Detail Letting Schedule for Cherokee County (FY 2008)
|
Detail Letting Schedule for Cherokee County (FY 2008) |
|
Last Update: Monday, February 2, 2009 |
Cherokee County (FY 2008) |
CCSJ: 0199-02-054
|
District: |
Tyler |
Let Date: |
JAN 2008 |
Highway: |
US 69 |
Let Status: |
Actual |
Project ID: |
NH 2008(325) |
CSJ: |
0199-02-054 |
Description: |
RESURFACE ROADWAY |
Handling Code: |
|
Limits From: |
LP 62(N), 0.373 MI N OF US 84, S |
Fund Cat: |
1 |
Limits To: |
0.1 MI S OF FM 343, IN RUSK |
Estimate: |
$2,909,924 |
Length: |
2.1 Miles |
Actual: |
$2,367,571 |
|
Back...
|
Totals for 0199-02-054 |
Length: |
2.1 Miles |
Estimate: |
$2,909,924 |
Actual: |
$2,367,571 |
CCSJ: 0378-07-025
|
District: |
Tyler |
Let Date: |
SEP 2007 |
Highway: |
FM 347 |
Let Status: |
Actual |
Project ID: |
STP 2008(026)HES |
CSJ: |
0378-07-025 |
Description: |
WIDEN PAVEMENT TO 24' |
Handling Code: |
|
Limits From: |
LP 456 IN S JACKSONVILLE, S |
Fund Cat: |
8 |
Limits To: |
FM 1910 |
Estimate: |
$2,050,307 |
Length: |
5.7 Miles |
Actual: |
$1,662,866 |
|
Back...
|
Totals for 0378-07-025 |
Length: |
5.7 Miles |
Estimate: |
$2,050,307 |
Actual: |
$1,662,866 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|