABILITATE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | GROSS LANE AT MEDINA RIVER | Fund Cat: | 6 |
Limits To: | . | Estimate: | $567,010 |
Length: | 0.0 Miles | Actual: | $527,481 |
Back... |
Totals for 0915-12-439 | ||
Length: | 0.0 Miles | ||
Estimate: | $567,010 | ||
Actual: | $527,481 | ||
CCSJ: 0915-12-496 | |||
District: | San Antonio | Let Date: | JUN 2015 |
Highway: | VA | Let Status: | Actual |
Project ID: | TCSP 2012(238) | CSJ: | 0915-12-496 |
Description: | EXTEND 36TH ST ALONG EXISTING WAGNER / TINKER RD - EXPAND TO | Handling Code: |
LN |
Limits From: | BILLY MITCHELL | Fund Cat: | 3 |
Limits To: | DUNCAN | Estimate: | $3,100,000 |
Length: | 0.0 Miles | Actual: | $8,078,661 |
Back... |
Totals for 0915-12-496 | ||
Length: | 0.0 Miles | ||
Estimate: | $3,100,000 | ||
Actual: | $8,078,661 | ||
CCSJ: 0915-12-511 | |||
District: | San Antonio | Let Date: | OCT 2014 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2014(563)MM | CSJ: | 0915-12-511 |
Description: | RECONSTRUCT ROADWAY AND REPLACE EXISTING SIDEWALKS, CURBS | Handling Code: |
LC |
Limits From: | IN BEXAR COUNTY ON GLENMONT | Fund Cat: | 3 |
Limits To: | FROM CRESTWAY DR.TO OLD WALZEM RD. | Estimate: | $9,154,473 |
Length: | 1.6 Miles | Actual: | $12,259,301 |
Back... |
Totals for 0915-12-511 | ||
Length: | 1.6 Miles | ||
Estimate: | $9,154,473 | ||
Actual: | $12,259,301 | ||
CCSJ: 0915-12-530 | |||
District: | San Antonio | Let Date: | OCT 2014 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2015(199) | CSJ: | 0915-12-530 |
Description: | CONSTRUCT ADA CURB RAMPS AT VARIOUS LOCATION ALONG IH 410, | Handling Code: |
|
Limits From: | VARIOUS LOCATIONS IN BEXAR COUNTY | Fund Cat: | 10 |
Limits To: | . | Estimate: | $2,739,275 |
Length: | 0.0 Miles | Actual: | $2,958,588 |
Back... |
Totals for 0915-12-530 | ||
Length: | 0.0 Miles | ||
Estimate: | $2,739,275 | ||
Actual: | $2,958,588 | ||
CCSJ: 0915-12-536 | |||
District: | San Antonio | Let Date: | APR 2015 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2014(161)TE | CSJ: | 0915-12-536 |
Description: | SAN ANTONIO MUNICIPAL BIKE SHARE B - CYCLE URBAN CORE | Handling Code: |
XX |
Limits From: | CITY OF SAN ANTONIO | Fund Cat: | 3 |
Limits To: | . | Estimate: | $1,249,995 |
Length: | 0.0 Miles | Actual: | $1,249,995 |
Back... |
Totals for 0915-12-536 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,249,995 | ||
Actual: | $1,249,995 | ||
CCSJ: 0915-12-541 | |||
District: | San Antonio | Let Date: | AUG 2015 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2016(261)MM | CSJ: | 0915-12-541 |
Description: | FURNISH & INSTALL DETECTION EQUIPMENT ALONG MAJOR CORRIDORS | Handling Code: |
XX |
Limits From: | CITYWIDE ITS OPERATIONAL IMPROVMNTS | Fund Cat: | 3 |
Limits To: | (CITY OF SAN ANTONIO) | Estimate: | $910,000 |
Length: | 0.0 Miles | Actual: | $911,000 |
Back... |
Totals for 0915-12-541 | ||
Length: | 0.0 Miles | ||
Estimate: | $910,000 | ||
Actual: | $911,000 | ||
CCSJ: 2255-03-006 | |||
District: | San Antonio | Let Date: | JUL 2015 |
Highway: | FM 327 | Let Status: | Actual |
Project ID: | CRX 2255-3-6 | CSJ: | 2255-03-006 |
Description: | REPLANKING AT FM 327 AND UPRR DOT 764280P | Handling Code: |
XX |
Limits From: | 0.816 MI W SL 1604 | Fund Cat: | 10 |
Limits To: | 0.768 MI W OF SL 1604 | Estimate: | $24,064 |
Length: | 0.0 Miles | Actual: | $24,064 |
Back... |
Totals for 2255-03-006 | ||
Length: | 0.0 Miles | ||
Estimate: | $24,064 | ||
Actual: | $24,064 | ||
CCSJ: 2452-01-057 | |||
District: | San Antonio | Let Date: | JUN 2015 |
Highway: | SL 1604 | Let Status: | Actual |
Project ID: | C 2452-1-57 | CSJ: | 2452-01-057 |
Description: | CONSTRUCT INTERCHANGE - SH 151 ML'S OVER LP 1604 | Handling Code: |
DB |
Limits From: | AT SH 151 | Fund Cat: | 1 |
Limits To: | . | Estimate: | $30,202,578 |
Length: | 0.4 Miles | Actual: | $44,000,000 |
Back... |
Totals for 2452-01-057 | ||
Length: | 0.4 Miles | ||
Estimate: | $30,202,578 | ||
Actual: | $44,000,000 |
|