Detail Letting Schedule for Cameron County (FY 2008)
Detail Letting Schedule for Cameron County (FY 2008) | ||||
Last Update: Monday, February 2, 2009 |
Cameron County (FY 2008) |
CCSJ: 0684-01-046 | |||
District: | Pharr | Let Date: | SEP 2007 |
Highway: | FM 511 | Let Status: | Actual |
Project ID: | NH 2008(020) | CSJ: | 0684-01-046 |
Description: | WIDEN TO 4 LANE DIVIDED | Handling Code: |
|
Limits From: | US 77/83 | Fund Cat: | 10 |
Limits To: | FM 3248 | Estimate: | $39,280,228 |
Length: | 7.3 Miles | Actual: | $32,444,671 |
District: | Pharr | Let Date: | SEP 2007 |
Highway: | FM 511 | Let Status: | Actual |
Project ID: | STP 2008(021)RGS | CSJ: | 0684-01-057 |
Description: | CONSTRUCT GRADE SEPARATION OVER RAILROAD | Handling Code: |
|
Limits From: | @ UPRR WEST OF FM 1847 | Fund Cat: | 6 |
Limits To: | . | Estimate: | $5,353,978 |
Length: | 0.4 Miles | Actual: | $4,578,394 |
District: | Pharr | Let Date: | SEP 2007 |
Highway: | FM 511 | Let Status: | Actual |
Project ID: | NH 2008(020) | CSJ: | 0684-01-063 |
Description: | WIDEN TO 4 LANE DIVIDED | Handling Code: |
|
Limits From: | .874 MI E OF FM 3248 | Fund Cat: | 3 |
Limits To: | SH 48 | Estimate: | $9,365,573 |
Length: | 2.0 Miles | Actual: | $7,127,346 |
Back... |
Totals for 0684-01-046 | ||
---|---|---|---|
Length: | 9.7 Miles | ||
Estimate: | $53,999,779 | ||
Actual: | $44,150,411 | ||
CCSJ: 0872-03-009 | |||
District: | Pharr | Let Date: | JAN 2008 |
Highway: | FM 733 | Let Status: | Actual |
Project ID: | C 872-3-9 | CSJ: | 0872-03-009 |
Description: | RESTORE AND REHABILITATE PAVEMENT AND WIDEN | Handling Code: |
|
Limits From: | US 83 NORTH 2.8 MI | Fund Cat: | 1 |
Limits To: | END OF STATE MAINTENANCE | Estimate: | $1,711,237 |
Length: | 2.7 Miles | Actual: | $1,351,213 |
Back... |
Totals for 0872-03-009 | ||
Length: | 2.7 Miles | ||
Estimate: | $1,711,237 | ||
Actual: | $1,351,213 | ||
CCSJ: 0921-06-159 | |||
District: | Pharr | Let Date: | MAY 2008 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2002(178)TE | CSJ: | 0921-06-159 |
Description: | CONSTRUCT HEART OF HARLINGEN PEDESTRIAN LINKAGE PROJECT | Handling Code: |
NC |
Limits From: | 13TH STREET TO "F" STREET AND | Fund Cat: | 9 |
Limits To: | JACKSON ST. TO PIERCE ST. | Estimate: | $1,077,505 |
Length: | 0.0 Miles | Actual: | $1,182,791 |
Back... |
Totals for 0921-06-159 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,077,505 | ||
Actual: | $1,182,791 | ||
CCSJ: 1140-02-032 | |||
District: | Pharr | Let Date: | OCT 2007 |
Highway: | FM 802 | Let Status: | Actual |
Project ID: | NH 2008(077) | CSJ: | 1140-02-032 |
Description: | WIDEN TO 6 LANE DIVIDED | Handling Code: |
|
Limits From: | US 77/83 E | Fund Cat: | 11 |
Limits To: | FM 1847 | Estimate: | $6,148,300 |
Length: | 1.2 Miles | Actual: | $6,467,572 |
District: | Pharr | Let Date: | OCT 2007 |
Highway: | FM 802 | Let Status: | Actual |
Project ID: | NH 2008(077) | CSJ: | 1140-02-033 |
Description: | LANDSCAPE IMPROVEMENTS | Handling Code: |
|
Limits From: | US 77/83 E | Fund Cat: | 10 |
Limits To: | FM 1847 | Estimate: | $234,655 |
Length: | 1.2 Miles | Actual: | $208,579 |
Back... |
Totals for 1140-02-032 | ||
Length: | 2.4 Miles | ||
Estimate: | $6,382,955 | ||
Actual: | $6,676,151 | ||
CCSJ: 1801-01-042 | |||
District: | Pharr | Let Date: | JAN 2008 |
Highway: | FM 1847 | Let Status: | Actual |
Project ID: | STP 2008(022) | CSJ: | 1801-01-041 |
Description: | WIDEN TO 4 LANE DIVIDED | Handling Code: |
|
Limits From: | FM 511, NORTH | Fund Cat: | 1 |
Limits To: | SH 100 | Estimate: | $9,055,670 |
Length: | 3.9 Miles | Actual: | $7,477,095 |
District: | Pharr | Let Date: | JAN 2008 |
Highway: | FM 1847 | Let Status: | Actual |
Project ID: | STP 2008(063) | CSJ: | 1801-01-042 |
Description: | WIDEN TO 4 LANE DIVIDED | Handling Code: |
|
Limits From: | SH 100 | Fund Cat: | 11 |
Limits To: | 0.14 MI N OF HENDERSON ROAD | Estimate: | $3,360,803 |
Length: | 1.1 Miles | Actual: | $3,102,708 |
Back... |
Totals for 1801-01-042 | ||
Length: | 5.0 Miles | ||
Estimate: | $12,416,473 | ||
Actual: | $10,579,803 |
|
|